BLD-Final | 6/27/2018 | 6/27/2018 | 6/28/2018 | P | DONE |
Tony Young
|
|
|
Andy Phone #: ###-####
|
BLD-Final | 6/26/2018 | 6/27/2018 | 6/27/2018 | A | PASS |
Tony Young
|
|
|
Andy Phone #: ###-####
|
DOC - Permit Finaled | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 6/25/2018 | 6/26/2018 | 6/26/2018 | A | PEND |
Tony Young
|
|
|
Andy Phone #: ###-####
|
BLD-Final | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | PART |
Tony Young
|
|
|
Andy Phone #: ###-####,, need trades,, needs fire caulking,, underfloor vapor barrier
|
BLD-Wall Bracing | 4/17/2018 | 4/17/2018 | 4/18/2018 | P | PASS |
Tony Young
|
|
|
interior shear, Andy; Phone #: ###-####
|
BLD-Wall Bracing | 4/16/2018 | 4/16/2018 | 4/16/2018 | P | NR |
Jim Storey
|
|
|
Andy Phone #: ###-####
|
BLD-Energy code compliance | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PASS |
Tony Young
|
|
|
Andy Phone #: ###-####
|
BLD-Framing/Rough-in | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | PART |
Tony Young
|
|
|
please call when on way // andy douglas Phone #: ###-####,, ok to insulate,, see paint notes
|
Plan Modification Accepted | | | 3/8/2018 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 3/8/2018 | | 3/8/2018 | | PASS |
Troy James
|
|
|
resubmitted acca report
|
BLD-Wall Bracing | 2/28/2018 | 3/1/2018 | 3/1/2018 | A | PASS |
Tony Young
|
|
|
Shear // Larry Phone #: ###-####
|
BLD-Foundation | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | PASS |
Jim Sly
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 1/30/2018 | 1/31/2018 | 1/31/2018 | A | PASS |
Tony Young
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 1/29/2018 | 1/30/2018 | 1/31/2018 | P | NR |
Tony Young
|
|
|
Matt Phone #: ###-####
|
BLD-Conference | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | PART |
Tony Young
|
|
|
want to check if staked correctly before start excavation // Ryan Phone #: ###-#### or call Andy ###-####,, looks ok but did not have reviewed plans
|
Issue PAID IN FULL permit | | | 1/17/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/17/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 1/12/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 12/29/2017 | 12/29/2017 | 1/12/2018 | | DONE |
Brian McGowan
|
|
|
1/15 resubmittal due.Needs to resubmit to Mechanical .1st review complete - 1/12 sfd L1 ePlan
|
Routing - MECHANICAL | 1/12/2018 | | 1/12/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 1/12/2018 | | 1/12/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 1/12/2018 | | DONE |
|
|
|
need RP
|
Routing - MECHANICAL | 1/10/2018 | | 1/10/2018 | | FAIL |
Troy James
|
|
|
Corrections have not been addressed.
|
1st review completed | | | 1/4/2018 | | FAIL |
Brian McGowan
|
|
|
Wall Bracing Issues
|
Routing - PLAN CHECK | 12/29/2017 | | 1/4/2018 | | FAIL |
Brian McGowan
|
|
|
Wall Bracing Issues
|
Routing - MECHANICAL | 12/29/2017 | | 1/3/2018 | | FAIL |
Troy James
|
|
|
|
Route to Impact Fee Review | 12/29/2017 | 1/1/2018 | 1/2/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 12/29/2017 | | 12/29/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 12/29/2017 | | 12/29/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/29/2017 | | 12/29/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 12/29/2017 | | FAIL |
Christina Prado
|
|
|
Need wall bracing & portal frame details
|
Plans ACCEPTED BY PLAN TECH | | | 12/29/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/29/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/29/2017 | | DONE |
|
|
|
|
Application received | | | 12/26/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 26 2017 11:10AM
|