BLD-Final | 6/6/2018 | 6/7/2018 | 6/7/2018 | A | PASS |
Mike Jordan
|
|
|
Vince Phone #: ###-####
|
DOC - Permit Finaled | 6/7/2018 | 6/7/2018 | 6/7/2018 | P | PASS |
Mike Jordan
|
|
|
All issues resolved.
|
BLD-Final | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | FAIL |
Mike Jordan
|
|
|
vince Phone #: ###-####. Provide blower door test result and additional CO detector at front bedrooms.
|
BLD-Energy code compliance | 4/12/2018 | 4/13/2018 | 4/13/2018 | A | PASS |
Mike Jordan
|
|
|
Vince Phone #: ###-####
|
BLD-Framing/Rough-in | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PASS |
Mike Jordan
|
|
|
Vince Phone #: ###-####
|
BLD-Framing/Rough-in | 4/4/2018 | 4/4/2018 | 4/4/2018 | P | FAIL |
Mike Jordan
|
|
|
Vince Phone #: ###-####. Provide 2 studs under 2 ply E5 truss. ok to insulate. Correctio notice posted.
|
BLD-Wall Bracing | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | PASS |
Mike Jordan
|
|
|
Shear // Vince Phone #: ###-####
|
BLD-Footing | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Mike Jordan
|
|
|
Derek Phone #: ###-####
|
BLD-Footing | 1/9/2018 | 1/9/2018 | 1/9/2018 | P | CANC |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/8/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/8/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 1/2/2018 | | |
|
|
|
|
Plan assigned to (M_H) | 12/29/2017 | | 1/2/2018 | | DONE |
Michael Hanson
|
|
|
01/05 sfd L1 ePlan - Plan review completed 12/29 Mech=open MDH
|
Plan Reviewer's activity | | | 1/2/2018 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 1/2/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/2/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/2/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/22/2017 | | 1/2/2018 | | PASS |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 12/22/2017 | | 1/2/2018 | | PASS |
Troy James
|
|
|
|
Plan assigned to (BJM) | 12/22/2017 | 12/22/2017 | 12/29/2017 | | DEFR |
Brian McGowan
|
|
|
1/5 sfd L1 ePlan
|
Routing - PUBLIC WORKS | 12/22/2017 | | 12/27/2017 | | PASS |
Morgan Webb
|
|
|
|
Route to Impact Fee Review | 12/22/2017 | 12/25/2017 | 12/26/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 12/22/2017 | | 12/26/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 12/22/2017 | | 12/26/2017 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 12/22/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 22 2017 1:29PM
|
Plans ACCEPTED BY PLAN TECH | | | 12/22/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/22/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/22/2017 | | DONE |
|
|
|
|