Third Notice | | 4/15/2018 | 4/13/2018 | | DONE |
|
|
|
This permit finaled on the web by Scott Simons
|
Second Notice | | 3/24/2018 | 4/10/2018 | | DONE |
|
|
|
mailed 4-11-18
|
First Notice | 2/21/2018 | 2/21/2018 | 3/14/2018 | | DONE |
Jim Sly
|
|
|
mailed 3-16-18
|
BLD-Final | 2/20/2018 | 2/21/2018 | 2/21/2018 | P | PASS |
Jim Sly
|
|
|
Hi! City approved plans and approved revisions are on site, any questions please call. Thanks! Phone #: ###-#### Inspection requested via web by Scott Simons
|
DOC - Permit Finaled | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 2/19/2018 | 2/20/2018 | 2/20/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-#### Inspection requested via web by Scott Simons
|
FIRE-Final Inspection | 2/15/2018 | 2/15/2018 | 2/15/2018 | A | FAIL |
Troy Cobbley
|
|
|
All corrections have been made except the door issue still needs resolved.
Phone #: ###-#### Inspection requested via web by Scott Simons
|
FIRE-Final Inspection | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | FAIL |
Troy Cobbley
|
|
|
Provide city approved plans and small docments, cover arrow on the exit sing near the main exit, provide a fire extinguisher near the south end of the building. Possibly speak with plans review about the door that has been disabled.
Phone #: ###-#### Inspection requested via web by Scott Simons
|
BLD-Final | 2/12/2018 | 2/13/2018 | 2/13/2018 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Simons Need Fire Final.
|
BLD-Framing/Rough-in | 1/22/2018 | 1/23/2018 | 1/23/2018 | A | PASS |
Jim Sly
|
|
|
Any Issues or questions please call...Thanks Phone #: ###-#### Inspection requested via web by Scott Simons
|
Print Occupancy Form | | | 1/19/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/19/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/16/2018 | | DONE |
|
|
|
NEED
GC - met
Rev Cert of Val - met
|
Plan assigned to (JG) | 12/20/2017 | 12/20/2017 | 1/13/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 1/02 L2 Amherst Madison ePlan
|
Routing - PLAN CHECK | 1/11/2018 | | 1/13/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/13/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/4/2018 | 1/7/2018 | 1/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 12/20/2017 | | 1/4/2018 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 1/4/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 12/20/2017 | | 12/20/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/20/2017 | | 12/20/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 12/20/2017 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 12/12/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 12 2017 10:25AM
|