Print Statement | | | 7/31/2019 | | DONE |
|
|
|
|
First Notice | | 6/9/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
Permanent Occupancy | | | 5/30/2019 | | DONE |
|
|
|
|
BLD-Final | 5/24/2019 | 5/28/2019 | 5/28/2019 | A | PASS |
Mike Jordan
|
|
|
Call when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton. All issues resolved. OK for perm occ.
|
BLD-Final | 5/10/2019 | 5/10/2019 | 5/10/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Bob Thornton Inspection cancelled from web by: Bob Thornton
|
Zoning Approval | 5/10/2019 | 5/10/2019 | 5/10/2019 | | PASS |
Katelyn Menuge
|
|
|
Final Zoning
|
BLD-Final | 4/12/2019 | 4/15/2019 | 4/15/2019 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton. OK for temp occ. Needs to provide ADA compliant sales counter in lobby. Provide final letter from special inspection firm.
|
BLD-Final | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | NR |
Mike Jordan
|
|
|
Please call me when you head this way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
PubWorks Occupancy Approval | 4/12/2019 | 4/12/2019 | 4/12/2019 | | DONE |
Tiffany Lowery
|
|
|
Bonding for landscape provided.
|
Zoning Approval Temp | 4/10/2019 | 4/10/2019 | 4/10/2019 | | DONE |
Katelyn Menuge
|
|
|
Landscape and striping bond BND19-00061
|
FIRE-Final Inspection | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Conference | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | DONE |
Mike Jordan
|
|
|
Give me a call Phone #: ###-#### Inspection requested via web by Bob Thornton
|
FIRE-Final Inspection | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need project related fire alarm permit finaled, another fire alarm permit needs to be applied for due to an apparent fire alarm panel replacement, need one additional fire extinguisher in the Shop, need thumbturn deadbolts removed as discussed.
I''ll plan to walk with you when you finish the alarm inspection. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
Print Occupancy Form | | | 3/14/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/22/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/22/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 1/16/2019 | | |
|
|
|
|
Plan assigned to (CJW) | 1/14/2019 | 1/14/2019 | 1/16/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod - Lyle Pearson Volvo (plan mod routed)
|
Plan Reviewer's activity | | | 1/16/2019 | | DONE |
|
|
|
Plan mod back from the permits desk and ready to route
|
Routing - Design Review | 1/16/2019 | | 1/16/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLAN CHECK | 1/16/2019 | | 1/16/2019 | | PASS |
Carl Westfall
|
|
|
|
Plan Reviewer's activity | | | 1/16/2019 | | PASS |
|
|
|
The 2nd plan mod was approved
|
Permit Ready to Issue | | | 1/16/2019 | | DONE |
|
|
|
Plan mod 2 approved
|
BLD-Ceiling Grid Inspection | 1/14/2019 | 1/15/2019 | 1/15/2019 | A | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####
|
Routing - PLAN CHECK | 1/14/2019 | | 1/15/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod plan intake and plan review approved
|
Plan Modification Accepted | | | 1/14/2019 | | DONE |
|
|
|
lan mod for valvo addtion-changes to sheets A1.2, A3.0 & A8.0-assigned to Carl W
|
BLD-Ceiling Grid Inspection | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Ceiling Grid Inspection | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PASS |
Mike Jordan
|
|
|
Call when you are headed this way. Phone #: ###-#### Inspection requested via web by Bob Thornton. Upper ceiling grid ok.
|
BLD-Conference | 12/27/2018 | 12/27/2018 | 12/27/2018 | P | DONE |
Brandon Shaw
|
|
|
Drop ceiling grid to be installed as per Manufactures installations instructions...
|
BLD-Ceiling Grid Inspection | 11/15/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Sly
|
|
|
Please look at the hard lid areas. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Energy code compliance | 10/31/2018 | 10/31/2018 | 10/31/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
BLD-Framing/Rough-in | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Mike Jordan
|
|
|
The inspection letter from the engineer is in my office. Phone #: ###-#### Inspection requested via web by Bob Thornton. Recieved letter from enginner of record. Ok to insulate.
|
BLD-Framing/Rough-in | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | PART |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Interior steel stud framed walls and soffits ok. Engineer of record to review exterior shear wall construction and approve or with modification.
