Print Statement | | | 9/21/2018 | | DONE |
|
|
|
|
First Notice | | 8/12/2018 | 9/6/2018 | | DONE |
|
|
|
mailed 9-10-18
|
Permanent Occupancy | | | 8/2/2018 | | DONE |
|
|
|
|
BLD-Final | 8/1/2018 | 8/1/2018 | 8/1/2018 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Andrew Clark
|
FIRE-Final Inspection | 7/31/2018 | 8/1/2018 | 8/1/2018 | A | DONE |
Jim Page
|
|
|
Life fire safety inspection completed on 6/22/2018.
Andrew Phone #: ###-####
|
BLD-Final | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | PART |
Jim Storey
|
|
|
Andrew Phone #: ###-#### temp ok need ada signage/ handle reversed tank side/protection under sink
|
FIRE-Final Inspection | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection complete.
Phone #: ###-#### Inspection requested via web by Andrew Clark
|
Temporary Occupancy | 6/22/2018 | 9/20/2018 | 6/22/2018 | | DONE |
Brittany Hill
|
|
|
|
BLD-Other | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | CANC |
Jim Storey
|
|
|
Need temp certificate of occupancy Phone #: ###-#### >> Inspection requested via web by Andrew Clark
|
BLD-Framing/Rough-in | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Andrew Clark
|
CHANGE STATUS TO (ISS) | | | 5/21/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/21/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 5/9/2018 | 5/9/2018 | 5/17/2018 | | PASS |
Javier Guzman
|
|
|
Plan Mod Boise Juice Company ePlan
|
Routing - PLUMBING | 5/15/2018 | | 5/17/2018 | | PASS |
Bill VanDegrift
|
|
|
1) move expansion tank to the water heater side of the check valve.
2) verify water heater sizing with the health department.
|
Permit Ready to Issue | | | 5/17/2018 | | DONE |
|
|
|
plan mod-please do not re issue-no rev cert of val needed for plan mod
|
Routing PW Environmental | 5/15/2018 | | 5/16/2018 | | PASS |
Rick Christenson
|
|
|
No grease abatement required at this time. Should menu change, grease abatement requirements will be reviewed.
|
Routing - PUBLIC WORKS | 5/15/2018 | | 5/15/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLAN CHECK | 5/15/2018 | | 5/15/2018 | | PASS |
Javier Guzman
|
|
|
|
Plan Modification Accepted | | | 5/9/2018 | | DONE |
Christina Prado
|
|
|
Plan Mod 2 - Plumbing updates for water heater
|
Telephone call | | | 5/8/2018 | | DONE |
|
|
|
called Andrew about the plan mod he brought in-left message with the office. I didn't realize while he was here that the permit was sibmitted through e plan so he needs to fill out the 522 app and email to me and I'll start the plan mod so he can go in and upload the drawings
|
CHANGE STATUS TO (ISS) | | | 4/11/2018 | | DONE |
|
|
|
attached new sign off card to e plan
|
Print Occupancy Form | | | 4/11/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 3/28/2018 | 3/28/2018 | 4/6/2018 | | PASS |
Javier Guzman
|
|
|
Plan Mod Boise Juice Company ePlan
|
Routing - PLAN CHECK | 3/29/2018 | | 4/6/2018 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 4/6/2018 | | DONE |
|
|
|
please do not re issue
NEED
Rev Cert of Val
i added the plan mod fees but wasn't sure if the valuation changed
|
Routing PW Environmental | 3/29/2018 | | 4/6/2018 | | PASS |
Rick Christenson
|
|
|
Any future menu change will require review for grease abatement.
|
Telephone call | | | 4/3/2018 | | DONE |
|
|
|
was emaild from Troy wanting to know how much longer until he gets his plan mod- I emailed him back taht it went threw several plan reviewers and is now back to JG so it shouldn't be too much longer
|
Routing - PLUMBING | 3/29/2018 | | 3/29/2018 | | PASS |
Bill VanDegrift
|
|
|
Verify premise protection
additional cross connection may be required
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 3/29/2018 | | 3/29/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plan Modification Accepted | | | 3/28/2018 | | DONE |
|
|
|
plan mod accepted in e plan for plumbing (new 4" line route, omit grease interceptor, 3 sinks direct drain, no copper lines-sheets P1.0 & P2.0
|
Issue PAID IN FULL permit | | | 2/20/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/20/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/19/2017 | 12/19/2017 | 1/18/2018 | | PASS |
Javier Guzman
|
|
|
1/12 L2 Boise Juice Co. ePlan******
|
Routing - PLAN CHECK | 1/3/2018 | | 1/18/2018 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 1/18/2018 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/18/2018 | | DONE |
|
|
|
NEED
GC FORM -met
REVISED CERT - met
|
Routing PW Environmental | 1/3/2018 | | 1/11/2018 | | PASS |
Rick Christenson
|
|
|
JUST IN CASE. I SAW THE WORDS GREASE INTERCEPTOR. BUT ITS JUST A SMOOTHIE AND JUICE COMPANY. ACCORDING TO THE MENU.
|
Routing - FIRE | 1/3/2018 | 1/3/2018 | 1/9/2018 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Routing - PLUMBING | 1/3/2018 | | 1/5/2018 | | PASS |
Bill VanDegrift
|
|
|
1) verify premise protection
2) additional cross connection protection may be required.
3) fixture schedule calls for floor sinks at the drop in sinks.
|
Routing - Addressing | 1/3/2018 | | 1/3/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/3/2018 | | 1/3/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 1/3/2018 | | 1/3/2018 | | PASS |
Andy J. Long
|
|
|
No ESC permit required, minimal external disturbance.
|
Route to Impact Fee Review | 12/19/2017 | 12/22/2017 | 12/20/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 12/19/2017 | | 12/19/2017 | | FAIL |
Javier Guzman
|
|
|
Need to route to appropriate dept. when plumbing plans come in
|
1st review completed | | | 12/19/2017 | | FAIL |
Javier Guzman
|
|
|
no Plumbing plans were uploaded
|
Intake Approval | | | 12/19/2017 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 12/12/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 12 2017 11:34AM
|