Second Notice | | 8/12/2019 | 8/19/2019 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
First Notice | | 7/20/2019 | 8/2/2019 | | DONE |
|
|
|
mailed 8/5/19
|
Permanent Occupancy | | | 7/10/2019 | | DONE |
|
|
|
|
BLD-Final | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PASS |
Mike Jordan
|
|
|
jeff Phone #: ###-####. Ok for perm occ. All issues resolved.
|
BLD-Final | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | PART |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Ok for temp oc. Need final letter from special inspection agency and needs to lower sinks in bathrroms to meet ADA.
|
Zoning Approval | 5/10/2019 | 5/10/2019 | 5/10/2019 | | PASS |
Josh Wilson
|
|
|
Existing fence may remain without slats JGW
|
FIRE-Final Inspection | 5/3/2019 | 5/6/2019 | 5/6/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor is going to provide an occupant load sign for the Conference room prior to a building inspection.
Jeff Phone #: ###-####
|
FIRE-Final Inspection | 5/1/2019 | 5/2/2019 | 5/2/2019 | P | CANC |
Mark Scharfen
|
|
|
Alarmco not ready. Jeff Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Concrete | 4/15/2019 | 4/16/2019 | 4/16/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff- concrete pad inspection Phone #: ###-####. Exterior slab on grade for trash enclosure.
|
OVERRIDE | | | 4/1/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 3/7/2019 | 3/7/2019 | 4/1/2019 | | DONE |
Julie Romig
|
|
|
03/22 - IBC Rev Comp - Plan Mod - Innovative Air Site Work
|
Print Occupancy Form | | | 4/1/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/1/2019 | | DONE |
|
|
|
attached plan mod sign revised sign off card in e plan
|
Print Occupancy Form | | | 4/1/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/1/2019 | | DONE |
|
|
|
plan mod approved
|
Routing - FIRE | 3/19/2019 | 3/19/2019 | 3/28/2019 | | PASS |
Erika Akin
|
|
|
Plan mod has no impact to exisitng FD access.
|
Routing - PLAN CHECK | 3/18/2019 | | 3/27/2019 | | PASS |
Julie Romig
|
|
|
|
Routing PW Street Lights | 3/19/2019 | | 3/26/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PUBLIC WORKS | 3/19/2019 | | 3/22/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing PW Solid Waste | 3/19/2019 | | 3/21/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Design Review | 3/18/2019 | | 3/20/2019 | | PASS |
Katelyn Menuge
|
|
|
Redlined Site Plan
|
Routing PW Drainage | 3/19/2019 | | 3/19/2019 | | PASS |
Brian Murphy
|
|
|
|
BLD-Conference | 3/8/2019 | 3/11/2019 | 3/11/2019 | A | DONE |
Mike Jordan
|
|
|
Jeff Phone #: ###-####-3190
|
Plan Modification Accepted | | | 3/7/2019 | | DONE |
|
|
|
plan mod accepted in e plan-changes to site work only-assigned to JAR
|
BLD-Footing | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Footings have been excavated down to 24 inch min depth.
|
BLD-Footing | 2/27/2019 | 2/28/2019 | 2/28/2019 | P | NR |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Footings at mid landing need min 24 inch for frost depth.
|
BLD-Ceiling Grid Inspection | 2/22/2019 | 2/25/2019 | 2/25/2019 | A | NR |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Needs trades first.
