BLD-Final | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | PASS |
Tony Young
|
|
|
Nate Phone #: ###-####
|
DOC - Permit Finaled | 10/29/2019 | 10/29/2019 | 10/29/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 10/21/2019 | 10/23/2019 | 10/23/2019 | A | CANC |
Dave Hannah
|
|
|
Nate Phone #: ###-####
|
BLD-Energy code compliance | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Tony Young
|
|
|
Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 5/3/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Tony Young
|
|
|
Nate Phone #: ###-####,, ok to insulate
|
BLD-Wall Bracing | 4/18/2018 | 4/19/2018 | 4/19/2018 | A | PART |
Tony Young
|
|
|
Nate Phone #: ###-####,, exterior ok,, verify hold downs at frame inspection
|
BLD-Wall Bracing | 4/4/2018 | 4/4/2018 | 4/4/2018 | P | PART |
Dave Hannah
|
|
|
shear // Nate Phone #: ###-#### ok to cover walls but needs to install hd hold downs and nail garage front
|
BLD-Foundation | 2/7/2018 | 2/8/2018 | 2/8/2018 | A | PASS |
Dave Hannah
|
|
|
Brandon-pour time 12:30 Phone #: ###-####
|
BLD-Footing | 2/6/2018 | 2/7/2018 | 2/7/2018 | A | PASS |
Dave Hannah
|
|
|
Brandon-ready, pour time 12:30 Phone #: ###-####
|
PubWorks Subgrade Approval | 2/7/2018 | 2/7/2018 | 2/7/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Foundation | 2/5/2018 | 2/6/2018 | 2/6/2018 | P | CANC |
Dave Hannah
|
|
|
wall- Nate Phone #: ###-####
|
BLD-Footing | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | CANC |
Brandon Shaw
|
|
|
Need subgrade appoval
|
OVERRIDE | | | 1/18/2018 | | |
|
|
|
|
Telephone call | | | 1/18/2018 | | DONE |
|
|
|
Spoke with Nate informing him that this permit is ready and the fee amount due for issuance
|
Issue PAID IN FULL permit | | | 1/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/18/2018 | | DONE |
|
|
|
MET
|
Plan assigned to (JAB) Josh | 12/15/2017 | 12/15/2017 | 1/17/2018 | | PASS |
Josh Bogle
|
|
|
1st done - needs ESC, more structural & WUI info
|
Plan Reviewer's activity | | | 1/17/2018 | | DONE |
Josh Bogle
|
|
|
printed ECS waiver letter from e-mail, took to ESC folks - JAB
|
Routing - Erosion and Sediment | 1/17/2018 | | 1/17/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Certified RP designated.
|
Inspection Record Card- Bld | | | 1/17/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 1/17/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/17/2018 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 1/12/2018 | | 1/12/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 1/11/2018 | 1/11/2018 | 1/11/2018 | P | FAIL |
Josh Bogle
|
|
|
took in resubmittals, waiting on ESC waiver letter
|
1st review completed | | | 12/20/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 12/18/2017 | | 12/20/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - Erosion and Sediment | 12/15/2017 | | 12/19/2017 | | FAIL |
Andy J. Long
|
|
|
Hillside zone additions require ESC plan or ESC plan waiver letter. see ESC documents page for template. ESCP waiver request would be approved.
|
Routing Walk-In (Zoning) | 12/15/2017 | 12/15/2017 | 12/15/2017 | A | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 12/15/2017 | 12/15/2017 | 12/15/2017 | A | FAIL |
Josh Bogle
|
|
|
took in as level 2 - asked for more info from applicant
|
Telephone call | | | 12/15/2017 | | DONE |
|
|
|
called Jason T-left message that i had a set of plans at my desk and if he could come look at them to see if they are a cat 1 or 2. customer said Jason T talked to his archit. and said didn't need pre approval
|
Application received | | 12/15/2017 | | | |
|
|
|
|
Routing PW Grading-Hillside | 12/15/2017 | | | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor ###-####.
|