BLD-Final | 8/27/2018 | 8/27/2018 | 8/27/2018 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by joey benart
|
DOC - Permit Finaled | 8/27/2018 | 8/27/2018 | 8/27/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 6/22/2018 | 6/25/2018 | 6/25/2018 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 6/21/2018 | 6/21/2018 | 6/21/2018 | P | PEND |
Brandon Shaw
|
|
|
Furnace flue to be moved at least 4' from 1hr roof assembly/property line and sealed.
|
Plan Modification Accepted | | | 6/21/2018 | | DONE |
|
|
|
revised acca report
|
Routing - MECHANICAL | 6/21/2018 | | 6/21/2018 | | PASS |
Chad Schwendiman
|
|
|
revised acca report
|
BLD-Wall Bracing | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | PASS |
Brandon Shaw
|
|
|
call when on way // Guillermo Phone #: ###-####
|
BLD-Foundation | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 2/2/2018 | 2/2/2018 | 2/2/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 1/22/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/22/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 1/18/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 12/29/2017 | 12/29/2017 | 1/18/2018 | | DONE |
Brian McGowan
|
|
|
1st review complete- need Mech sign off - 1/18 Townhome L2 ePlan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/18/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 1/18/2018 | | DONE |
|
|
|
do no issue without BLD17-04###-####
met
|
Routing - PLAN CHECK | 12/29/2017 | | 1/17/2018 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 1/17/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLANNING | 12/29/2017 | | 1/12/2018 | | PASS |
Sarah Schafer
|
|
|
|
Routing - MECHANICAL | 12/29/2017 | | 1/3/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 12/29/2017 | 1/1/2018 | 1/2/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 12/29/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/29/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/29/2017 | | DONE |
|
|
|
|
Routing - Addressing | 12/29/2017 | | 12/29/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/29/2017 | | 12/29/2017 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 12/28/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 28 2017 9:12AM
|