BLD-Final | 11/16/2018 | 11/19/2018 | 11/20/2018 | A | PASS |
Dave Hannah
|
|
|
Tom Phone #: ###-#### ok after zoning finals
|
Zoning Approval | 11/20/2018 | 11/20/2018 | 11/20/2018 | | DONE |
Andrea Tuning
|
|
|
|
Letter of compliance/Occupancy | | | 11/20/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/15/2018 | 11/16/2018 | 11/16/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, no fire alarm modifications for this project, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
Tom Phone #: ###-####
|
BLD-Final | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | NR |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 9/11/2018 | 9/12/2018 | 9/12/2018 | A | PASS |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
OVERRIDE | | | 9/10/2018 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/10/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/10/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/10/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/10/2018 | | DONE |
|
|
|
PLAN MOD
|
Plan assigned to (JAR) | 8/28/2018 | 8/28/2018 | 9/8/2018 | | DONE |
Julie Romig
|
|
|
09/10 - Plan Mod - Capitol Terrace Facade Improvements
|
Routing - PLAN CHECK | 9/4/2018 | | 9/8/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - Design Review | 9/4/2018 | | 9/4/2018 | | PASS |
Andrea Tuning
|
|
|
|
BLD-Framing/Rough-in | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | PART |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
Plan Modification Accepted | | | 8/28/2018 | | DONE |
|
|
|
Plan Mod - As part of the replacement of the exterior canopies some existing intake louvers will need to be moved. At Taphouse the existing louvers will be removed and replaced with louvers that match the new paint color and design. These new louvers will require minor modifications to the existing interior transition ductwork as shown on details.
|
BLD-Framing/Rough-in | 7/20/2018 | 7/23/2018 | 7/24/2018 | A | PASS |
Dave Hannah
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 7/11/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Dave Hannah
|
|
|
Tom Phone #: ###-#### ok to south end
|
Issue PAID IN FULL permit | | | 5/17/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 4/25/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 1/22/2018 | 1/22/2018 | 4/25/2018 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 2nd Comp - L3 Capitol Terrace Canopy Additions
|
Routing - PLAN CHECK | 4/25/2018 | | 4/25/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/25/2018 | | DONE |
|
|
|
Need- all met
GC Form
Revised Cert of Value
RP-MET
ACHD-MET
|
Routing Off Site - STRUCTURAL | 3/19/2018 | | 3/29/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 3/22/2018 | | 3/22/2018 | | FAIL |
Julie Romig
|
|
|
Need verification of ACHD/CCDC agreements.
|
Routing - PLUMBING | 3/21/2018 | | 3/21/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Design Review | 3/19/2018 | | 3/19/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Erosion and Sediment | 1/22/2018 | | 3/19/2018 | | PASS |
Michael Zawacki
|
|
|
Waiver request approved. On site manager responsible for following actions listed in waiver request.
|
Route to Impact Fee Review | 3/7/2018 | 3/10/2018 | 3/8/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 3/7/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 1/22/2018 | | 3/7/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - Addressing | 1/22/2018 | | 3/6/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing Off Site - STRUCTURAL | 1/22/2018 | | 1/31/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLUMBING | 1/22/2018 | | 1/25/2018 | | FAIL |
Bill VanDegrift
|
|
|
ISPC table 1101b- minimum horizontal rain water piping is 3".
|
Routing - FIRE | 1/22/2018 | 1/22/2018 | 1/24/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Street Lights | 1/23/2018 | | 1/24/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Drainage | 1/23/2018 | | 1/23/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Solid Waste | 1/23/2018 | | 1/23/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PUBLIC WORKS | 1/22/2018 | | 1/23/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 1/22/2018 | | 1/23/2018 | | FAIL |
Andrea Tuning
|
|
|
The proposed building materials do not match the Design Review approval.
|
Intake Approval | | | 1/22/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie accepted pre screen
|
Plan Reviewer's activity | | | 1/19/2018 | | DONE |
Julie Romig
|
|
|
Application is a 520 Major TI for exterior improvements to an existing buidling, not a 502 new construction.
|
Application received | | | 12/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 29 2017 8:49AM
|