Permit Information
Permit NumberBLD17-04623
StatusFinaled
Name RTA SKYLINE LLC
Site Address 2180 S HUDSON AVE
Project NameSkyline Apartments Bldg A
Customer NumberBLD17-04623 TO BLD17-04632
ePlanReviewYes
Description
(Building A)(SKYLINE APARTMENTS – BUILDING TYPE 2, Building A, B, C, E, G and J) (24 units)PLAN MOD RELOCATE WAHER/DRYER FROM BATHROOM TO HALLWAY ADD CLOSED DOOR AS NOTED ON APPROVED PLANS 7-2-18**AJS**The NFPA 13-R fire sprinkler system is used for occupancy and for story increase. To construct a 25,320 square foot three story VB Type of Construction apartment building (8,458 sq. ft. 1st story and 8,431 sq. ft. 2nd story and 8,431 sq. ft. 3rd story). Each unit is 1 story. Work is to include concrete footings, concrete foundations, concrete slabs on grade, wood stud bearing walls, wood stud shear walls, fiberglass shingles, 1-hr dwelling unit separations, 1 hour fire barriers for stair and breezeways, rated doors in breezeway, interior nonbearing walls, millwork, and finishes. Special Inspection is NOT required. The roof truss design is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13-R as regulated by the Fire Department. Separate fire sprinkler permits shall be obtained prior to beginning any modification or installation work on such systems. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/22/201910/23/201910/23/2019APASS
DetailsJim Storey
Permanent Occupancy  10/22/2019 DONE
Zoning Approval10/14/201910/14/201910/14/2019 PASS
DetailsKatelyn Menuge
Telephone call  9/12/2019 DONE
talked to Bob Miller about the temp c of o expiring-he will take care of it when he gets back in the office on 9-17-16
BLD-Aging Inspection9/2/20199/2/20199/3/2019 PASS
DetailsJim Storey
ramp ok
Temporary Occupancy7/16/201910/14/20197/16/2019 DONE
DetailsTiffany Carson-Herker
BLD-Final7/3/20197/3/20197/5/2019PPART
DetailsJim Storey
building final Phone #: ###-#### Inspection requested via web by J.C. Murray temp ok pending c/n for ramp 1014.4 and pz perm.
BLD-Final7/2/20197/3/20197/3/2019ANR
DetailsJim Storey
building final Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Final7/2/20197/2/20197/2/2019PDEFR
DetailsJim Storey
building final Phone #: ###-#### Inspection requested via web by J.C. Murray am 7/3
FIRE-Final Inspection7/2/20197/2/20197/2/2019PPASS
DetailsJim Page
Previously noted items have been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags, final life fire safety inspection complete.

fire/ life ; safety final Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Final6/25/20196/26/20196/26/2019PCANC
DetailsJim Storey
Final occupancy signature. Phone #: ###-#### Inspection requested via web by J.C. Murray
FIRE-Final Inspection6/25/20196/26/20196/26/2019PFAIL
DetailsJim Page
Called point of contact with no answer, provide street address fopr building. Could not access rooms to verify sprinkler escutcheons were in place. Need fire lane signage installed where required.

Fire/ Life ; Safety Final. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Aging Inspection6/11/20196/11/20196/11/2019 PASS
DetailsJim Storey
PubWorks Occupancy Approval6/7/20196/7/20196/7/2019 DONE
DetailsTiffany Lowery
Bonding in place for additional drainage installation.
PubWorks Temp Occupancy Appr6/6/20196/6/20196/6/2019 DONE
DetailsMike Sheppard
Zoning Approval Temp6/3/20196/3/20196/3/2019 PASS
DetailsKatelyn Menuge
Temporary Occupancy - BND19-00086
FIRE-Conference3/29/20193/29/20193/29/2019PDONE
DetailsJim Page
Each building that is requiring heat trace on the fire sprinkler lines has a FIR permit associated with the heat trace install. Inspection for heat trace needs to be scheduled with the associated permit for proper inspection procedure.

