BLD-Aging Inspection | 8/3/2018 | 8/3/2018 | 8/3/2018 | | PASS |
Tony Young
|
|
|
|
BLD-Footing | 3/21/2018 | 3/22/2018 | 3/22/2018 | A | PASS |
Tony Young
|
|
|
Ed Phone #: ###-####
|
BLD-Foundation | 3/14/2018 | 3/15/2018 | 3/15/2018 | A | PART |
Tony Young
|
|
|
concrete rebar // ed Phone #: ###-####, 2nd phase of 5 ok
|
BLD-Foundation | 3/6/2018 | 3/7/2018 | 3/7/2018 | A | PASS |
Tony Young
|
|
|
Rebar // Ed Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/12/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/12/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 2/8/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 1/11/2018 | 1/11/2018 | 2/8/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) (Jan 31 - 15 days) (8 sheets) Kensington Apartments Carports
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/8/2018 | | DONE |
Christina Prado
|
|
|
Need:
GC form - met
Revised Value - Applicant GC, not needed
Email permits to James McLaughlin
|
Plan resubmittals received | | | 2/7/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/7/2018 | | 2/7/2018 | | PASS |
Carl Westfall
|
|
|
Pending structural approval
|
Routing Off Site - STRUCTURAL | 2/7/2018 | | 2/7/2018 | | PASS |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Route to Impact Fee Review | 1/29/2018 | 2/1/2018 | 1/30/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/29/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/29/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/11/2018 | | 1/29/2018 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Plan Reviewer's activity | | | 1/26/2018 | | DONE |
|
|
|
Emailed James telling him I will try to have it done by Feb 14
|
Routing - FIRE | 1/11/2018 | 1/11/2018 | 1/17/2018 | | PASS |
Scott Arellano
|
|
|
New construction (Carports Only); no comments attached. Inspector to field verify no encroachment of carports into the required FD access
|
Routing Off Site - STRUCTURAL | 1/11/2018 | | 1/16/2018 | | FAIL |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing - Design Review | 1/11/2018 | | 1/12/2018 | | PASS |
Sarah Schafer
|
|
|
Approved.
|
Routing - PLANNING | 1/11/2018 | | 1/12/2018 | | PASS |
David Moser
|
|
|
|
Routing - Addressing | 1/11/2018 | | 1/11/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/11/2018 | | 1/11/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 1/11/2018 | | 1/11/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved.
|
Intake Approval | | | 1/11/2018 | | PASS |
|
|
|
|
Routing PW Drainage | 1/11/2018 | | 1/11/2018 | | PASS |
Jason C. Taylor
|
|
|
|
Plan Reviewer's activity | | | 1/10/2018 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 12/22/2017 | | FAIL |
|
|
|
(12-22-17) Please refer to the circled items in the plan intake checklist. Please resolve each item as directed. CJW
|
Application received | | | 12/11/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 11 2017 10:26AM
|