|
Print Occupancy Form | | | 2/21/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/21/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 2/19/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 2/13/2019 | 2/13/2019 | 2/19/2019 | | DONE |
Julie Romig
|
|
|
02/20 - Plan Mod Innovative Air Exterior Stair resubmittal
|
Routing - PLAN CHECK | 2/15/2019 | | 2/19/2019 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 2/19/2019 | | DONE |
|
|
|
Plan mod-do not re issue
|
Plan Modification Accepted | | | 2/13/2019 | | DONE |
|
|
|
Per Jeff Geibel scope is the same as provided on 1/24/19:
Delayed submittal of the second floor exterior stair component previously approved in the original permit application. This will be for the approval of engineer stamped construction plans of the manufactured metal stair only. Footins and vertical load components were provided by the building Engineer of record (Jeremy Parrish, Strucural ERdge Engineering) approved under the original permit and are not a part of this submittal
|
CHANGE STATUS TO (ISS) | | | 2/7/2019 | | DONE |
|
|
|
plan mod
|
Print Occupancy Form | | | 2/7/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 2/1/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 1/24/2019 | 1/24/2019 | 2/1/2019 | | DONE |
Julie Romig
|
|
|
02/01 - Plan Mod Innovative Air Ext Stairs Engineering Submittal
|
Routing - PLAN CHECK | 1/28/2019 | | 2/1/2019 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 2/1/2019 | | DONE |
|
|
|
plan mod approved
|
BLD-Framing/Rough-in | 1/30/2019 | 1/31/2019 | 1/31/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Interior framing for new vestibule ok.
|
Routing Off Site - STRUCTURAL | 1/28/2019 | | 1/31/2019 | | PASS |
Julie Romig
|
|
|
|
Plan Modification Accepted | | | 1/24/2019 | | DONE |
|
|
|
Delayed submittal of the second floor exterior stair component previously approved in the original permit application. This will be for the approval of engineer stamped construction plans of the manufactured metal stair only. Footins and vertical load components were provided by the building Engineer of record (Jeremy Parrish, Strucural ERdge Engineering) approved under the original permit and are not a part of this submittal
|
BLD-Footing | 1/11/2019 | 1/14/2019 | 1/14/2019 | P | CANC |
Mike Jordan
|
|
|
Jeff Phone #: ###-#### // cancelled by requestor 1-11-2019 GF
|
BLD-Framing/Rough-in | 1/10/2019 | 1/11/2019 | 1/11/2019 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Riser room framing ok.
|
BLD-Framing/Rough-in | 1/9/2019 | 1/9/2019 | 1/9/2019 | P | PART |
Brandon Shaw
|
|
|
Mezzanine bathroom and IT room... Beam to Beam straps, as per plans...
|
BLD-Framing/Rough-in | 1/7/2019 | 1/8/2019 | 1/8/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Interior wwod and steel stud framed walls at 1st. floor only and remaining shear walls.
|
BLD-Framing/Rough-in | 12/18/2018 | 12/19/2018 | 12/19/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Interior steel stud framed walls from floor to ceiling and mezz to ceiling on gridline E grids 4.5 to 9 and grids 4.5 from grids A to E. per approved plans and ASI 02 for top track connection to purlins.
|
BLD-Framing/Rough-in | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | PART |
Mike Jordan
|
|
|
new exterior wall framing for new exterior finish. partial 2nd floor deck diaphragm. Waiting on on panel edge nailing.
|
BLD-Conference | 12/13/2018 | 12/13/2018 | 12/13/2018 | P | DONE |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Webber Phone #: ###-####. at channel on interior side of exterior walls ok.
|
BLD-Framing/Rough-in | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Shear walls on grids A and 9.
|
BLD-Conference | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | DONE |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Discussed one siding shear walls prior to standing were walls are against the existing structure.
|
Issue PAID IN FULL permit | | | 11/5/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/5/2018 | | DONE |
|
|
|
|
Telephone call | | | 10/31/2018 | | DONE |
|
|
|
emailed mberard@kreizenbeck.com, informing fees are still due
|
OVERRIDE | | | 10/24/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 4/3/2018 | 4/3/2018 | 10/24/2018 | | DONE |
Julie Romig
|
|
|
10/24 - 1st Rev Comp - L3 Innovative Air (3rd Resubmittal in Process at owner's request for modifications)
|
Routing - PLAN CHECK | 10/18/2018 | | 10/24/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/24/2018 | | DONE |
|
|
|
Need - ALL MET - Email permits to Joe Saucerman
RP
GC Form
Revised Cert of Value
|
Routing - FIRE | 10/19/2018 | 10/19/2018 | 10/23/2018 | | PASS |
Erika Akin
|
|
|
|
Routing - Design Review | 10/18/2018 | | 10/19/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLUMBING | 10/18/2018 | | 10/18/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLAN CHECK | 9/20/2018 | | 10/8/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 9/20/2018 | | 9/27/2018 | | PASS |
Troy James
|
|
|
|
Routing Off Site - STRUCTURAL | 9/20/2018 | | 9/24/2018 | | PASS |
Julie Romig
|
|
|
AHJ
|
Routing - Design Review | 9/20/2018 | | 9/21/2018 | | FAIL |
Andrea Tuning
|
|
|
Need to choose Class I tree species.
