MISC ACTIONS | | | 10/16/2019 | | DONE |
|
|
|
Recalculated plan check fees for entire project for permits BLD17-03885, 4409, 4410, 4411, 4413, 4415, 4417, 4418, 4419, 4420, 4422, 4423, 4424, 4425, 4426, 4427, 4428, 4429. Overall final plan check fee put on BLD17-03885, see calculation worksheet attached to that permit.
|
Third Notice | | 9/23/2019 | 10/14/2019 | | DONE |
|
|
|
This permit finaled on the web by Jackie Phelps
|
Second Notice | | 8/18/2019 | 9/18/2019 | | DONE |
|
|
|
mailed 9-19-19
|
First Notice | | 7/27/2019 | 8/8/2019 | | DONE |
|
|
|
mailed 8-9-19
|
Print Occupancy Form | | | 7/17/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 7/17/2019 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 7/12/2019 | 7/12/2019 | 7/12/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 7/8/2019 | 7/8/2019 | 7/9/2019 | P | PASS |
Dave Hannah
|
|
|
FInal for Occ viewing structures Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
FIRE-Final Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
FIre final for Viewing structures Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
Elevation Cert Rec'd-Final | | | 3/6/2019 | | DONE |
|
|
|
Recieved Final Elevation Certificate. Project is approved for occupancy for Floodplain. Jason Taylor ###-####
|
Elevation Cert Rec'd-Midconst | | | 2/25/2019 | | DONE |
|
|
|
Second Elevation Certificate recieved/approved. Jason Taylor ###-####
|
Issue PAID IN FULL permit | | | 4/23/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/23/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/20/2018 | | DONE |
|
|
|
met
|
Plan assigned to (CDM) | 12/5/2017 | 12/5/2017 | 4/19/2018 | | PASS |
Carl D Madsen
|
|
|
Zoo Boise
|
Routing PW Drainage | 4/19/2018 | | 4/19/2018 | | PASS |
Brian Murphy
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2018 | | DONE |
|
|
|
|
Routing PW Sewer Design | 4/19/2018 | | 4/19/2018 | | PASS |
Mike Sheppard
|
|
|
|
Routing - PLAN CHECK | 3/15/2018 | | 4/19/2018 | | PASS |
Carl D Madsen
|
|
|
|
Elevation Cert Rec'd-Prelim | | | 4/4/2018 | | DONE |
|
|
|
|
Routing PW Flood Plain | 4/4/2018 | | 4/4/2018 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor ###-####.
|
Routing - PLANNING | 3/15/2018 | | 3/16/2018 | | PASS |
David Moser
|
|
|
|
Routing - PLAN CHECK | 1/20/2018 | | 3/15/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 1/20/2018 | | 3/15/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Flood Plain | 2/2/2018 | | 2/2/2018 | | FAIL |
Jason C. Taylor
|
|
|
Elevation Certificate Needed, elevations need to be placed on site plan, foundation plan, and these cross section plans. Jason Taylor ###-####
|
Routing - PLANNING | 1/20/2018 | | 1/24/2018 | | FAIL |
David Moser
|
|
|
Need to submit Floodplain Development application
|
Route to Impact Fee Review | 1/5/2018 | 1/8/2018 | 1/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/5/2018 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/5/2017 | | 1/5/2018 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 12/5/2017 | | 1/5/2018 | | FAIL |
David Moser
|
|
|
need a Floodplain Review Application
|
Routing - Erosion and Sediment | 12/5/2017 | | 1/5/2018 | | PASS |
Andy J. Long
|
|
|
|
Routing Off Site - STRUCTURAL | 12/5/2017 | | 1/5/2018 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Environmental | 12/6/2017 | | 1/4/2018 | | PASS |
Terry Alber
|
|
|
|
Routing PW Sewer Design | 12/6/2017 | | 12/22/2017 | | PASS |
Mike Sheppard
|
|
|
|
Routing PW Flood Plain | 12/6/2017 | | 12/18/2017 | | FAIL |
Jason C. Taylor
|
|
|
Need project to comply with floodplain ordiance and new BFE from FEMA maps. Please resubmit revised drawings showing how project will comply with ordinance. Jason Taylor ###-####
|
Routing - FIRE | 12/5/2017 | 12/5/2017 | 12/15/2017 | | PASS |
Scott Arellano
|
|
|
See attached Fire Review comments under BLD17-03885.
|
Routing - PUBLIC WORKS | 12/5/2017 | | 12/13/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 12/5/2017 | | 12/6/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Solid Waste | 12/6/2017 | | 12/6/2017 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Street Lights | 12/6/2017 | | 12/6/2017 | | PASS |
Tom Marshall
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/4/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/4/2017 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/4/2017 | | DONE |
|
|
|
intake fees paid to BLD17-03885
|
Routing PW Drainage | 12/6/2017 | | 1/2/2017 | | FAIL |
Brian Murphy
|
|
|
|
Application received | | 12/5/2017 | | | |
|
|
|
|