BLD-Final | 3/25/2019 | 3/28/2019 | 3/28/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 3/28/2019 | 3/28/2019 | 3/28/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 3/25/2019 | 3/28/2019 | 3/28/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.44
|
BLD-Energy code compliance | 1/21/2019 | 1/23/2019 | 1/23/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 1/17/2019 | 1/22/2019 | 1/22/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 12/21/2018 | 12/21/2018 | 12/21/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Conference | 9/26/2018 | 9/26/2018 | 9/26/2018 | P | DEFR |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Aging Inspection | 9/26/2018 | 9/26/2018 | 9/26/2018 | | DEFR |
Brandon Shaw
|
|
|
|
BLD-Conference | 9/25/2018 | 9/25/2018 | 9/25/2018 | P | DEFR |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Conference | 9/25/2018 | 9/25/2018 | 9/25/2018 | P | DEFR |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Aging Inspection | 9/25/2018 | 9/25/2018 | 9/25/2018 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Foundation | 5/11/2018 | 5/14/2018 | 5/14/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 5/10/2018 | 5/11/2018 | 5/11/2018 | A | PASS |
Brandon Shaw
|
|
|
Manny Phone #: ###-####
|
BLD-Footing | 5/3/2018 | 5/3/2018 | 5/3/2018 | P | CANC |
Brandon Shaw
|
|
|
Early afternoon - Edger Phone #: ###-####
|
(F) Reprint permit | | | 12/21/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 12/20/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 12/7/2017 | 12/7/2017 | 12/20/2017 | | DONE |
Brian McGowan
|
|
|
12/20 sfd L1 ePlan
|
Routing - PLAN CHECK | 12/7/2017 | | 12/20/2017 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 12/20/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 12/20/2017 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 12/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/20/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 12/7/2017 | 12/10/2017 | 12/8/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 12/7/2017 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/7/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/7/2017 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - MECHANICAL | 12/7/2017 | | 12/7/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/7/2017 | | 12/7/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 12/7/2017 | | 12/7/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/7/2017 | | 12/7/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 12/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 6 2017 11:17AM
|