Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD17-04590
StatusFinaled
Name DAVINCI STONE LLC
Site Address 11522 W FAIRVIEW AVE
Project NameDaVinci Stone Warehouse Add
Customer Number 
ePlanReviewYes
Description
(DAVINCI STONE – WAREHOUSE ADDITION) (DRH17-00255) The fire sprinkler system is used for building area increase, for fire area, and for fire flow. To construct a 7,161 square foot warehouse addition on the North end of an existing 10,010 square foot building. After the addition, this building will have a total floor area of about 17,171 square feet (18,078 square feet including the existing 907 square foot mezzanine). For the addition, work is to include concrete footings, concrete stem walls, concrete slab on grade, steel moment frames (beams and columns), steel columns, lateral bracing cables, steel roof purlins, steel roof panels, steel wall purlins, steel wall panels, an overhead door, and side-hinged swinging doors. A liner system with R-38 insulation, a vapor retarder installed on the warm in winter side of the insulation, and thermal spacers will be used to insulate the roof. The walls will be insulated with R-25 insulation with thermal break tape at the horizontal purlins and will have a vapor retarder installed on the warm in winter side of the insulation. Work to be done to the adjacent existing roof to support the added snow drift load includes additional steel purlins, purlin blocking, reinforcing steel plates welded to the top and/or bottom flange of existing steel beams, and additional bolts at existing beam splices. Special Inspection is required for concrete, steel (including bolting and welding), and anchors post-installed in hardened concrete. A new 8 foot tall masonry trash enclosure will be constructed. A separate permit is required for racks over 8 feet tall. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. A fire sprinkler system will be installed throughout this building (existing and new addition) in conjunction with this permit. This permit is intended to establish a Certificate of Occupancy for the entire building, the existing building and the building addition. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  5/16/2019 DONE
Second Notice 4/18/20195/6/2019 DONE
mailed 5-10-19
First Notice 3/31/20194/8/2019 DONE
mailed 4-11-19
BLD-Final3/21/20193/21/20193/21/2019PPASS
DetailsMike Jordan
Randy Phone #: ###-####
Permanent Occupancy  3/21/2019 DONE
Zoning Approval3/20/20193/20/20193/20/2019 DONE
DetailsAndrea Tuning
FIRE-Final Inspection1/15/20191/16/20191/16/2019APASS
DetailsTroy Cobbley
Life safety passed.

Randy Phone #: ###-####
FIRE-Final Inspection1/4/20191/4/20191/4/2019PFAIL
DetailsTroy Cobbley
Life safety will be ok to pass when the project related fire sprinkler permit is passed

Randy Phone #: ###-####
BLD-Final1/4/20191/4/20191/4/2019PNR
DetailsJim Sly
Randy Phone #: ###-####
Need Fir18-00609 sprinkler. Zoning and Fire life safety.
FIRE-Final Inspection1/4/20191/4/20191/4/2019PFAIL
DetailsTroy Cobbley
Need small documents and the project related fire sprinkler permit finaled.
FIRE-Conference11/27/201811/27/201811/27/2018PDONE
DetailsTroy Cobbley
Randy and I went over basic life safety requirements for his project.
PubWorks Occupancy Approval11/5/201811/5/201811/5/2018 DONE
DetailsTiffany Lowery
BLD-Wall Bracing6/28/20186/29/20186/29/2018APASS
DetailsJim Sly
Jeff Phone #: ###-####
East 1/2 of Foundation Wall.....OK
BLD-Footing6/26/20186/27/20186/27/2018APART
DetailsJim Sly
Jeff Phone #: ###-####
East 1/2 of bldg.......OK. verified anchor bolts 24" long.
BLD-Foundation6/4/20186/5/20186/5/2018APART
DetailsJim Sly
Jeff Phone #: ###-####
No Special Inspection required. PART West 1/2 of Bldg. OK.
