Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD17-04479
StatusFinaled
Name BARKER CONTRACTING INC
Site Address 3419 N COLE RD
Project NameCSL Plasma
Customer NumberBLD18-00076 NONSTRUCT DEMO
ePlanReviewNo
Description
(CSL PLASMA – BLOOD PLASMA COLLECTION FACILITY) (CZC17-00210) The fire sprinkler system is used for building area increase and for fire area. Interior nonstructural demolition work was done under permit BLD18-00076. To completely renovate a 11,653 square foot tenant space for a blood plasma collection facility where no one will be incapable of self-preservation. Work is to include a 400 square foot recessed concrete slab on grade to accommodate the floor thickness of a new walk-in freezer; concrete floor patches at plumbing trenches; concrete footings, steel columns, and a steel beam to redirect roof gravity loads where a column will be removed; structural upgrades to the roof structure to support new roof top HVAC units; exterior concrete landings, ramps, rails, and awnings at the back exterior doors; new concrete stem walls where existing exterior doors will be removed in the storefront; interior nonbearing walls; suspended acoustical ceilings; gypsum board soffits and bulkheads; 2 multi-user toilet rooms accessible to the disabled for the public; 2 multi-user toilet rooms accessible to the disabled for employees; interior windows; interior doors; double-acting gates; service counters; new storefront doors and windows; millwork; equipment; furniture, and interior finishes. Special Inspection is required for soils, concrete, masonry, welding, and epoxy anchors and other anchors post-installed in hardened concrete. The West awnings are allowed to be deferred submittal items. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 (including quick-response heads installed in light-hazard areas) and the partial fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/20/20187/17/2018 DONE
This permit finaled on the web by Alicia Simmons
First Notice 6/17/20187/10/2018 DONE
mailed 7-11-18
Plan Reviewer's activity  6/8/2018 DONE
Drawings taken to Records
BLD-Final6/6/20186/7/20186/7/2018PPASS
DetailsJim Sly
Dave Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection6/6/20186/7/20186/7/2018APASS
DetailsTroy Cobbley
life safety passed

Dave Phone #: ###-####
Permanent Occupancy  6/7/2018 DONE
BLD-Final6/5/20186/6/20186/6/2018PNR
DetailsJim Sly
Dave Barker Phone #: ###-####
Need FIR18-00379 Final.
FIRE-Final Inspection6/5/20186/6/20186/6/2018AFAIL
DetailsTroy Cobbley
Life safety will be ok to pass when the two emergency lights are repaired and the project related fire alrm permit is finaled.

Dave Barker Phone #: ###-####
BLD-Final6/1/20186/1/20186/1/2018PNR
DetailsJim Sly
Dave Phone #: ###-####
Need all fire finals and MEC 18-00890
FIRE-Final Inspection6/1/20186/1/20186/1/2018PFAIL
DetailsTroy Cobbley
Need sign offs on the project related fire alarm and fire sprinkler permits. Need the three missing exit discharge lights installed and tested. Need the emergency lights marked on the city approved plans repaired and tesed

