Third Notice | | 6/16/2018 | 6/26/2018 | | DONE |
|
|
|
This permit finaled on the web by Ryan Allen
|
Second Notice | | 5/20/2018 | 6/11/2018 | | DONE |
|
|
|
Mailed 6-12
|
First Notice | | 4/29/2018 | 5/10/2018 | | DONE |
|
|
|
mailed 5-11-18
|
Print Occupancy Form | | | 4/19/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 4/19/2018 | | DONE |
|
|
|
|
BLD-Final | 4/5/2018 | 4/6/2018 | 4/6/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Allen,, all ok,, Mech is only for a temp occ.. ok
|
FIRE-Final Inspection | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags, storage shelfs were being lowered to 8 foot at time of inspection, double door behind roaster to remain in-operable. Final life fire safety inspection complete.
|
BLD-Conference | 3/22/2018 | 3/22/2018 | 3/22/2018 | P | PART |
Tony Young
|
|
|
Inspection of insulation in shaft wall assembly. If at all possible, please come late afternoon as the work is to be completed in the morning/ early afternoon. Thank you. Phone #: ###-#### Inspection requested via web by Ryan Allen// ok to cover,, will be 2 layers,, new permit in review will go into next area,,
|
BLD-Conference | 3/13/2018 | 3/14/2018 | 3/14/2018 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Allen,, add electrical to this permit.. will still need mechanical
|
BLD-Framing/Rough-in | 3/13/2018 | 3/13/2018 | 3/13/2018 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Allen,, needs electrical attached,, needs mechanical permit,, ok to rock walls
|
Issue PAID IN FULL permit | | | 3/13/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/13/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/1/2018 | | 3/8/2018 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/8/2018 | | DONE |
|
|
|
Need
Revised Cert of Value - met
ACHD-Met
|
Routing - FIRE | 3/1/2018 | 3/1/2018 | 3/7/2018 | | PASS |
Scott Arellano
|
|
|
Attached revised comments to case
|
Route to Impact Fee Review | 3/6/2018 | 3/9/2018 | 3/6/2018 | | PASS |
Eric Bilimoria
|
|
|
|
Routing - Design Review | 3/6/2018 | | 3/6/2018 | | PASS |
KayCee Babb
|
|
|
XREF CZC18-00043
|
Route to Impact Fee Review | 1/26/2018 | 1/29/2018 | 1/29/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (CDM) | 1/26/2018 | 1/26/2018 | 1/29/2018 | | PASS |
Carl D Madsen
|
|
|
1st Comp Caffecina
|
Plan assigned to (CJW) | 12/27/2017 | 12/27/2017 | 1/27/2018 | | DEFR |
Carl Westfall
|
|
|
(Jan 16 - 15 days) (13 sheets) Caffateria
|
Routing Off Site - C.D.H | 12/27/2017 | | 1/27/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/27/2017 | | 1/26/2018 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 1/26/2018 | | FAIL |
|
|
|
|
Routing PW Environmental | 12/27/2017 | | 12/29/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - FIRE | 12/27/2017 | 12/27/2017 | 12/28/2017 | | FAIL |
Scott Arellano
|
|
|
Emailed plan review report to architect. Attached report to case.
|
Routing - PUBLIC WORKS | 12/27/2017 | | 12/28/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLUMBING | 12/27/2017 | | 12/28/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
see redlines
|
Routing - Addressing | 12/27/2017 | | 12/27/2017 | | PASS |
Doug Chausow
|
|
|
Corrected address: 4774 W State St
|
Routing - Erosion and Sediment | 12/27/2017 | | 12/27/2017 | | PASS |
Michael Zawacki
|
|
|
TI interior approvement. Waiver letter read and approved.
|
Routing - MECHANICAL | 12/27/2017 | | 12/27/2017 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 12/27/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Michael accepted pre screen, routed to CDH, Javier notified applicant of ACHD fees and that this change of use be routed as major ti.
|
Application received | | | 12/12/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 12 2017 3:49PM
|