First Notice | | 10/14/2018 | 11/6/2018 | | DONE |
|
|
|
mailed 11-12
|
BLD-Final | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Tony Young
|
|
|
Ken Phone #: ###-####
|
Permanent Occupancy | | | 10/4/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags, final life fire safety inspection complete.
|
BLD-Ceiling Grid Inspection | 9/4/2018 | 9/5/2018 | 9/5/2018 | A | NR |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Framing/Rough-in | 8/2/2018 | 8/2/2018 | 8/2/2018 | P | PASS |
Tony Young
|
|
|
Please call ahead // Evan Phone #: ###-####,, interior wallsok
|
BLD-Energy code compliance | 6/25/2018 | 6/25/2018 | 6/25/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 6/21/2018 | 6/22/2018 | 6/22/2018 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Palmer,, ok to insulate,, no trades will be covered
|
BLD-Other | 6/21/2018 | 6/22/2018 | 6/22/2018 | A | PASS |
Tony Young
|
|
|
Anchor bolt and interior wall cover Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 6/20/2018 | 6/21/2018 | 6/21/2018 | P | NR |
Tony Young
|
|
|
Anchor bolt and interior wall cover Phone #: ###-#### Inspection requested via web by Chris Palmer
|
BLD-Framing/Rough-in | 6/18/2018 | 6/19/2018 | 6/19/2018 | P | PART |
Tony Young
|
|
|
Roof nailing requested Phone #: ###-#### Inspection requested via web by Chris Palmer,, roof nailing ok after a couple fixes
|
BLD-Footing | 6/13/2018 | 6/14/2018 | 6/14/2018 | P | PART |
Jim Sly
|
|
|
Trellis footing pour scheduled for 1:30 pm. MTI scheduled for rebar and concrete as well. Phone #: ###-#### Inspection requested via web by Chris Palmer OK pending MTI special inspection, tests and approvals.
|
Telephone call | | | 5/29/2018 | | DONE |
|
|
|
Spoke with Anna at ESI informing her that this permit is going to expire in 7 days and they may either pay and pick up the permit or if not ready send in a request for 180 days
|
Issue PAID IN FULL permit | | | 5/29/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/29/2018 | | DONE |
|
|
|
|
Expiration Notice | 5/7/2018 | 5/28/2018 | 5/7/2018 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (JG) | 2/8/2018 | 2/8/2018 | 4/17/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 2/21 Starbucks TI Level 3 ePlan pend planning
|
Routing - PLAN CHECK | 4/17/2018 | | 4/17/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLANNING | 4/17/2018 | | 4/17/2018 | | PASS |
Leon Letson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/17/2018 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED VALUE
|
Routing - PLUMBING | 4/7/2018 | | 4/9/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - PLAN CHECK | 4/3/2018 | | 4/7/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLANNING | 4/3/2018 | | 4/4/2018 | | FAIL |
Leon Letson
|
|
|
The City has not approved the land division for this site. Please remove the property line from the site plan or submit a Record of Survey for Minor Land Division.
|
Routing PW Solid Waste | 4/3/2018 | | 4/3/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Design Review | 4/3/2018 | | 4/3/2018 | | PASS |
Andrea Tuning
|
|
|
|
Route to Impact Fee Review | 2/27/2018 | 3/2/2018 | 2/28/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing PW Solid Waste | 2/8/2018 | | 2/27/2018 | | FAIL |
Evan Carpenter
|
|
|
The solid waste enclosure location does not match the approved site plan from BLD18-00032. Resubmit with an updated site plan showing the approved enclosure location.
|
1st review completed | | | 2/27/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Sewer Design | 2/8/2018 | | 2/26/2018 | | PASS |
Mike Sheppard
|
|
|
|
Routing - PLAN CHECK | 2/8/2018 | | 2/23/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 2/8/2018 | | 2/15/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - FIRE | 2/8/2018 | 2/8/2018 | 2/14/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Street Lights | 2/8/2018 | | 2/13/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLANNING | 2/8/2018 | | 2/13/2018 | | FAIL |
Leon Letson
|
|
|
landscape plan required
|
Routing - MECHANICAL | 2/8/2018 | | 2/9/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 2/8/2018 | | 2/9/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC and see redlines.
|
Routing - Design Review | 2/8/2018 | | 2/8/2018 | | FAIL |
Andrea Tuning
|
|
|
Must submit site and landscape plans.
|
Routing - Addressing | 2/8/2018 | | 2/8/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/8/2018 | | 2/8/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 2/8/2018 | | 2/8/2018 | | PASS |
Michael Zawacki
|
|
|
Building construction covered by ESC18-00014
|
Intake Approval | | | 2/8/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie accepted pre screen
|
Routing PW Drainage | 2/8/2018 | | 2/8/2018 | | PASS |
Brian Murphy
|
|
|
|
Plan Reviewer's activity | | | 1/24/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
I had to fail the pre screen after Julie had accepted. The building has not been submitted and we can not route the TI until the building comes in. I have sent the task back to the applicant to submit once the building is submitted.
|
Intake Approval | | | 12/11/2017 | | FAIL |
Julie Romig
|
|
|
1. Fire flow at hydrants letter.
2. Central District Health stamped approved plans.
|
Application received | | | 12/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 7 2017 7:35AM
|
Intake Approval | | | 12/7/2017 | | FAIL |
Julie Romig
|
|
|
Need: 1. Completed Form 520 Submittal Checklist, completed and with any additional information as required by checklist, which includes the following items below.
2. Completed Form 304 Design Professional Form.
3. Fire flow at hydrants letter.
4. Central District Health stamped approved plans.
5. Planning and Zoning letters of approval.
6. COMcheck forms for lighting, mechanical, and plumbing.
|