Permit Information
Permit NumberBLD17-04568
StatusFinaled
Name THE RUSSELL CORPORATION
Site Address 7805 W GRATZ DR
Project NameLyle Pearson Volvo - Addition
Customer Number 
ePlanReviewYes
Description
(LYLE PEARSON VOLVO – WEST BUILDING ADDITION) (DRH17-00566) (1-15-19 PLAN MODIFICATION TO REPLACE THE FORMERLY PROPOSED EXTERIOR AUTOMOBILE DOOR LEAVES INCLUDING THE ADJACENT SIDE-HINGED EXIT DOOR AT THE AUTOMOBILE SHOW ROOM WITH AN OVERHEAD DOOR. THE OCCUPANT LOAD OF THE SHOW ROOM WAS RE-EVALUATED AND THE OCCUPANT LOAD WAS DETERMINED TO BE 47 AND THE MAXIMUM TRAVEL DISTANCE TO THE OUTSIDE WAS DETERMINED TO BE LESS THAN 100 FEET LONG REQUIRING ONLY ONE EXIT.) (9-6-18 PLAN MODIFICATION TO REVISE THE SITE GRADING AND DRAINAGE AND TO DELETE A LANDSCAPE PLANTER AND TO MODIFY ANOTHER LANDSCAPE PLANTER.) The fire sprinkler system is used for building area increase, story increase, and for fire area. To construct a 5,249 square foot 1st story addition to the existing 17,286 square foot 1st story of an existing two story building (4,943 square foot existing 2nd story). After the addition, the 1st story will have a total floor area of about 22,535 square feet. Work is to include concrete footings, concrete stem walls, concrete slabs on grade, exterior and interior masonry bearing walls, exterior and interior steel stud bearing and shear walls with OSB sheathing, steel beams and steel columns, steel headers and epoxy bolts at new masonry wall openings, steel bar roof joists, steel roof deck, minimum R-30 rigid insulation installed on top of the roof deck, a single ply roofing membrane, aluminum composite exterior panels, exterior windows, exterior doors, interior nonbearing walls, a toilet room accessible to the disabled, interior glass windows/walls, interior doors, ribbed wood suspended ceiling, suspended acoustical ceiling, gypsum board ceilings and soffits, millwork, and finishes. Special Inspection is required for concrete, masonry, steel (welding), and anchors (rebar, bolts, etc.) post-installed in masonry or hardened concrete. The entry portal, including its structural design, is a deferred submittal item. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. This permit is intended to establish a Certificate of Occupancy only for the 5,249 square foot 1st story addition. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  7/31/2019 DONE
First Notice 6/9/20197/10/2019 DONE
mailed 7-11
Permanent Occupancy  5/30/2019 DONE
BLD-Final5/24/20195/28/20195/28/2019APASS
DetailsMike Jordan
Call when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton. All issues resolved. OK for perm occ.
BLD-Final5/10/20195/10/20195/10/2019PCANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Bob Thornton Inspection cancelled from web by: Bob Thornton
Zoning Approval5/10/20195/10/20195/10/2019 PASS
DetailsKatelyn Menuge
Final Zoning
BLD-Final4/12/20194/15/20194/15/2019APART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Bob Thornton. OK for temp occ. Needs to provide ADA compliant sales counter in lobby. Provide final letter from special inspection firm.
BLD-Final4/12/20194/12/20194/12/2019PNR
DetailsMike Jordan
Please call me when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton
PubWorks Occupancy Approval4/12/20194/12/20194/12/2019 DONE
DetailsTiffany Lowery
Bonding for landscape provided.
Zoning Approval Temp4/10/20194/10/20194/10/2019 DONE
DetailsKatelyn Menuge
Landscape and striping bond BND19-00061
FIRE-Final Inspection3/27/20193/28/20193/28/2019APASS
DetailsTroy Cobbley
Life safety passed

Phone #: ###-#### Inspection requested via web by Bob Thornton
BLD-Conference3/19/20193/19/20193/19/2019PDONE
DetailsMike Jordan
Give me a call Phone #: ###-#### Inspection requested via web by Bob Thornton
FIRE-Final Inspection3/18/20193/19/20193/19/2019AFAIL
DetailsTroy Cobbley
Need project related fire alarm permit finaled, another fire alarm permit needs to be applied for due to an apparent fire alarm panel replacement, need one additional fire extinguisher in the Shop, need thumbturn deadbolts removed as discussed.