|
Routing - PLUMBING | 9/20/2018 | | 9/21/2018 | | FAIL |
Daryl Spivey
|
|
|
Need to submit waste and vent plan with sizing and a fixture schedule.
|
Routing - PLAN CHECK | 6/1/2018 | | 7/19/2018 | | FAIL |
Julie Romig
|
|
|
3rd Review
|
Routing Off Site - STRUCTURAL | 6/1/2018 | | 6/11/2018 | | FAIL |
Julie Romig
|
|
|
3rd Review
|
Routing - FIRE | 6/1/2018 | 6/1/2018 | 6/4/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - Design Review | 6/1/2018 | | 6/4/2018 | | FAIL |
Andrea Tuning
|
|
|
Move the two (2) proposed Class II trees a minimum of 10 lateral feet away from the overhead powerlines or choose an approved Class I tree species.
|
Extend Review Timeline | | | 5/29/2018 | | DONE |
|
|
|
1st approved 180 day extension per Adele. See documents
|
Plan Modification Accepted | | | 4/3/2018 | | DONE |
Christina Prado
|
|
|
Plan RESUBMITTAL - permit not yet issued but applicant requesting structural changes to proposed 2nd story
|
Plan Reviewer's activity | | | 4/3/2018 | | DONE |
Julie Romig
|
|
|
Spoke with owner George Massing. He would like to change the building Construction Type from IIB to VB and the 2nd floor structure from steel to wood to save costs. Permit has not been picked up yet. Greg confirmed that he would like ePlan Case sent back to architect to resubmit plans with modifications. He anticipates resubmitting in a month or so. Told him that project would be reviewed by fire/bldg/structural at a 10-15 day timeframe, and if a 4th review is required, additional review fees accrue at an hourly rate.
|
OVERRIDE | | | 3/12/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 3/12/2018 | | DONE |
|
|
|
Need:
RP
GC form
Revised value from GC
|
Plan assigned to (JAR) | 1/4/2018 | 1/4/2018 | 3/11/2018 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 2nd Rec'd 02/22 - L3 Innovative Air
|
Routing - PLAN CHECK | 2/22/2018 | | 3/11/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/22/2018 | | 2/27/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
Route to Impact Fee Review | 2/7/2018 | 2/10/2018 | 2/8/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/7/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 1/4/2018 | | 2/7/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 1/4/2018 | | 1/16/2018 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview
|
Routing - FIRE | 1/4/2018 | 1/4/2018 | 1/11/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Environmental | 1/4/2018 | | 1/11/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 1/4/2018 | | 1/8/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/4/2018 | | 1/5/2018 | | PASS |
Bill VanDegrift
|
|
|
1) additional cross conection protection may be required for
the swamp cooler and fluid cooler.
2) recommend DCVA for premise protection.
|
Routing - Addressing | 1/4/2018 | | 1/4/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/4/2018 | | 1/4/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 1/4/2018 | | 1/4/2018 | | PASS |
Michael Zawacki
|
|
|
Waiver approved. TI interior only
|
Routing - Design Review | 1/4/2018 | | 1/4/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH17-00558
|
Intake Approval | | | 1/4/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie accepted pre screen
|
Intake Approval | | | 1/2/2018 | | FAIL |
Julie Romig
|
|
|
Need: Site specific flow at Hydrants Letter, Sheet A5.01, Rotate Sheet A6.12
|
Application received | | | 12/21/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 21 2017 1:04PM
|