First Notice | | 2/7/2019 | 1/28/2019 | | DONE |
|
|
|
This permit finaled on the web by Ami Ostrow
|
Letter of compliance/Occupancy | | | 1/28/2019 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 1/28/2019 | | DONE |
|
|
|
Passed final 1/23/19
|
BLD-Final | 1/23/2019 | 1/23/2019 | 1/23/2019 | P | PASS |
Mike Jordan
|
|
|
Please call Darius Phone #: ###-#### Inspection requested via web by Ami Ostrow. OK for perm occ.
|
FIRE-Final Inspection | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
FIRE-Final Inspection | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | FAIL |
Troy Cobbley
|
|
|
There are still sync issues with the notification devices.
Phone #: ###-#### Inspection requested via web by Ami Ostrow
|
FIRE-Alarm Testing | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | FAIL |
Troy Cobbley
|
|
|
There are still sync'ing issues with the notification devices.
Please call Darius Phone #: ###-#### Inspection requested via web by Ami Ostrow
|
FIRE-Final Inspection | 11/14/2018 | 11/14/2018 | 11/14/2018 | A | CANC |
Troy Cobbley
|
|
|
Need the project related fire alarm permit addressed prior to a fire life safety inspection
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
Telephone call | | | 7/16/2018 | | DONE |
|
|
|
called Ami-left message on her phone that she needs to call in the final bldg and fire life safety inspections to final permit out
|
BLD-Final | 5/15/2018 | 5/16/2018 | 5/16/2018 | A | PART |
Mike Jordan
|
|
|
Call Darius when on site. Phone #: ###-#### Inspection requested via web by Ami Tracy. Ok for temp occ. Will be ok for perm occ. once the fire alarm issues have been resolved.
|
FIRE-Final Inspection | 5/15/2018 | 5/16/2018 | 5/16/2018 | A | PART |
Jim Page
|
|
|
Partial final inspection for life fire safety complete, fire sprinkler inspection is complete, fire extinguishers are in common areas with current inspection tags, fire alarm system has sync issues that is currently being worked on. TCO is authorized for 60 days per conversation with Romeo Gervais contingent on sync issue for fire alarms is corrected.
Call Darius before coming to job site, please. Phone #: ###-#### Inspection requested via web by Ami Tracy
|
FIRE-Final Inspection | 5/15/2018 | 5/16/2018 | 5/15/2018 | A | CANC |
Troy Cobbley
|
|
|
Call Darius when on site. Phone #: ###-#### >> Inspection requested via web by Ami Tracy Inspection cancelled from web by: Ami Tracy
|
FIRE-Final Inspection | 5/11/2018 | 5/11/2018 | 5/11/2018 | A | FAIL |
Troy Cobbley
|
|
|
Still need to address the project related fire alarm permit
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Ceiling Grid Inspection | 4/25/2018 | 4/26/2018 | 4/26/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
FIRE-Conference | 4/9/2018 | 4/10/2018 | 4/10/2018 | A | DONE |
Troy Cobbley
|
|
|
We spoke of the sync requirements as per NFPA 72 for the syncronization of the audio and visual fire alarm device. Specifically the new/remodel area devices with the existing/path of egress devices.
Please call Darius when on site Phone #: ###-#### Inspection requested via web by Ami Tracy
|
BLD-Final | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PART |
Mike Jordan
|
|
|
Partial final for phase I. Please call Ami when on site. Late morning Phone #: ###-#### Inspection requested via web by Ami Tracy. Ok to occupy phase 1. Contractor to replace round knobs to lever hardware on 2 doors.
|
FIRE-Final Inspection | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PART |
Troy Cobbley
|
|
|
Partial life safety final for phase I (CT#2 Room/Control Room) is complete. There is a sync issue with the project related fire alarm permit that will need to be addressed prior to a final sign off.
Please call Ami when on site. Phone #: ###-#### Inspection requested via web by Ami Tracy
|
BLD-Ceiling Grid Inspection | 3/27/2018 | 3/27/2018 | 3/27/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Conference | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | DONE |
Mike Jordan
|
|
|
Early if possible Phone #: ###-#### Inspection requested via web by Darius Saxton
|
BLD-Framing/Rough-in | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Darius Saxton Frame CTU ....OK.
|
Issue PAID IN FULL permit | | | 2/21/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/21/2018 | | DONE |
|
|
|
|
Plan assigned to (RMH) | 2/20/2018 | 2/20/2018 | 2/20/2018 | | DONE |
Ron Hill
|
|
|
|
Plan assigned to (JAR) | 1/16/2018 | 1/16/2018 | 2/20/2018 | | DEFR |
Julie Romig
|
|
|
02/12 - L3 SARMC CT #2
|
Routing - PLAN CHECK | 1/16/2018 | | 2/20/2018 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 2/20/2018 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/20/2018 | | DONE |
|
|
|
MET
Need
GC Form
Revise Cert of Value
|
Routing Off Site - STRUCTURAL | 1/16/2018 | | 2/20/2018 | | PASS |
Ron Hill
|
|
|
|
Routing - FIRE | 1/16/2018 | 1/16/2018 | 1/19/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Environmental | 1/17/2018 | | 1/17/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 1/16/2018 | | 1/17/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 1/16/2018 | | 1/17/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/16/2018 | | 1/17/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLUMBING | 1/16/2018 | | 1/16/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Intake Approval | | | 1/16/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Intake accepted by Julie
|
Intake Approval | | | 12/11/2017 | | FAIL |
Julie Romig
|
|
|
Need:
1. Site specific fire flow at hydrants letter.
2. Provide door schedule for existing egress doors from area of work.
3. Provide structural calculations and details for the attachment of the new CT machine.
4. Form #310 if applicable (for example, if special inspections are required for any attachments).
|
Application received | | | 12/8/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 8 2017 11:04AM
|