I''ll plan to walk with you when you finish the alarm inspection. Phone #: ###-#### Inspection requested via web by Bob Thornton
Print Occupancy Form  3/14/2019 DONE
CHANGE STATUS TO (ISS)  1/22/2019 DONE
Print Occupancy Form  1/22/2019 DONE
OVERRIDE  1/16/2019  
Plan assigned to (CJW)1/14/20191/14/20191/16/2019 PASS
DetailsCarl Westfall
Plan mod - Lyle Pearson Volvo (plan mod routed)
Plan Reviewer's activity  1/16/2019 DONE
Plan mod back from the permits desk and ready to route
Routing - Design Review1/16/2019 1/16/2019 PASS
DetailsKatelyn Menuge
Routing - PLAN CHECK1/16/2019 1/16/2019 PASS
DetailsCarl Westfall
Plan Reviewer's activity  1/16/2019 PASS
The 2nd plan mod was approved
Permit Ready to Issue  1/16/2019 DONE
Plan mod 2 approved
BLD-Ceiling Grid Inspection1/14/20191/15/20191/15/2019APASS
DetailsMike Jordan
Bob Phone #: ###-####
Routing - PLAN CHECK1/14/2019 1/15/2019 PASS
DetailsCarl Westfall
Plan mod plan intake and plan review approved
Plan Modification Accepted  1/14/2019 DONE
lan mod for valvo addtion-changes to sheets A1.2, A3.0 & A8.0-assigned to Carl W
BLD-Ceiling Grid Inspection1/10/20191/11/20191/11/2019ACANC
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Bob Thornton
BLD-Ceiling Grid Inspection1/3/20191/3/20191/3/2019PPASS
DetailsMike Jordan
Call when you are headed this way. Phone #: ###-#### Inspection requested via web by Bob Thornton. Upper ceiling grid ok.
BLD-Conference12/27/201812/27/201812/27/2018PDONE
DetailsBrandon Shaw
Drop ceiling grid to be installed as per Manufactures installations instructions...
BLD-Ceiling Grid Inspection11/15/201811/16/201811/16/2018PPASS
DetailsJim Sly
Please look at the hard lid areas. Phone #: ###-#### Inspection requested via web by Bob Thornton
BLD-Energy code compliance10/31/201810/31/201810/31/2018PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Bob Thornton
BLD-Framing/Rough-in10/22/201810/22/201810/22/2018PPASS
DetailsMike Jordan
The inspection letter from the engineer is in my office. Phone #: ###-#### Inspection requested via web by Bob Thornton. Recieved letter from enginner of record. Ok to insulate.
BLD-Framing/Rough-in10/17/201810/18/201810/18/2018APART
DetailsMike Jordan
Bob Phone #: ###-####. Interior steel stud framed walls and soffits ok. Engineer of record to review exterior shear wall construction and approve or with modification.
Print Occupancy Form  10/17/2018 DONE
CHANGE STATUS TO (ISS)  10/17/2018 DONE
OVERRIDE  9/6/2018  
Plan assigned to (CJW)8/29/20188/29/20189/6/2018 PASS
DetailsCarl Westfall
Plan Mod - Lyle Pearson
Routing PW Drainage8/30/2018 9/6/2018 PASS
DetailsBrian Murphy
Routing PW Environmental8/30/2018 9/6/2018 PASS
DetailsRick Christenson
PLANS/APPL TAKEN TO FRONT DESK  9/6/2018 DONE
Permit Ready to Issue  9/6/2018 DONE
PLAN MOD
Routing PW Street Lights8/30/2018 9/5/2018 PASS
DetailsTom Marshall
Routing PW Grading-Hillside8/30/2018 9/5/2018 CANC
DetailsMelissa Jannusch
No review required
Routing PW Solid Waste8/30/2018 8/30/2018 PASS
DetailsEvan Carpenter
Routing - PLAN CHECK8/29/2018 8/30/2018 PASS
DetailsCarl Westfall
Routing - Design Review8/30/2018 8/30/2018 PASS
DetailsKatelyn Menuge
Routing - PUBLIC WORKS8/30/2018 8/30/2018 PASS
DetailsRachael Beierle
Plan Modification Accepted  8/29/2018 DONE
Revisions to grading and drainage at the south side of the building
BLD-Footing8/2/20188/2/20188/2/2018PPART
DetailsMike Jordan
Look at thickened footing in the show room. Concrete tomorrow morning. Phone #: ###-#### Inspection requested via web by Bob Thornton. Will have special ispection.
