Permanent Occupancy | | | 10/22/2019 | | DONE |
|
|
|
|
BLD-Final | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | DONE |
Jim Storey
|
|
|
Brian Phone #: ###-####
|
PubWorks Occupancy Approval | 10/17/2019 | 10/17/2019 | 10/17/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 10/14/2019 | 10/14/2019 | 10/14/2019 | | PASS |
Katelyn Menuge
|
|
|
|
FIRE-Final Inspection | 8/26/2019 | 8/29/2019 | 8/29/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete, card signed for fire alarm, fire sprinkler and life safety.
call rob Phone #: ###-#### Inspection requested via web by J.C. Murray
|
Temporary Occupancy | 8/29/2019 | 11/27/2019 | 8/29/2019 | | DONE |
Judith Amador
|
|
|
|
Zoning Approval Temp | 8/29/2019 | 8/29/2019 | 8/29/2019 | | PASS |
Katelyn Menuge
|
|
|
Temporary
|
PubWorks Temp Occupancy Appr | 8/29/2019 | 8/29/2019 | 8/29/2019 | | PASS |
Mike Sheppard
|
|
|
Ok per Mike S for Temp occ
|
BLD-Final | 8/26/2019 | 8/29/2019 | 8/28/2019 | P | DONE |
Jim Storey
|
|
|
call rob Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Final | 8/27/2019 | 8/28/2019 | 8/28/2019 | P | PASS |
Jim Storey
|
|
|
rob final ok pending fire
|
BLD-Framing/Rough-in | 5/15/2019 | 5/16/2019 | 5/16/2019 | A | PASS |
Jim Storey
|
|
|
Bld E - west side drop ceilings for cover, fire caulking Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Energy code compliance | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | PASS |
Jim Storey
|
|
|
insulation inspection. Phone #: ###-#### Inspection requested via web by J.C. Murray ok for cover
|
BLD-Other | 3/13/2019 | 3/14/2019 | 3/14/2019 | A | PASS |
Jim Storey
|
|
|
fire caulking- Craig Phone #: ###-####
|
BLD-Framing/Rough-in | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | PASS |
Mike Jordan
|
|
|
Bld H - framing roof trusses/ engineering. hold downs, titan bolts. exterior shear nailing. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 10/24/2018 | 10/25/2018 | 10/25/2018 | A | PASS |
Jim Storey
|
|
|
Building H interior shear walls. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Foundation | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | PASS |
Jim Storey
|
|
|
Manual Phone #: ###-####
|
BLD-Foundation | 8/1/2018 | 8/1/2018 | 8/1/2018 | P | CANC |
Jim Storey
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 8/1/2018 | 8/1/2018 | 8/1/2018 | P | PASS |
Jim Storey
|
|
|
Manual Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/16/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/16/2018 | | DONE |
|
|
|
|
Expiration Notice | 5/15/2018 | 6/5/2018 | 5/15/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 5/2/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 5/2/2018 | | DONE |
Christina Prado
|
|
|
all met
|
Plan assigned to (AJS) | 1/9/2018 | 1/9/2018 | 5/1/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Skyline Apartments
|
Routing - PLAN CHECK | 5/1/2018 | | 5/1/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing Off Site - STRUCTURAL | 5/1/2018 | | 5/1/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2018 | | DONE |
|
|
|
|
Routing - Design Review | 4/2/2018 | | 4/2/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Route to Impact Fee Review | 2/12/2018 | 2/15/2018 | 2/13/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/12/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 1/9/2018 | | 2/12/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Sewer Design | 1/9/2018 | | 1/25/2018 | | PASS |
Mike Sheppard
|
|
|
approval per ePlan
|
Routing - Erosion and Sediment | 1/9/2018 | | 1/23/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Petra needs to designate their own RP. Site preparation inspection required. See also ESC17-01754
|
Routing Off Site - STRUCTURAL | 1/9/2018 | | 1/22/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 1/9/2018 | 1/9/2018 | 1/10/2018 | | PASS |
Scott Arellano
|
|
|
See Fire Code plan review comments previously approved under BLD15-03960.
|
Routing PW Sewer Rating | 1/9/2018 | | 1/10/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 1/9/2018 | | 1/10/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/9/2018 | | 1/10/2018 | | PASS |
Nicolette Womack
|
|
|
Required to provide 192 bicycle spaces.
|
Routing - Addressing | 1/9/2018 | | 1/9/2018 | | PASS |
Doug Chausow
|
|
|
Address: 2045 S Hudson Ave
|
Routing - PUBLIC WORKS | 1/9/2018 | | 1/9/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 1/9/2018 | | 1/9/2018 | | FAIL |
Katelyn Menuge
|
|
|
Corrections to landscape and light pole locations required.
|
Intake Approval | | | 1/9/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Solid Waste | 1/9/2018 | | 1/9/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 1/9/2018 | | 1/9/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 1/9/2018 | | 1/9/2018 | | PASS |
Tom Marshall
|
|
|
|
Application received | | | 12/22/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 22 2017 11:30AM
|
First Notice | | 11/1/2019 | | | |
|
|
|
|