Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD17-04624
StatusFinaled
Name PETRA INC
Site Address 2120 S HUDSON AVE
Project NameSkyline Apartments BLDG B
Customer NumberBLD17-04623 IN EPLAN
ePlanReview 
Description
(Building B)(SKYLINE APARTMENTS – BUILDING TYPE 2, Building A, B, C, E, G and J) (24 Units)PLAN MOD RELOCATE WAHER/DRYER FROM BATHROOM TO HALLWAY ADD CLOSED DOOR AS NOTED ON APPROVED PLANS 7-2-18**AJS**The NFPA 13-R fire sprinkler system is used for occupancy and for story increase. To construct a 25,320 square foot three story VB Type of Construction apartment building (8,458 sq. ft. 1st story and 8,431 sq. ft. 2nd story and 8,431 sq. ft. 3rd story). Each unit is 1 story. Work is to include concrete footings, concrete foundations, concrete slabs on grade, wood stud bearing walls, wood stud shear walls, fiberglass shingles, 1-hr dwelling unit separations, 1 hour fire barriers for stair and breezeways, rated doors in breezeway, interior nonbearing walls, millwork, and finishes. Special Inspection is NOT required. The roof truss design is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13-R as regulated by the Fire Department. Separate fire sprinkler permits shall be obtained prior to beginning any modification or installation work on such systems. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  10/22/2019 DONE
BLD-Aging Inspection10/14/201910/14/201910/16/2019 PASS
DetailsJim Storey
Zoning Approval10/14/201910/14/201910/14/2019 PASS
DetailsKatelyn Menuge
Temporary Occupancy9/25/201912/24/20199/25/2019 DONE
DetailsCandy A. Nichols
Jason Blais ok'd temp c of o ext good until 11/15/19
Telephone call  9/12/2019 DONE
talked to Bob Miller about the temp c of o expiring-he will take care of it when he gets back in the office on 9-17-16
BLD-Aging Inspection8/13/20198/13/20198/15/2019 PASS
DetailsJim Storey
zoning temp.
Temporary Occupancy6/14/20199/12/20196/14/2019 DONE
DetailsTiffany Carson-Herker
BLD-Final6/13/20196/13/20196/13/2019PPASS
DetailsJim Storey
issues resolved. re-inspection for Building final Phone #: ###-#### Inspection requested via web by J.C. Murray final ok
BLD-Final6/11/20196/12/20196/12/2019PNR
DetailsJim Storey
Building final. Phone #: ###-#### Inspection requested via web by J.C. Murray need handrail 12 inches top and bottom// under stair protection.
BLD-Final6/11/20196/11/20196/11/2019PNR
DetailsJim Storey
Building final. Phone #: ###-#### Inspection requested via web by J.C. Murray
PubWorks Occupancy Approval6/7/20196/7/20196/7/2019 DONE
DetailsTiffany Lowery
Bonding in place for additional drainage installation.
PubWorks Temp Occupancy Appr6/6/20196/6/20196/6/2019 DONE
DetailsMike Sheppard
Zoning Approval Temp6/3/20196/3/20196/3/2019 DONE
DetailsKatelyn Menuge
Temporary Occupancy - BND19-00086
BLD-Final5/30/20195/31/20195/31/2019PNR
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by J.C. Murray
FIRE-Final Inspection5/30/20195/31/20195/31/2019APASS
DetailsJim Page
Fire sprinkler inspection complete, fire al;arm inspection complete, fire extinguishers are placed with current inspection tags, knox box is located by fire sprinkler riser room. Final life fire safety inspection complete, fire alarms must be monitored after occupancy.

Fire / Life ; Safety Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Ceiling Grid Inspection2/14/20192/14/20192/14/2019PPASS
DetailsJim Storey
Building B south 12 units. drop ceiling for cover. fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Wall cover2/1/20192/1/20192/1/2019PPASS
DetailsJim Storey
Building B - north 12 units. drop ceiling for cover, fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Energy code compliance1/10/20191/11/20191/11/2019APASS
DetailsMike Jordan
Bld B - south 12 energy, insulation and tenting. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in12/28/201812/28/201812/28/2018PPASS
DetailsJim Storey
Bld B - south 12 fire caulking/ framing Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Energy code compliance12/28/201812/28/201812/28/2018PPASS
DetailsJim Storey
Bld -B: north 12 units. insulation and RC Channel Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in12/21/201812/21/201812/21/2018PPASS
DetailsJim Storey
Bld B - north 12 unit framing and fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in12/6/201812/7/201812/7/2018PPASS
DetailsJim Storey
Bld B - interior framing and fire caulking Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in11/14/201811/15/201811/15/2018APASS
DetailsJim Storey
Bld B - roof truss engineering Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in11/13/201811/14/201811/14/2018APART
DetailsJim Storey
Bld B - roof truss engineering and interior framing. Phone #: ###-#### Inspection requested via web by J.C. Murray no engineering
BLD-Framing/Rough-in11/12/201811/13/201811/13/2018ACANC
DetailsJim Sly
Bld B
rough framing interior, truss engineering . Phone #: ###-#### Inspection requested via web by J.C. Murray
Called in wrong Bldg.
BLD-Framing/Rough-in11/6/201811/7/201811/7/2018APASS
DetailsJim Storey
Building B. exterior nailing, straps Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in11/1/201811/2/201811/2/2018APASS
DetailsJim Storey
Bld B; foundation to building anchor bolts, hold downs and titan bolts. Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in9/14/20189/19/20189/19/2018APASS
DetailsJim Storey
slab on grade shear walls, center and south sections.