Dave Phone #: 208-###-####
BLD-Ceiling Grid Inspection5/17/20185/17/20185/17/2018PPASS
DetailsJim Sly
Dave Phone #: ###-####
BLD-Framing/Rough-in5/3/20185/3/20185/4/2018PPASS
DetailsJim Sly
Dave Phone #: ###-####
BLD-Framing/Rough-in3/19/20183/19/20183/19/2018PPASS
DetailsJim Sly
Dave Phone #: ###-####
BLD-Framing/Rough-in3/12/20183/13/20183/13/2018APART
DetailsJim Sly
Dave-partial-room #er''s-rooms 137, 143, 144, 134, 133, 110, 141, 142, 107, 104, 102 north wall Phone #: ###-####
BLD-Concrete3/1/20183/2/20183/2/2018APASS
DetailsJim Sly
pouring at 9am- Dave Phone #: ###-####
BLD-Concrete3/1/20183/1/20183/2/2018PDONE
DetailsJim Sly
Dave Phone #: ###-####
BLD-Foundation2/27/20182/27/20182/27/2018PCANC
DetailsJim Sly
Stem wall for garage - Jeremy Phone #: ###-####
BLD-Conference2/27/20182/27/20182/27/2018PDONE
DetailsJim Sly
Please call if after 3:30 - Dave Phone #: ###-####
Issue PAID IN FULL permit  2/9/2018 DONE
Print Occupancy Form  2/9/2018 DONE
OVERRIDE  2/8/2018  
OVERRIDE  2/8/2018  
Plan assigned to (CJW)12/8/201712/8/20172/8/2018 PASS
DetailsCarl Westfall
(1st done) (Dec 28 - 15 days) (55 sheets) paper CSL Plasma
Print Occupancy Form  2/8/2018 DONE
Permit Ready to Issue  2/8/2018 DONE
DetailsChristina Prado
Still need RP //leg 2-8-18
Called Tommy to advise permit is ready for issuance pending revised cert of value(met) & RP
PLANS/APPL TAKEN TO FRONT DESK  2/8/2018 DONE
Print Occupancy Form  2/8/2018 DONE
Permit Ready to Issue  2/8/2018 DONE
NEED
RP
Rev Cert of Val
Routing - Design Review2/7/2018 2/7/2018 PASS
DetailsAndrea Tuning
Plan Reviewer's activity  2/7/2018 DONE
Sent an Email to the applicant asking for 2 sets of revised structural drawings
Plan resubmittals received  2/7/2018 DONE
two copies of sheets S100, S101, S102 and S103. taken to Carl W
Routing - Erosion and Sediment2/7/2018 2/7/2018 PASS
DetailsAndy J. Long
Routing Off Site - STRUCTURAL2/5/2018 2/6/2018 PASS
DetailsCarl Westfall
Tiffany Curtis (AHJ)
Telephone call  2/5/2018 DONE
Called the applicant and asked for additional copies of the resubmittals.
Telephone call  2/5/2018 DONE
called couriers for pick up for outside engineering review
Routing - PLAN CHECK2/2/2018 2/5/2018 PASS
DetailsCarl Westfall
Pending structural
Plan resubmittals received  2/2/2018 DONE
received (dropped off at desk) response, one copy of structural calcs, one copy of plan sheet S100, S101, S102, S103; taken to Carl Westfall
Route to Impact Fee Review2/1/20182/4/20182/1/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE1/27/20181/29/20181/29/2018 PASS
DetailsErika Akin
Attached comments to case and plans
1st review completed  1/29/2018 DONE
Plan resubmittals requested  1/27/2018 DONE
Routing - PLAN CHECK12/19/2017 1/27/2018 PASS
DetailsCarl Westfall
Pending structural - Plan review report Emailed to applicant
Routing - MECHANICAL12/8/2017 12/19/2017 PASS
DetailsTroy James
Routing - PLUMBING12/18/2017 12/18/2017 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing Off Site - STRUCTURAL12/8/2017 12/18/2017 FAIL
DetailsCarl Westfall
Tiffany Curtis (AHJ)
Routing - Erosion and Sediment12/15/2017 12/18/2017 PASS
DetailsAndy J. Long
ESC plan waiver approved. contract out to bid, RP needs to be designated.
Routing - Design Review12/15/2017 12/15/2017 FAIL
DetailsAndrea Tuning
The applicant submitted a zoning certificate (CZC17-00210) for a change of use only. No exterior modfiications were proposed and no exterior modifications were approved. If the applicant wishes to add, remove or modify windows, doors or any portion of the exterior, a Design Review application is required.
Routing - PUBLIC WORKS12/8/2017 12/14/2017 PASS
DetailsMorgan Webb
Routing PW Environmental12/8/2017 12/14/2017 PASS
DetailsTerry Alber
No comment.
Routing PW Sewer Rating12/8/2017 12/8/2017 PASS
DetailsMorgan Webb
CONTACT WEST BOISE FOR FEES AND PERMIT
Routing - Addressing12/8/2017 12/8/2017 PASS
DetailsDoug Chausow
Plans ACCEPTED BY PLAN TECH  12/8/2017 DONE
DetailsChristina Prado
Intake Approval  12/8/2017 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  12/8/2017 DONE
DetailsChristina Prado
Pending Assignment by AJS12/8/2017 12/8/2017 DONE
DetailsAdele J Schaffeld-Griffin
Plan Reviewer's activity  12/8/2017 DONE
DetailsAdele J Schaffeld-Griffin
email sent 12/8/17
Steve,

Please make sure that you reach out to ACHD for review on this change of use/occupancy.(General Office/retail to Medical Office) If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are do please submit the documentation from ACDH as such.

You can reach ACHD at ###-####.


Thank you



Adele Schaffeld-Griffin
Assistant Building Official
Planning and Development Services
Office: ###-####
aschaffeldgriffin@cityofboise.org

Making Boise the most livable city in the country.
Application received 12/8/2017