BLD-Final | 10/30/2018 | 10/31/2018 | 10/31/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart, late am
|
DOC - Permit Finaled | 10/31/2018 | 10/31/2018 | 10/31/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 10/29/2018 | 10/30/2018 | 10/30/2018 | A | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Final | 10/26/2018 | 10/29/2018 | 10/29/2018 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Blower Door Test Results | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart, 3.48
|
BLD-Final | 10/26/2018 | 10/26/2018 | 10/26/2018 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart,, ok after installing a protection post in the garage in front of gas appliances
|
BLD-Energy code compliance | 8/21/2018 | 8/22/2018 | 8/22/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Framing/Rough-in | 8/20/2018 | 8/20/2018 | 8/20/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
BLD-Wall Bracing | 7/23/2018 | 7/24/2018 | 7/24/2018 | A | PASS |
Tony Young
|
|
|
Gorge Phone #: ###-####
|
BLD-Foundation | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Tony Young
|
|
|
wall- Ryan Phone #: ###-####
|
BLD-Footing | 1/11/2018 | 1/11/2018 | 1/11/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 1/4/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/4/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 12/29/2017 | | |
|
|
|
|
Plan assigned to (M_H) | 12/18/2017 | | 12/29/2017 | | DONE |
Michael Hanson
|
|
|
12/20 sfd L1 ePlan - 1st review completed. RTA - structural deficiencies. MDH
|
Routing - PLAN CHECK | 12/19/2017 | | 12/29/2017 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/29/2017 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/29/2017 | | DONE |
|
|
|
met
|
Plan Reviewer's activity | | | 12/19/2017 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 12/19/2017 | | FAIL |
Michael Hanson
|
|
|
RTA - structural deficiencies. MDH
|
Routing - PLAN CHECK | 12/7/2017 | | 12/19/2017 | | FAIL |
Michael Hanson
|
|
|
RTA - structural deficiencies. MDH
|
Plan assigned to (BJM) | 12/7/2017 | 12/7/2017 | 12/18/2017 | | DEFR |
Brian McGowan
|
|
|
12/20 sfd L1 ePlan
|
Route to Impact Fee Review | 12/7/2017 | 12/10/2017 | 12/8/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 12/7/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/7/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/7/2017 | | PASS |
|
|
|
|
Routing - MECHANICAL | 12/7/2017 | | 12/7/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/7/2017 | | 12/7/2017 | | FAIL |
Jeff Lowe
|
|
|
it would appear that the dwelling proposed encroaches into the ACHD easement. the plan must show that the home does not encroach into the easement
|
Routing - Addressing | 12/7/2017 | | 12/7/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/7/2017 | | 12/7/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 12/7/2017 | | 12/7/2017 | | PASS |
Jeff Lowe
|
|
|
version 2 of plan approved - building shown outside of easement
|
Application received | | | 12/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 6 2017 11:02AM
|