Building B Phone #: ###-#### Inspection requested via web by J.C. Murray
BLD-Framing/Rough-in9/4/20189/5/20189/5/2018PPART
DetailsJim Sly
partial 1st floor shear wall north end. Bld B. Inspection requested via web by J.C. Murray
Interior layers.....OK.
BLD-Foundation7/25/20187/25/20187/25/2018PPASS
DetailsJim Storey
Manual Phone #: ###-####
BLD-Footing7/20/20187/20/20187/20/2018PPASS
DetailsJim Storey
manuel Phone #: ###-####
CHANGE STATUS TO (ISS)  7/10/2018 DONE
plan mod
OVERRIDE  7/3/2018  
Plan assigned to (AJS)6/26/20186/26/20187/3/2018 PASS
DetailsAdele J Schaffeld-Griffin
Routing - MECHANICAL7/2/2018 7/3/2018 PASS
DetailsAdele J Schaffeld-Griffin
Routing - PLUMBING7/2/2018 7/3/2018 CANC
DetailsAdele J Schaffeld-Griffin
Permit Ready to Issue  7/3/2018 DONE
PLAN MOD (17-04623, 04624, 4625, 4627, 4628, 4630, 4631)
Routing - PLAN CHECK7/2/2018 7/2/2018 PASS
DetailsAdele J Schaffeld-Griffin
PLAN MOD RELOCATE WAHER/DRYER FROM BATHROOM TO HALLWAY ADD CLOSED DOOR AS NOTED ON APPROVED PLANS 7-2-18**AJS**
Plan Modification Accepted  6/26/2018 DONE
started workflow for modification; Type 2 - Relocate the wsher/dryer from the bathroom to the hallway. Add pocket door to bedroom closet. Type 2-HC - Add pocket door to bedroom closet. Type 5 - Relocate the washer dryer from the bathroom to the hallway and reconfigure bathroom. Type 5-HC - Remove closet adjacent to kitchen counter.
Issue PAID IN FULL permit  5/16/2018 DONE
Print Occupancy Form  5/16/2018 DONE
Expiration Notice5/15/20186/5/20185/15/2018 DONE
DetailsBrittany Hill
OVERRIDE  5/2/2018  
Permit Ready to Issue  5/2/2018 DONE
DetailsChristina Prado
All requirements met
Plan assigned to (AJS)1/9/20181/9/20185/1/2018 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Skyline Apartments
Routing - PLAN CHECK5/1/2018 5/1/2018 PASS
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL5/1/2018 5/1/2018 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  5/1/2018 DONE
Routing - Design Review4/2/2018 4/2/2018 PASS
DetailsKatelyn Menuge
Route to Impact Fee Review2/12/20182/15/20182/13/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLUMBING1/9/2018 2/13/2018 PASS
DetailsBill VanDegrift
Routing - PLAN CHECK1/9/2018 2/12/2018 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL1/9/2018 2/12/2018 FAIL
DetailsAdele J Schaffeld-Griffin
1st review completed  2/12/2018 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Sewer Design1/9/2018 1/25/2018 PASS
DetailsMike Sheppard
Sewer plans have not been approved

approval per ePlan
Routing - Erosion and Sediment1/9/2018 1/23/2018 PASS
DetailsAndy J. Long
ESC plan approved. Petra needs to designate their own RP. Site preparation inspection required. See also ESC17-01754
Routing - FIRE1/9/20181/9/20181/10/2018 PASS
DetailsScott Arellano
See Fire Code plan review comments previously approved under BLD15-03954.
Routing - MECHANICAL1/9/2018 1/10/2018 PASS
DetailsTroy James
Routing PW Sewer Rating1/9/2018 1/10/2018 PASS
DetailsMorgan Webb
Routing - PLANNING1/9/2018 1/10/2018 PASS
DetailsNicolette Womack
Required to provide 192 bicycle spaces.
Routing - Addressing1/9/2018 1/9/2018 PASS
DetailsDoug Chausow
Address: 2120 S Hudson Ave
Routing - PUBLIC WORKS1/9/2018 1/9/2018 PASS
DetailsRachael Beierle
Routing - Design Review1/9/2018 1/9/2018 FAIL
DetailsKatelyn Menuge
Corrections to landscape and light pole locations required.
Intake Approval  1/9/2018 PASS
DetailsAdele J Schaffeld-Griffin
Routing PW Solid Waste1/9/2018 1/9/2018 PASS
DetailsEvan Carpenter
Routing PW Drainage1/9/2018 1/9/2018 PASS
DetailsBrian Murphy
Routing PW Street Lights1/9/2018 1/9/2018 PASS
DetailsTom Marshall
Application received  12/22/2017 DONE
Application submitted via PDS Online on Dec 22 2017 11:30AM
First Notice 11/1/2019