Print Statement | | | 8/13/2020 | | DONE |
|
|
|
1st past due
|
Meeting | | | 4/9/2020 | | DONE |
|
|
|
waiting for hear back from curtis on the electrical value total, how to divide the mechanical value with the two companies and who did the plumbing since no plm attached to bld.
|
Third Notice | | 3/14/2020 | 4/3/2020 | | DONE |
|
|
|
emailed curtis 4-3-2020
|
Second Notice | | 2/17/2020 | 3/9/2020 | | DONE |
|
|
|
emailed curtis 3-9-20
|
First Notice | | 1/19/2020 | 2/7/2020 | | DONE |
|
|
|
emailed victoria and curtis 2-7-20
|
Letter of compliance/Occupancy | | | 1/9/2020 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 1/9/2020 | | DONE |
|
|
|
Permit Finaled 3/29/18
|
(F) Reprint permit | | | 8/16/2019 | | DONE |
|
|
|
|
BLD-Final | 3/28/2018 | 3/29/2018 | 3/29/2018 | A | PASS |
Dave Hannah
|
|
|
Daryl Phone #: ###-####
|
FIRE-Final Inspection | 3/23/2018 | 3/27/2018 | 3/26/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
|
BLD-Ceiling Grid Inspection | 3/16/2018 | 3/19/2018 | 3/19/2018 | A | PASS |
Dave Hannah
|
|
|
Darly Phone #: ###-####
|
BLD-Conference | 2/27/2018 | 2/28/2018 | 2/28/2018 | A | DONE |
Dave Hannah
|
|
|
Fire wall // Daryl Phone #: ###-####
|
BLD-Framing/Rough-in | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | PEND |
Dave Hannah
|
|
|
Daryl Phone #: ###-#### ok to cover after elec rough in
|
Issue PAID IN FULL permit | | | 2/14/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/14/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/8/2018 | | DONE |
Christina Prado
|
|
|
Need:
GC form - met
Revised Value - met
|
Plan assigned to (JG) | 12/29/2017 | 12/29/2017 | 1/6/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 12/26 L1 MI WAITING ROOM RELOCATION ePlan
|
Routing - PLAN CHECK | 1/3/2018 | | 1/6/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/6/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 12/29/2017 | 1/1/2018 | 1/2/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 12/20/2017 | 12/20/2017 | 12/29/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 12/26 L1 MI WAITING ROOM RELOCATION ePlan
|
Routing - PLAN CHECK | 12/20/2017 | | 12/29/2017 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 12/29/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 12/28/2017 | | 12/28/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/28/2017 | | 12/28/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - FIRE | 12/20/2017 | 12/20/2017 | 12/26/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Routing - MECHANICAL | 12/20/2017 | | 12/26/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 12/20/2017 | | 12/20/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 12/20/2017 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 12/19/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 19 2017 2:23PM
|