BLD-Foundation6/12/20186/13/20186/13/2018APART
DetailsMike Jordan
Late morning would be good. We have concrete scheduled for 1:00 Phone #: ###-#### Inspection requested via web by Bob Thornton. work in progress. Will have special inspection.
BLD-Footing6/6/20186/7/20186/8/2018PPASS
DetailsMike Jordan
We will be ready late afternoon. Phone #: ###-#### Inspection requested via web by Bob Thornton
Issue PAID IN FULL permit  4/12/2018 DONE
DetailsChristina Prado
Print Occupancy Form  4/12/2018 DONE
OVERRIDE  3/20/2018  
Plan assigned to (CJW)12/20/201712/20/20173/20/2018 PASS
DetailsCarl Westfall
(2nd done) (Jan 23 - 25 days) (63 sheets) Lyle Pearson addition
PLANS/APPL TAKEN TO FRONT DESK  3/20/2018 DONE
Permit Ready to Issue  3/20/2018 DONE
Need - Do Not Issue without GRD18-00002
Revised Cert of Value (split out for grading and building) - met
GC Form
RP (for grading)
Routing Off Site - STRUCTURAL3/14/2018 3/19/2018 PASS
DetailsCarl Westfall
Jan Welch (Stapley)
Routing - MECHANICAL3/14/2018 3/16/2018 PASS
DetailsTroy James
Service bays are to be only used as detail and lube shop. No engine repairs are to be done without having exhaust source capture system per the IMC.
Routing PW Sewer Rating3/14/2018 3/14/2018 PASS
DetailsRachael Beierle
2 drinking fountains added. Contact West Boise Sewer for updated permit.
Routing - PLAN CHECK3/13/2018 3/14/2018 PASS
DetailsCarl Westfall
Pending structural - remember to upload the 2nd plan review
Plan resubmittals received  3/13/2018 DONE
Route to Impact Fee Review3/7/20183/10/20183/7/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  3/7/2018 DONE
Plan resubmittals requested  3/7/2018 DONE
Routing - PLAN CHECK12/20/2017 3/7/2018 FAIL
DetailsCarl Westfall
Routing PW Street Lights12/21/2017 1/3/2018 PASS
DetailsTom Marshall
Routing Off Site - STRUCTURAL12/20/2017 1/2/2018 FAIL
DetailsCarl Westfall
Jan Welch (Stapley)
Routing PW Grading-Hillside12/21/2017 1/2/2018 CANC
DetailsJason C. Taylor
no review required.
Routing PW Environmental12/21/2017 12/29/2017 PASS
DetailsRick Christenson
Flammable Liquids Interceptor shown
Routing PW Solid Waste12/21/2017 12/29/2017 PASS
DetailsEvan Carpenter
Routing - FIRE12/20/201712/20/201712/28/2017 PASS
DetailsScott Arellano
Attached comments to case
Routing PW Drainage12/21/2017 12/28/2017 PASS
DetailsBrian Murphy
Routing - MECHANICAL12/20/2017 12/28/2017 FAIL
DetailsTroy James
Routing - PLUMBING12/20/2017 12/22/2017 PASS
DetailsBill VanDegrift
Per plans and ISPC
Routing - PLANNING12/20/2017 12/22/2017 PASS
DetailsCody Riddle
No review required. Approved by DR>
Routing - Addressing12/20/2017 12/21/2017 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS12/20/2017 12/21/2017 PASS
DetailsRachael Beierle
CONTACT WEST BOISE SEWER DISTRICT FOR PERMIT.
Routing - Erosion and Sediment12/20/2017 12/21/2017 PASS
DetailsAndy J. Long
ESC plan approved. Valid PD. RP needs to be designated.
Site preparation inspection required.
Routing - Design Review12/20/2017 12/21/2017 PASS
DetailsKatelyn Menuge
Pass contingent on Hillside Approval
Routing PW Sewer Design12/21/2017 12/21/2017 PASS
DetailsMike Sheppard
Intake Approval  12/20/2017 PASS
Plan Reviewer's activity  12/19/2017 PASS
DetailsCarl Westfall
Plan intake review approved
Application received  12/18/2017 DONE
Application submitted via PDS Online on Dec 18 2017 1:35PM