Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD17-04571
StatusFinaled
Name FIRST TEAM RESTORATION
Site Address 2770 S ORCHARD ST
Project NameGrand Theft Auto
Customer Number 
ePlanReviewNo
Description
(GRAND THEFT AUTO) Repair permit with Certificate of Occupancy Evaluation. A PRE-CONSTRUCTION CONFERENCE WITH THE BUILDING INSPECTOR IS REQUIRED TO ANY RECONSTRUCTION. Permit for repairs as a result of fire damage to an existing auto repair shop. Per the plans and description all structural members showing any signs of damage are to be replaced including beams. This building is not fire sprinklered. Tenant does not currently have certificate of occupancy; Certificate of Occupancy to be issued upon completion and approval of the building and repair. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/12/20192/25/2019 DONE
This permit finaled on the web by Darrin Preece
Second Notice 1/17/20192/7/2019 DONE
mailed 2-11-19
First Notice 1/5/20191/7/2019 DONE
mailed 1-11-19
Permanent Occupancy  12/26/2018 DONE
BLD-Final12/21/201812/24/201812/24/2018PPASS
DetailsJim Sly
Stuart Phone #: ###-####
FIRE-Final Inspection12/21/201812/24/201812/24/2018APASS
DetailsTroy Cobbley
Life safety passed. Owner will provide single action ADA hardware on all of the doors per conversation.

Stuart Phone #: ###-####
FIRE-Final Inspection12/20/201812/21/201812/21/2018AFAIL
DetailsJim Page
Provide fire extinguisher with current inspection tag. Provide sticker on front door reading "Door to remain unlocked while building is occupied. Need city approved drawings/documents for final inspection.

Stuart Phone #: ###-####
BLD-Aging Inspection12/14/201812/14/201812/21/2018 CANC
DetailsJim Sly
BLD-Final12/19/201812/20/201812/20/2018PNR
DetailsJim Sly
Stewart Phone #: ###-####
Need Fire and Mech.
BLD-Framing/Rough-in8/1/20188/2/20188/2/2018APART
DetailsJim Sly
We had electrical inspection for rough in on 7/31. we need framing inspection so we can cover. Any questions please call Darrin ###-#### Thank you. Phone #: ###-#### Inspection requested via web by Darrin
OK to cover select walls. Do not cover any walls/ceilings that will interfear with Plumbing or Mech rough-in inspections.
Issue PAID IN FULL permit  1/2/2018 DONE
Plan assigned to (JAR)12/19/201712/19/201712/29/2017 DONE
DetailsJulie Romig
12/26 (5days) - Fire Repair for 2770 S. Orchard
Routing - PLAN CHECK12/19/2017 12/29/2017 PASS
DetailsJulie Romig
1st review completed  12/29/2017 DONE
DetailsJulie Romig
Case Summary (BLD)  12/29/2017 DONE
PLANS/APPL TAKEN TO FRONT DESK  12/29/2017 DONE
Permit Ready to Issue  12/29/2017 DONE
DetailsChristina Prado
Need:
GC Form
Print Occupancy Form  12/29/2017 DONE
DetailsChristina Prado
Intake Approval  12/19/2017 PASS
per JAR
Plans ACCEPTED BY PLAN TECH  12/19/2017 DONE
Recd Pcfee & Taken To Pln CK  12/19/2017 DONE
Application received 12/18/2017