Breezeway sprinkler pipe heat tape insulation inspection
for Buildings A B C E. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Ceiling Grid Inspection3/7/20193/8/20193/8/2019PPASS
DetailsJim Storey
Builiding A - drop ceiling for cover, fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray lower units fed side
BLD-Ceiling Grid Inspection3/4/20193/4/20193/4/2019PPASS
DetailsJim Storey
Bld A - north 12 units. drop ceilings for cover. fire caulking Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Energy code compliance1/28/20191/28/20191/28/2019PPASS
DetailsJim Storey
Bld A - insulation energy code. RC channel at ceilings and walls. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Other1/22/20191/23/20191/23/2019APASS
DetailsJim Storey
building A - interior framing and fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in1/18/20191/22/20191/22/2019PDEFR
DetailsJim Storey
building A - interior framing and fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in11/27/201811/28/201811/28/2018PPASS
DetailsJim Storey
exterior railing and straps, interior first floor hold-downs and tighten bolts and truss engineering // JC Phone #: ###-####
BLD-Framing/Rough-in11/26/201811/27/201811/27/2018PNR
DetailsJim Storey
exterior railing and straps, interior first floor hold-downs and tighten bolts and truss engineering // JC Phone #: ###-####
Fees Due Hold10/25/2018 11/26/2018 DONE
DetailsTisha Gallop
plan mod fees due on BLD17-04632 for plan mod on clubhouse not Bld A
OVERRIDE  10/24/2018  
Plan assigned to (AJS)8/22/20188/22/201810/24/2018 PASS
DetailsAdele J Schaffeld-Griffin
CHANGE STATUS TO (ISS)  10/24/2018 DONE
Permit Ready to Issue  10/24/2018 DONE
plan mod
Routing - MECHANICAL10/10/2018 10/10/2018 PASS
DetailsTroy James
BLD-Wall Bracing9/20/20189/21/20189/21/2018APART
DetailsBrandon Shaw
Interior shear, first floor
BLD-Framing/Rough-in9/20/20189/21/20189/21/2018ACANC
DetailsBrandon Shaw
JC Phone #: ###-####
Case Summary (BLD)  9/18/2018 DONE
DetailsAdele J Schaffeld-Griffin
Case Summary (BLD)  9/18/2018 DONE
DetailsAdele J Schaffeld-Griffin
Routing - FIRE8/27/20188/27/20189/5/2018 PASS
DetailsErika Akin
Modification to clubhouse design. No change to previous comments
Routing - PLUMBING8/27/2018 8/29/2018 PASS
DetailsDaryl Spivey
See redline notes..Provide suds relief and funnel drain for condensates.
Routing - MECHANICAL8/27/2018 8/28/2018 FAIL
DetailsTroy James
New uploaded sheets are versioned over existing sheets that are different.
Routing - PUBLIC WORKS8/27/2018 8/27/2018 PASS
DetailsRachael Beierle
Routing PW Drainage8/27/2018 8/27/2018 PASS
DetailsBrian Murphy
Routing - Design Review8/27/2018 8/27/2018 PASS
DetailsKatelyn Menuge
DRH18-00381
Plan Modification Accepted  8/22/2018 DONE
Revise the interior and exterior design of the Clubhouse building. Interior areas have been revised and the exterior updated to match. The exterior design uses the same design and materials of the original design.
BLD-Foundation7/19/20187/20/20187/20/2018APASS
DetailsJim Storey
wall- Manuel Phone #: ###-####
BLD-Foundation7/19/20187/19/20187/19/2018PDEFR
DetailsJim Storey
wall- Manuel Phone #: ###-####out of time
BLD-Footing7/16/20187/17/20187/17/2018APASS
DetailsJim Storey
manny Phone #: ###-####
CHANGE STATUS TO (ISS)  7/10/2018 DONE
Plan mod
OVERRIDE  7/3/2018  
Plan assigned to (AJS)6/26/20186/26/20187/3/2018 PASS
DetailsAdele J Schaffeld-Griffin
Routing - PLUMBING7/2/2018 7/3/2018 PASS
DetailsDan Ediger
Minor washer box relocation. No resubmittal required.
