Second Notice | | 7/21/2018 | 7/13/2018 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | | 6/30/2018 | 7/11/2018 | | DONE |
|
|
|
mailed 7-12-18
|
Letter of compliance/Occupancy | | | 6/20/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 6/20/2018 | | DONE |
|
|
|
|
Zoning Approval | 6/19/2018 | 6/19/2018 | 6/19/2018 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Final | 6/15/2018 | 6/18/2018 | 6/18/2018 | P | PASS |
Dave Hannah
|
|
|
Please Contact Gerome 30 min Prior ###-#### Phone #: ###-#### Inspection requested via web by Brian McCoy
|
FIRE-Final Inspection | 6/15/2018 | 6/18/2018 | 6/18/2018 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
Please Contact Gerome 30 min Prior ###-#### Phone #: ###-#### Inspection requested via web by Brian McCoy
|
CHANGE STATUS TO (ISS) | | | 6/15/2018 | | DONE |
Christina Prado
|
|
|
Plan Mod fees paid
|
Plan assigned to (CJW) | 5/22/2018 | 5/22/2018 | 6/7/2018 | | PASS |
Carl Westfall
|
|
|
x (plan intake approved - routed) Plan Modification - Hops and Bottles
|
Plan Reviewer's activity | | | 6/7/2018 | | PASS |
|
|
|
1st plan mod approved
|
Permit Ready to Issue | | | 6/7/2018 | | |
|
|
|
DO NOT REISSUE - Plan mod
|
Routing - Design Review | 5/24/2018 | | 6/6/2018 | | PASS |
Katelyn Menuge
|
|
|
CUP18-00025
|
Routing - PUBLIC WORKS | 5/24/2018 | | 5/24/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - PLANNING | 5/24/2018 | | 5/24/2018 | | PASS |
Brent Moore
|
|
|
|
Routing - PLAN CHECK | 5/22/2018 | | 5/23/2018 | | FAIL |
Carl Westfall
|
|
|
Plan intake failed. Provide a dimensioned aisle and seating plan showing a minimum 42 inch wide aisle connecting the exit doors. Show a minimum 36 inch wide aisle giving access to the restrooms. Show 4 accessible drinking surfaces (or a number equal to 5% of the total seating) located so that aisles will not be blocked when a wheelchair is at the space. Show tables located so that at least 19 inches is provided to accommodate chairs (at least 31 inches to accommodate wheelchairs) so that chairs will not block aisles. CJW
|
Routing - PLAN CHECK | 5/23/2018 | | 5/23/2018 | | PASS |
Carl Westfall
|
|
|
Aisle and seating plan provided and approved with red lines.
|
Plan Modification Accepted | | | 5/22/2018 | | DONE |
Christina Prado
|
|
|
Plan Modification - add bar and seating to plan
|
BLD-Other | 5/17/2018 | 5/18/2018 | 5/18/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Gerome Fries North and East ..steel stud walls.......insulated, and vapor barrier installed.
|
BLD-Framing/Rough-in | 5/16/2018 | 5/16/2018 | 5/16/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Gerome Fries
|
BLD-Footing | 4/19/2018 | 4/19/2018 | 4/19/2018 | P | PASS |
Dave Hannah
|
|
|
Please call 30 mins prior Phone #: ###-#### Inspection requested via web by Gerome Fries
|
Issue PAID IN FULL permit | | | 4/9/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/9/2018 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 1/4/2018 | 1/4/2018 | 3/20/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) (Jan 24 - 15 days) (26 sheets) Bottle Shop
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/20/2018 | | DONE |
|
|
|
MET
Need
Revised Cert of Value
(MET) GC Form
ACHD
|
Routing Off Site - STRUCTURAL | 3/15/2018 | | 3/19/2018 | | PASS |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - PLAN CHECK | 3/14/2018 | | 3/15/2018 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Plan resubmittals received | | | 3/14/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/9/2018 | 3/12/2018 | 3/9/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 3/9/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/9/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/4/2018 | | 3/9/2018 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Routing Off Site - C.D.H | 1/4/2018 | | 1/16/2018 | | PASS |
Carl Westfall
|
|
|
Will Reynolds - no review required
|
Routing - FIRE | 1/4/2018 | 1/4/2018 | 1/11/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 1/4/2018 | | 1/11/2018 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing PW Environmental | 1/5/2018 | | 1/11/2018 | | PASS |
Rick Christenson
|
|
|
Any future food prep will require Environmental review for grease abatement.
|
Routing - MECHANICAL | 1/4/2018 | | 1/5/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/4/2018 | | 1/5/2018 | | PASS |
Bill VanDegrift
|
|
|
1) additional cross connection protection may be required
2) verify premis protection
|
Routing - Addressing | 1/4/2018 | | 1/5/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/4/2018 | | 1/5/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 1/4/2018 | | 1/5/2018 | | PASS |
Michael Zawacki
|
|
|
Interior TI. No ESCP required.
|
Routing - Design Review | 1/4/2018 | | 1/5/2018 | | PASS |
Katelyn Menuge
|
|
|
See Planning memo regarding use restrictions.
|
Intake Approval | | | 1/4/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Carl M accepted pre screen,
|
Intake Approval | | | 12/26/2017 | | FAIL |
|
|
|
|
Application received | | | 12/18/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 18 2017 4:13PM
|