MISC ACTIONS | | | 10/16/2019 | | DONE |
|
|
|
Recalculated plan check fees for entire project for permits BLD17-03885, 4409, 4410, 4411, 4413, 4415, 4417, 4418, 4419, 4420, 4422, 4423, 4424, 4425, 4426, 4427, 4428, 4429. Overall final plan check fee put on BLD17-03885, see calculation worksheet attached to that permit.
|
Third Notice | | 9/23/2019 | 10/14/2019 | | DONE |
|
|
|
This permit finaled on the web by Jackie Phelps
|
Second Notice | | 8/16/2019 | 9/18/2019 | | DONE |
|
|
|
mailed 9-19-19
|
First Notice | | 8/1/2019 | 8/6/2019 | | DONE |
|
|
|
mailed 8-7-19
|
Print Occupancy Form | | | 7/15/2019 | | DONE |
|
|
|
|
Permanent Occupancy | | | 7/15/2019 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 7/12/2019 | 7/12/2019 | 7/12/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 7/8/2019 | 7/8/2019 | 7/11/2019 | P | PASS |
Dave Hannah
|
|
|
Mixed Aviary BLD final for Occupancy Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
Elevation Cert Rec'd-Final | | | 7/9/2019 | | DONE |
|
|
|
The final Elevation Certificate has been received and is acceptable. Final occupancy may be approved by the building department. Jason Taylor ###-####
|
FIRE-Final Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
Mixed Aviary FIre life safety Final, Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Wall cover | 3/13/2019 | 3/18/2019 | 3/18/2019 | P | PASS |
Dave Hannah
|
|
|
Approval to cover ceiling in D6 prior to spray foam and Drywall. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
Elevation Cert Rec'd-Midconst | | | 2/21/2019 | | DONE |
|
|
|
Elevation Certificate #2 recieved/approved. Jason Taylor ###-####
|
BLD-Framing/Rough-in | 2/7/2019 | 2/8/2019 | 2/8/2019 | P | PASS |
Dave Hannah
|
|
|
Rody Phone #: ###-####
|
BLD-Energy code compliance | 10/26/2018 | 10/29/2018 | 10/30/2018 | P | CANC |
Dave Hannah
|
|
|
Inspect spray foam insulation prior to hanging drywall Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Wall cover | 10/26/2018 | 10/29/2018 | 10/30/2018 | P | PASS |
Dave Hannah
|
|
|
Inspect to cover ceiling and soffits at D5 Electrical inspections schedule for A.M. Phone #: ###-#### Inspection requested via web by Brandon Reynolds
|
BLD-Foundation | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | PEND |
Dave Hannah
|
|
|
Building D6 Stem wall rebar. Mti will be on site as well Phone #: ###-#### Inspection requested via web by Brandon Reynolds ok after spec inspection oks
|
BLD-Footing | 10/11/2018 | 10/12/2018 | 10/12/2018 | A | PASS |
Jim Sly
|
|
|
Need rebar inspection for footing. Please call ahead in the morning. Thanks! Phone #: ###-#### Inspection requested via web by Justin Palm OK ....pending MTI special inspection, tests and approvals.
|
Issue PAID IN FULL permit | | | 4/23/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/23/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/20/2018 | | DONE |
|
|
|
met
|
Plan assigned to (CDM) | 12/6/2017 | 12/6/2017 | 4/19/2018 | | PASS |
Carl D Madsen
|
|
|
Zoo Boise
|
Routing PW Drainage | 4/19/2018 | | 4/19/2018 | | PASS |
Brian Murphy
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2018 | | DONE |
|
|
|
|
Routing PW Sewer Design | 4/19/2018 | | 4/19/2018 | | PASS |
Mike Sheppard
|
|
|
|
Routing - PLAN CHECK | 3/15/2018 | | 4/19/2018 | | PASS |
Carl D Madsen
|
|
|
|
Elevation Cert Rec'd-Prelim | | | 4/4/2018 | | DONE |
|
|
|
|
Routing PW Flood Plain | 4/4/2018 | | 4/4/2018 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor ###-####.
|
Routing - PLANNING | 3/15/2018 | | 3/16/2018 | | PASS |
David Moser
|
|
|
|
Routing - PLAN CHECK | 1/20/2018 | | 3/15/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 1/20/2018 | | 3/15/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Flood Plain | 2/2/2018 | | 2/2/2018 | | PASS |
Jason C. Taylor
|
|
|
Need elevation of bottom of vent. cannot be more that 12" above GRADE not floor. Jason Taylor ###-####
Elevation Certificate Needed, elevations need to be placed on site plan, foundation plan, and these cross section plans. Jason Taylor ###-####
|
Routing - PLANNING | 1/20/2018 | | 1/24/2018 | | FAIL |
David Moser
|
|
|
|
Route to Impact Fee Review | 1/5/2018 | 1/8/2018 | 1/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/5/2018 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/6/2017 | | 1/5/2018 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 12/6/2017 | | 1/5/2018 | | FAIL |
David Moser
|
|
|
need a Floodplain Review Application
|
Routing - Erosion and Sediment | 12/6/2017 | | 1/5/2018 | | PASS |
Andy J. Long
|
|
|
|
Routing Off Site - STRUCTURAL | 12/6/2017 | | 1/5/2018 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Environmental | 12/6/2017 | | 1/4/2018 | | PASS |
Terry Alber
|
|
|
|
Routing PW Drainage | 12/6/2017 | | 1/2/2018 | | FAIL |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 12/6/2017 | | 12/22/2017 | | FAIL |
Mike Sheppard
|
|
|
|
Routing PW Flood Plain | 12/6/2017 | | 12/18/2017 | | FAIL |
Jason C. Taylor
|
|
|
Need project to comply with floodplain ordiance and new BFE from FEMA maps. Please resubmit revised drawings showing how project will comply with ordinance. Jason Taylor ###-####
|
Routing - FIRE | 12/6/2017 | 12/6/2017 | 12/15/2017 | | PASS |
Scott Arellano
|
|
|
See attached Fire Review comments under BLD17-03885.
|
Routing - PUBLIC WORKS | 12/6/2017 | | 12/13/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLUMBING | 12/6/2017 | | 12/11/2017 | | PASS |
Bill VanDegrift
|
|
|
additional cross connection protection may be required
|
Routing - Addressing | 12/6/2017 | | 12/6/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 12/6/2017 | | 12/6/2017 | | PASS |
Troy James
|
|
|
|
Routing PW Solid Waste | 12/6/2017 | | 12/6/2017 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Street Lights | 12/6/2017 | | 12/6/2017 | | PASS |
Tom Marshall
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/4/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/4/2017 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/4/2017 | | DONE |
|
|
|
intake fees paid to BLD17-03885
|
Application received | | 12/5/2017 | | | |
|
|
|
|