Permit Information
Permit NumberBLD17-04634
StatusFinaled
Name K2 CONSTRUCTION
Site Address 800 W DIAMOND ST
Project NameAce Co. Break Room Addition
Customer Number 
ePlanReviewYes
Description
(ACECO MANUFACTURING - BREAK ROOM) (DRH17-00543) This building is fire sprinklered for fire area. Permit for a 717 sq ft addition with new break room and restrooms. Work to include: new exterior walls, roof, and concrete slab; new mechanical, electrical, and plumbing; related site work; interior finishes in compliance with Ch. 8 of the 2012 IBC. Special inspections are required per Form 310. The work is required to comply with the approved drawings, with the plan review report, with the structural design, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 6/21/20186/18/2018 DONE
This permit finaled on the web by Melanie Kreizenbeck
First Notice 6/10/20186/11/2018 DONE
mailed 6-12
BLD-Final5/30/20185/31/20185/31/2018APASS
DetailsJim Storey
Dennis Phone #: ###-####
Permanent Occupancy  5/31/2018 DONE
BLD-Final5/29/20185/30/20185/30/2018PDEFR
DetailsJim Storey
Dennis Phone #: ###-####
FIRE-Final Inspection5/30/20185/30/20185/30/2018APASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work complete.
Zoning Approval5/30/20185/30/20185/30/2018 DONE
DetailsAndrea Tuning
BLD-Other5/29/20185/30/20185/30/2018PCANC
DetailsJim Storey
Dennis Phone #: ###-####
BLD-Final5/25/20185/29/20185/29/2018PNR
DetailsJim Sly
Derek Phone #: ###-####
Need Zoning, Fire/life, Fire alarm, and plumbing finals. Cannot find Plumbing permit. Permit Techs cannot find Plumbing permit either. Notified Contractor.
FIRE-Final Inspection5/25/20185/29/20185/29/2018AFAIL
DetailsJim Page
Fire alarm panel was in alarm at time of inspection and fire panel would not reset, life fire safety inspection will need to be rescheduled after fire alarm issue is resolved.



Derek Phone #: ###-####
BLD-Final5/25/20185/29/20185/29/2018ACANC
DetailsJim Sly
Dennis- for landscape and zoning Phone #: ###-####
BLD-Energy code compliance5/1/20185/2/20185/2/2018PPASS
DetailsJim Storey
Steve---Dennis Peterson is the contact Phone #: ###-####
BLD-Framing/Rough-in4/25/20184/26/20184/26/2018PPASS
DetailsJim Storey
Steve Phone #: ###-#### insulation and slip sheet ok
BLD-Framing/Rough-in4/24/20184/25/20184/25/2018PPASS
DetailsJim Storey
Shawn Phone #: ###-#### roof nailling ok
BLD-Wall Bracing4/24/20184/25/20184/25/2018PPASS
DetailsJim Storey
Shawn Phone #: ###-#### wall nailling and hold downs ok
BLD-Foundation3/29/20183/30/20183/30/2018PPASS
DetailsJim Storey
rebar stem wall-Steve Phone #: ###-####
BLD-Footing3/28/20183/29/20183/29/2018PPASS
DetailsJim Storey
Rebar, pouring at 2:30 - Jay Phone #: ###-####
Print Occupancy Form  3/20/2018 DONE
Issue PAID IN FULL permit  3/20/2018 DONE
OVERRIDE  3/19/2018  
Plan assigned to (JAR)1/10/20181/10/20183/19/2018 DONE
DetailsJulie Romig
*1st Rev Comp - 2nd Rec'd 03/12 - 502 Ace Co Break Room Addition
Routing Off Site - STRUCTURAL3/12/2018 3/19/2018 PASS
DetailsJulie Romig
Passed per ePlanReview
PLANS/APPL TAKEN TO FRONT DESK  3/19/2018 DONE
Permit Ready to Issue  3/19/2018 DONE
MET
NEED
GC FORM
REVISED CERT
Routing - PLAN CHECK3/12/2018 3/12/2018 PASS
DetailsJulie Romig
Route to Impact Fee Review3/9/20183/12/20183/9/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  3/9/2018 FAIL
DetailsJulie Romig
Routing - PLAN CHECK1/10/2018 3/9/2018 FAIL
DetailsJulie Romig
Corrections required per ePlanReview. Plan Review report emailed to architect.
Routing - FIRE1/10/20181/10/20181/17/2018 PASS
DetailsErika Akin
Attached commetns to case
Routing Off Site - STRUCTURAL1/10/2018 1/15/2018 FAIL
DetailsJulie Romig
Corrections required per ePlanReview
Routing - Erosion and Sediment1/10/2018 1/11/2018 PASS
DetailsMichael Zawacki
RP needed.
Routing - PLUMBING1/10/2018 1/11/2018 PASS
DetailsDaryl Spivey
Per plan and ISPC
Routing - Addressing1/10/2018 1/10/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS1/10/2018 1/10/2018 PASS
DetailsMorgan Webb
Routing - MECHANICAL1/10/2018 1/10/2018 PASS
DetailsTroy James
Routing - Design Review1/10/2018 1/10/2018 PASS
DetailsKatelyn Menuge
DRH17-00543
Intake Approval  1/10/2018 PASS
DetailsAdele J Schaffeld-Griffin
Pre screen accepted by Julie
Application received  12/22/2017 DONE
Application submitted via PDS Online on Dec 22 2017 12:18PM