BLD-Final | 6/5/2018 | 6/6/2018 | 6/6/2018 | A | PASS |
Dave Hannah
|
|
|
David Phone #: ###-####
|
First Notice | | 6/16/2018 | 6/6/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 6/6/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/1/2018 | 6/1/2018 | 6/1/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, final commercial hood fire suppression system inspection complete. Final life fire safety inspection for area of work complete.
|
Extend Permit 90/180 days | 6/1/2018 | 6/1/2018 | 6/1/2018 | A | CANC |
Jim Page
|
|
|
|
BLD-Framing/Rough-in | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PASS |
Jim Storey
|
|
|
Dave Phone #: ###-#### steel stud header ok with walls ok to cover pending plm
|
Plan assigned to (JAR) | 1/5/2018 | 1/5/2018 | 2/1/2018 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - L3 Donut Glaze
|
Routing - PLAN CHECK | 1/5/2018 | | 2/1/2018 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 2/1/2018 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/1/2018 | | DONE |
|
|
|
NEED
GC
Rev cert of Val
|
Issue PAID IN FULL permit | | | 2/1/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/1/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/5/2018 | | 1/31/2018 | | PASS |
Julie Romig
|
|
|
|
Routing PW Environmental | 1/8/2018 | | 1/16/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - FIRE | 1/5/2018 | 1/5/2018 | 1/11/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Sewer Rating | 1/8/2018 | | 1/10/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 1/5/2018 | | 1/8/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PUBLIC WORKS | 1/5/2018 | | 1/8/2018 | | PASS |
Rachael Beierle
|
|
|
ROUTED ONLY
|
Routing - MECHANICAL | 1/5/2018 | | 1/8/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLUMBING | 1/5/2018 | | 1/5/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 1/5/2018 | | 1/5/2018 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 1/5/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Rob accepted pre screen, CDH approval uploaded in documents
|
Routing - Erosion and Sediment | 1/5/2018 | | 1/5/2018 | | PASS |
Michael Zawacki
|
|
|
TI. No ESCP needed.
|
Plan Reviewer's activity | | | 1/5/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Katlyn,
Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are do please submit the documentation from ACDH as such.
Please note that this change of use permit application will be routed as a major TI.
You can reach ACHD at ###-####.
Thank you
|
Intake Approval | | | 12/27/2017 | | FAIL |
Rob Patrick
|
|
|
12-27-17: Please provide the following:
1. Planning and Zoning Approval Letter
2. Structural Engineering for Type 1 Hood with install details
3. Structural Engineering for MAU 1 install on roof with install details
4. Portable Fire Extinguisher locations
5. Fire Water Flow letter
Thank you
Rob Patrick
|
Intake Approval | | | 12/20/2017 | | FAIL |
Rob Patrick
|
|
|
12-20-17: Please provide the Central District Health Department signed review documents.
Thank you.
Rob Patrick
|
Application received | | | 12/19/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 19 2017 3:23PM
|