Meeting | | | 4/17/2020 | | DONE |
|
|
|
per Jim Story and Christina for mechanical see MEC19-02879
|
FIRE-Final Inspection | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work is complete, signature provided on permit sign off card.
Call ahead for Access - Ben Phone #: ###-####
|
FIRE-Final Inspection | 4/13/2020 | 4/15/2020 | 4/15/2020 | A | FAIL |
Troy Cobbley
|
|
|
I called the contact phone number and left message that I would be there at 8am. I arrived but no one was here and building is locked. I noted the address on the Howard Street side is missing, fire extinguishers are not mounted and are placed on the floor, exit signs do not appear to have power. These items were noted by view through the windows.
Benjamin Phone #: ###-####
Benjamin Phone #: ###-####
|
BLD-Final | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | NR |
Jim Storey
|
|
|
screened - Benjamin Phone #: ###-#### need sign offs and permits// need 2nd floor occ.
|
Print Occupancy Form | | | 4/10/2020 | | DONE |
|
|
|
|
BLD-Aging Inspection | 2/5/2020 | 2/5/2020 | 2/5/2020 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Energy code compliance | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | PASS |
Jim Storey
|
|
|
Eric Phone #: ###-####
|
BLD-Aging Inspection | 8/16/2019 | 8/16/2019 | 8/16/2019 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Wall Bracing | 5/9/2019 | 5/9/2019 | 5/9/2019 | P | NR |
Jim Storey
|
|
|
Eric - Sheer wall and roof sheeting Phone #: ###-#### ti permit
|
BLD-Foundation | 4/3/2019 | 4/4/2019 | 4/4/2019 | A | PASS |
Jim Storey
|
|
|
Eric Phone #: ###-#### vapor barrior under slab ok
|
Place hold on job | 5/2/2018 | | 11/19/2018 | | DONE |
Brittany Hill
|
|
|
DO NOT ISSUE WITHOUT GRD18-00009(has been issued) & BLD17-04650 (must split up values between building permits)
|
Issue PAID IN FULL permit | | | 11/19/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/19/2018 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/19/2018 | | DONE |
|
|
|
|
Extend Review Timeline | | | 6/25/2018 | | DONE |
|
|
|
1st Approved 180 day extension per Adele. See documents
|
Meeting | | | 6/19/2018 | | DONE |
|
|
|
EXTENSION REQUEST SENT IN
|
Expiration Notice | 6/4/2018 | 6/25/2018 | 6/4/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 5/2/2018 | | |
|
|
|
|
OVERRIDE | | | 5/2/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 1/16/2018 | 1/16/2018 | 5/2/2018 | | DONE |
Julie Romig
|
|
|
*1st Rev Comp - 3rd Rec'd - 502 Broadway Office - Benjamin Victor Studio
|
Routing - PLUMBING | 1/16/2018 | | 5/2/2018 | | PASS |
Bill VanDegrift
|
|
|
see bld17-04650
|
Routing PW Sewer Design | 4/30/2018 | | 5/2/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - MECHANICAL | 5/1/2018 | | 5/2/2018 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/2/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/2/2018 | | DONE |
|
|
|
NEED
ACHD (see attached email)(cant issue without ACHD approval/impact fees)
DO NOT ISSUE WITHOUT BLD17-04650
GC FORM-met
REVISED VALUE-met
|
Routing - PLAN CHECK | 4/30/2018 | | 5/1/2018 | | PASS |
Julie Romig
|
|
|
|
Routing PW Drainage | 4/12/2018 | | 5/1/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 4/12/2018 | | 4/23/2018 | | FAIL |
DeAnn Brown
|
|
|
Saddle taps are not allowed. ADS pipe is not appropriate for direct bury. Invert and manhole rim elevations appear incorrect per datum NAVD88. Please refer to changemarks in eplanreview and revise.
|
Routing - Erosion and Sediment | 4/12/2018 | | 4/20/2018 | | PASS |
Michael Zawacki
|
|
|
RP needed before ground disturbing activities begin.
|
Routing - PLAN CHECK | 4/12/2018 | | 4/20/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 4/12/2018 | | 4/18/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
Routing - MECHANICAL | 1/16/2018 | | 4/18/2018 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 1/16/2018 | | 4/18/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING | 4/12/2018 | | 4/17/2018 | | PASS |
Celine Acord
|
|
|
per CUP16-00078 and CVA16-00059
|
1st review completed | | | 3/15/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 1/16/2018 | | 3/15/2018 | | FAIL |
Julie Romig
|
|
|
Corrections required per ePlanReview
|
Routing PW Environmental | 1/17/2018 | | 2/2/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - FIRE | 1/16/2018 | 1/16/2018 | 1/18/2018 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Routing - PLANNING | 1/16/2018 | | 1/17/2018 | | FAIL |
Leon Letson
|
|
|
Failed per ePlanReview
|
Routing - Addressing | 1/16/2018 | | 1/17/2018 | | PASS |
Doug Chausow
|
|
|
Address 2227 S Broadway Ave
|
Routing - PUBLIC WORKS | 1/16/2018 | | 1/17/2018 | | PASS |
Rachael Beierle
|
|
|
permit inside shell. c/o needs to be reviewed by RWC.
|
Intake Approval | | | 1/16/2018 | | PASS |
|
|
|
|
Application received | | 12/29/2017 | | | |
|
|
|
|
Application received | | 12/29/2017 | | | |
|
|
|
|