BLD-Footing5/31/20186/1/20186/1/2018PPASS
DetailsJim Sly
Jeff Phone #: ###-####
Issue PAID IN FULL permit  5/8/2018 DONE
Print Occupancy Form  5/8/2018 DONE
OVERRIDE  5/3/2018  
Plan assigned to (CJW)2/24/20182/24/20185/3/2018 PASS
DetailsCarl Westfall
(3rd done) (Mar 30 - 25 days) (Feb 24 PI) (28 sheets) Davinci Stone Addition
PLANS/APPL TAKEN TO FRONT DESK  5/3/2018 DONE
Permit Ready to Issue  5/3/2018 DONE
Need:
GC form- met
Revised value from GC-met
RP-met
Routing - PLAN CHECK5/1/2018 5/2/2018 PASS
DetailsCarl Westfall
Routing - PLANNING5/2/2018 5/2/2018 PASS
DetailsDavid Moser
Routing - Design Review5/2/2018 5/2/2018 PASS
DetailsAndrea Tuning
Plan resubmittals received  5/1/2018 DONE
Plan resubmittals requested  4/14/2018 DONE
Routing PW Solid Waste4/11/2018 4/13/2018 PASS
DetailsEvan Carpenter
Routing - PLANNING4/11/2018 4/12/2018 FAIL
DetailsDavid Moser
need to make sure the west side building setbacks are the same on SP1.0, SP2.0 and C1.0 site plans
Route to Impact Fee Review4/10/20184/13/20184/11/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Plan resubmittals received  4/11/2018 DONE
Routing - PLAN CHECK4/11/2018 4/11/2018 PASS
DetailsCarl Westfall
Routing - Design Review4/11/2018 4/11/2018 FAIL
DetailsAndrea Tuning
Provide a copy of a recorded cross access and shared parking agreement allowing this parcel to utilize the drive aisles and parking throughout the neighboring property. The applicant will be required to continue to provide a total of 14-parking spaces on this parcel in perpetuity or obtain other off-site parking meeting the required criteria. The agreement should be reviewed and approved By the City of Boise's Legal Department prior to being recorded.
Plan resubmittals requested  4/10/2018 DONE
Other agencies have items that need to be resolved.
1st review completed  4/10/2018 DONE
Routing - PLAN CHECK2/24/2018 4/10/2018 PASS
DetailsCarl Westfall
1st IBC plan review completed and approved
Routing PW Drainage3/12/2018 3/12/2018 PASS
DetailsBrian Murphy
Routing Off Site - STRUCTURAL2/24/2018 3/8/2018 PASS
DetailsCarl Westfall
Dave Haugland (AHJ)
Routing PW Drainage2/26/2018 3/5/2018 FAIL
DetailsBrian Murphy
apendx j
Routing PW Environmental2/26/2018 3/5/2018 PASS
DetailsRick Christenson
Storage only
Routing - FIRE2/24/20182/24/20183/2/2018 PASS
DetailsScott Arellano
Attached comments to case
Routing - MECHANICAL2/24/2018 2/27/2018 PASS
DetailsChad Schwendiman
Routing - PLANNING2/24/2018 2/26/2018 FAIL
DetailsDavid Moser
The site plan SP2.0 does not match the site plan C1.0. Remove note 11 from parcel 1655 Bryson since the outdoor gravel storage area is not approved.
Routing - Addressing2/24/2018 2/26/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS2/24/2018 2/26/2018 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment2/24/2018 2/26/2018 PASS
DetailsMichael Zawacki
Valid RP needed prior to any ground disturbing activities. Plan designer will need to update schedule and BMPs as stated in schedule section of SWPPP.
Site inspection required before work begins.
Routing PW Solid Waste2/26/2018 2/26/2018 FAIL
DetailsEvan Carpenter
The solid waste enclosure must have at least 12 feet of unobstructed clearance between gate posts (measured from the innermost points).
Routing - Design Review2/24/2018 2/26/2018 FAIL
DetailsAndrea Tuning
Provide a copy of a recorded cross access and shared parking agreement allowing this parcel to utilize the drive aisles and parking throughout the neighboring property. The applicant will be required to continue to provide a total of 14-parking spaces on this parcel in perpetuity or obtain other off-site parking meeting the required criteria.
Intake Approval  2/24/2018 PASS
Plan Reviewer's activity  2/20/2018 PASS
Plan intake review approved
Intake Approval  2/5/2018 FAIL
(2-5-18) Please refer to the circled items (without an OK in the circle) in the plan intake checklist. Please resolve each item as directed. CJW
Intake Approval  1/10/2018 FAIL
(1-10-18) Please refer to the circled items in the plan intake checklist. Please resolve each item as directed. CJW
Intake Approval  12/22/2017 FAIL
Nothing but the application was uploaded
Application received  12/19/2017 DONE
Application submitted via PDS Online on Dec 19 2017 4:40PM