|
Print Occupancy Form | | | 10/17/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/17/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 9/6/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 8/29/2018 | 8/29/2018 | 9/6/2018 | | PASS |
Carl Westfall
|
|
|
Plan Mod - Lyle Pearson
|
Routing PW Drainage | 8/30/2018 | | 9/6/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Environmental | 8/30/2018 | | 9/6/2018 | | PASS |
Rick Christenson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/6/2018 | | DONE |
|
|
|
PLAN MOD
|
Routing PW Street Lights | 8/30/2018 | | 9/5/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Grading-Hillside | 8/30/2018 | | 9/5/2018 | | CANC |
Melissa Jannusch
|
|
|
No review required
|
Routing PW Solid Waste | 8/30/2018 | | 8/30/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLAN CHECK | 8/29/2018 | | 8/30/2018 | | PASS |
Carl Westfall
|
|
|
|
Routing - Design Review | 8/30/2018 | | 8/30/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PUBLIC WORKS | 8/30/2018 | | 8/30/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plan Modification Accepted | | | 8/29/2018 | | DONE |
|
|
|
Revisions to grading and drainage at the south side of the building
|
BLD-Footing | 8/2/2018 | 8/2/2018 | 8/2/2018 | P | PART |
Mike Jordan
|
|
|
Look at thickened footing in the show room. Concrete tomorrow morning. Phone #: ###-#### Inspection requested via web by Bob Thornton. Will have special ispection.
|
BLD-Foundation | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PART |
Mike Jordan
|
|
|
Late morning would be good. We have concrete scheduled for 1:00 Phone #: ###-#### Inspection requested via web by Bob Thornton. work in progress. Will have special inspection.
|
BLD-Footing | 6/6/2018 | 6/7/2018 | 6/8/2018 | P | PASS |
Mike Jordan
|
|
|
We will be ready late afternoon. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
Issue PAID IN FULL permit | | | 4/12/2018 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 4/12/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 3/20/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 12/20/2017 | 12/20/2017 | 3/20/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) (Jan 23 - 25 days) (63 sheets) Lyle Pearson addition
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/20/2018 | | DONE |
|
|
|
Need - Do Not Issue without GRD18-00002
Revised Cert of Value (split out for grading and building) - met
GC Form
RP (for grading)
|
Routing Off Site - STRUCTURAL | 3/14/2018 | | 3/19/2018 | | PASS |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - MECHANICAL | 3/14/2018 | | 3/16/2018 | | PASS |
Troy James
|
|
|
Service bays are to be only used as detail and lube shop. No engine repairs are to be done without having exhaust source capture system per the IMC.
|
Routing PW Sewer Rating | 3/14/2018 | | 3/14/2018 | | PASS |
Rachael Beierle
|
|
|
2 drinking fountains added. Contact West Boise Sewer for updated permit.
|
Routing - PLAN CHECK | 3/13/2018 | | 3/14/2018 | | PASS |
Carl Westfall
|
|
|
Pending structural - remember to upload the 2nd plan review
|
Plan resubmittals received | | | 3/13/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/7/2018 | 3/10/2018 | 3/7/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 3/7/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/7/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/20/2017 | | 3/7/2018 | | FAIL |
Carl Westfall
|
|
|
|
Routing PW Street Lights | 12/21/2017 | | 1/3/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing Off Site - STRUCTURAL | 12/20/2017 | | 1/2/2018 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing PW Grading-Hillside | 12/21/2017 | | 1/2/2018 | | CANC |
Jason C. Taylor
|
|
|
no review required.
|
Routing PW Environmental | 12/21/2017 | | 12/29/2017 | | PASS |
Rick Christenson
|
|
|
Flammable Liquids Interceptor shown
|
Routing PW Solid Waste | 12/21/2017 | | 12/29/2017 | | PASS |
Evan Carpenter
|
|
|
|
Routing - FIRE | 12/20/2017 | 12/20/2017 | 12/28/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Routing PW Drainage | 12/21/2017 | | 12/28/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 12/20/2017 | | 12/28/2017 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 12/20/2017 | | 12/22/2017 | | PASS |
Bill VanDegrift
|
|
|
Per plans and ISPC
|
Routing - PLANNING | 12/20/2017 | | 12/22/2017 | | PASS |
Cody Riddle
|
|
|
No review required. Approved by DR>
|
Routing - Addressing | 12/20/2017 | | 12/21/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/20/2017 | | 12/21/2017 | | PASS |
Rachael Beierle
|
|
|
CONTACT WEST BOISE SEWER DISTRICT FOR PERMIT.
|
Routing - Erosion and Sediment | 12/20/2017 | | 12/21/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid PD. RP needs to be designated.
Site preparation inspection required.
|
Routing - Design Review | 12/20/2017 | | 12/21/2017 | | PASS |
Katelyn Menuge
|
|
|
Pass contingent on Hillside Approval
|
Routing PW Sewer Design | 12/21/2017 | | 12/21/2017 | | PASS |
Mike Sheppard
|
|
|
|
Intake Approval | | | 12/20/2017 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 12/19/2017 | | PASS |
Carl Westfall
|
|
|
Plan intake review approved
|
Application received | | | 12/18/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 18 2017 1:35PM
|