Permit Ready to Issue  7/3/2018 DONE
PLAN MOD (17-04623, 04624, 4625, 4627, 4628, 4630, 4631)
Routing - PLAN CHECK7/2/2018 7/2/2018 PASS
DetailsAdele J Schaffeld-Griffin
PLAN MOD RELOCATE WAHER/DRYER FROM BATHROOM TO HALLWAY ADD CLOSED DOOR AS NOTED ON APPROVED PLANS 7-2-18**AJS**
Routing - MECHANICAL7/2/2018 7/2/2018 PASS
DetailsTroy James
exhaust fan relocation
Plan Modification Accepted  6/26/2018 DONE
started workflow for modification; Type 2 - Relocate the wsher/dryer from the bathroom to the hallway. Add pocket door to bedroom closet. Type 2-HC - Add pocket door to bedroom closet. Type 5 - Relocate the washer dryer from the bathroom to the hallway and reconfigure bathroom. Type 5-HC - Remove closet adjacent to kitchen counter.
Issue PAID IN FULL permit  5/16/2018 DONE
Print Occupancy Form  5/16/2018 DONE
Expiration Notice5/15/20186/5/20185/15/2018 DONE
DetailsBrittany Hill
OVERRIDE  5/2/2018  
Permit Ready to Issue  5/2/2018 DONE
DetailsChristina Prado
All requirements met
Plan assigned to (AJS)1/9/20181/9/20185/1/2018 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Skyline Apartment
Routing - PLAN CHECK5/1/2018 5/1/2018 PASS
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL5/1/2018 5/1/2018 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  5/1/2018 DONE
Routing Off Site - STRUCTURAL4/16/2018 4/16/2018 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK4/16/2018 4/16/2018 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - Design Review4/2/2018 4/2/2018 PASS
DetailsKatelyn Menuge
Route to Impact Fee Review2/12/20182/15/20182/13/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  2/12/2018 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK1/9/2018 2/12/2018 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL1/9/2018 2/12/2018 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Sewer Design1/9/2018 1/25/2018 PASS
DetailsMike Sheppard
Engineer will submit a separate set plans for approval.

approval per ePlan
Routing - Erosion and Sediment1/9/2018 1/23/2018 PASS
DetailsAndy J. Long
ESC plan approved. Petra needs to designate their own RP. Site preparation inspection required.
Routing - PLUMBING1/9/2018 1/16/2018 PASS
DetailsBill VanDegrift
1)sewer design must be reviewed and approved by IDEQ, building services are to be permitted and inspected by the building department.
2) floor drains under furnaces must be provided with a funnel and must not be in a return air plenum.
3) area under furnace at floor drain must be vented for moisture.
4) provide suds relief through out.
Routing - FIRE1/9/20181/9/20181/10/2018 PASS
DetailsScott Arellano
See Fire Code plan review comments previously approved under BLD15-03953.
Routing - MECHANICAL1/9/2018 1/10/2018 PASS
DetailsTroy James
Routing PW Sewer Rating1/9/2018 1/10/2018 PASS
DetailsMorgan Webb
Routing - PLANNING1/9/2018 1/10/2018 PASS
DetailsNicolette Womack
Required to provide 192 bicycle spaces.
Routing - Addressing1/9/2018 1/9/2018 PASS
DetailsDoug Chausow
Address: 2180 S Hudson Ave
Routing - PUBLIC WORKS1/9/2018 1/9/2018 PASS
DetailsRachael Beierle
ROUTED ONLY. WAITING FOR ADDRESSING PRIOR TO SEWER RATING.
Routing - Design Review1/9/2018 1/9/2018 FAIL
DetailsKatelyn Menuge
Corrections to landscape and light pole locations required. (Check for 192 bike parking stalls on updated site plan)
Routing PW Solid Waste1/9/2018 1/9/2018 PASS
DetailsEvan Carpenter
Routing PW Drainage1/9/2018 1/9/2018 PASS
DetailsBrian Murphy
Routing PW Street Lights1/9/2018 1/9/2018 PASS
DetailsTom Marshall
Intake Approval  1/9/2018 PASS
DetailsAdele J Schaffeld-Griffin
Intake Approval  12/28/2017 FAIL
DetailsAdele J Schaffeld-Griffin
Please see mark ups on check list for missing items. Thank you
Application received  12/22/2017 DONE
Application submitted via PDS Online on Dec 22 2017 11:30AM
First Notice 11/1/2019