Third Notice | | 4/16/2019 | 4/12/2019 | | DONE |
|
|
|
This permit finaled on the web by Curtis Weedop
|
Third Notice | | 3/12/2019 | 4/11/2019 | | DONE |
|
|
|
mailed 4-12-19 with first follow up letter, mcenteev@slhs.org (vira)
|
First Follow up | | | 4/11/2019 | | DONE |
|
|
|
|
Third Notice | | 2/11/2019 | 3/7/2019 | | DONE |
|
|
|
emailed curtis 3-7-19
|
Third Notice | | 1/13/2019 | 3/7/2019 | | DONE |
|
|
|
emailed curtis 2-6-19
|
Second Notice | | 12/24/2018 | 1/8/2019 | | DONE |
|
|
|
emailed value to curtis
|
First Notice | | 12/9/2018 | 12/14/2018 | | DONE |
|
|
|
maild 12-17
|
Permanent Occupancy | | | 11/29/2018 | | DONE |
|
|
|
|
BLD-Final | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Dave Hannah
|
|
|
zack Phone #: ###-####
|
FIRE-Final Inspection | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire exitnguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
zack Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
BLD-Final | 9/7/2018 | 9/10/2018 | 9/10/2018 | A | PART |
Dave Hannah
|
|
|
Zack Phone #: ###-#### phase one ok
|
FIRE-Final Inspection | 9/7/2018 | 9/7/2018 | 9/7/2018 | P | PART |
Jim Page
|
|
|
Project is being worked in phases, fire sprinklers complete for phase 2 (West side of level 7), fire alarms complete for phase 2, fire extinguisher are placed with current inspection tags, final life fire safety inspection for phase 2 west side complete, west side to be inspected at a later date.
Zack Phone #: ###-####
|
BLD-Framing/Rough-in | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PART |
Tony Young
|
|
|
rocky Phone #: ###-####,, walls ok pending trades
|
BLD-Final | 8/17/2018 | 8/20/2018 | 8/20/2018 | P | PART |
Dave Hannah
|
|
|
partial pednding MEC & PLM - Zack Phone #: ###-#### phase 1 ok to occ
|
BLD-Ceiling Grid Inspection | 8/10/2018 | 8/13/2018 | 8/13/2018 | A | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
FIRE-Final Inspection | 8/10/2018 | 8/10/2018 | 8/10/2018 | P | PART |
Jim Page
|
|
|
Project is being worked in phases, fire sprinklers complete for phase 1 (East side of level 7), fire alarms complete for phase 1, fire extinguisher are placed with current inspection tags, final life fire safety inspection for phase 1 east side complete, west side to be inspected at a later date.
Final life safety // Zac Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
BLD-Framing/Rough-in | 8/2/2018 | 8/3/2018 | 8/3/2018 | A | PASS |
Dave Hannah
|
|
|
Zach Phone #: ###-####
|
BLD-Framing/Rough-in | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | PART |
Dave Hannah
|
|
|
Ken Phone #: ###-####k to cover first phase
|
BLD-Framing/Rough-in | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | NR |
Tony Young
|
|
|
Ken Phone #: ###-####
|
Print Occupancy Form | | | 2/23/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/23/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/21/2017 | 12/21/2017 | 2/6/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 1/03 L2 WGP4 -7th Floor Patient Access ePlan
|
Routing - PLAN CHECK | 2/5/2018 | | 2/6/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/6/2018 | | DONE |
Christina Prado
|
|
|
Need
GC form - met
Revised Cert of Value - met
|
CHANGE STATUS TO (REV) | | | 2/6/2018 | | DONE |
|
|
|
sent back to plan reviewer (changemarks)
|
CHANGE STATUS TO (RDY) | | | 2/6/2018 | | DONE |
|
|
|
|
Routing - FIRE | 1/26/2018 | 1/26/2018 | 1/31/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 1/26/2018 | | 1/27/2018 | | FAIL |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 1/9/2018 | 1/12/2018 | 1/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 12/21/2017 | | 1/9/2018 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 1/9/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 12/21/2017 | | 1/5/2018 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 12/21/2017 | 12/21/2017 | 12/28/2017 | | FAIL |
Scott Arellano
|
|
|
Attached comments to case and emailed architect
|
Routing - PLUMBING | 12/21/2017 | | 12/22/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 12/21/2017 | | 12/22/2017 | | PASS |
Doug Chausow
|
|
|
Ste 720
|
Routing - PUBLIC WORKS | 12/21/2017 | | 12/22/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 12/21/2017 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 12/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 20 2017 11:35AM
|