Permit Information
Permit NumberBLD17-04695
StatusFinaled
Name ELDA PROPERTY SERVICES LLC
Site Address 4712 W STATE ST
Project NameTreasure Valley Skate - TI
Customer Number 
ePlanReviewYes
Description
(TREASURE VALLEY SKATE – ROLLER SKATING RINK) (5-30-18 PLAN MODIFICATION TO ADD A TYPE II HOOD OVER A PIZZA OVEN IN THE KITCHEN.) The fire sprinkler system is used for building area increase and for fire area. Interior nonstructural demolition work was done under permit BLD17-04501. To convert a former bowling alley to an 20,263 square foot indoor roller skating rink facility. Work is to include interior nonbearing walls, two muli-user toilet rooms upgraded to be accessible to the disabled, a reinforced concrete ramp accessible to the disabled as an accessible route and using geofoam as a filler, a reinforced concrete ramp used for egress and using geofoam as a filler but not necessarily complying as an accessible means of egress, reinforced concrete steps, new roof top HVAC units installed directly above existing glulam girders, floor coverings, millwork, and interior wall finishes. Cooking operations that create grease laden vapors are not allowed within this building. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Meeting  10/29/2018 DONE
Emailed Elda Property Services about final values given. Values might be switched or demo value included in TI.
Third Notice 9/15/201810/12/2018 DONE
mailed 10-15-18
First Follow up  10/12/2018 DONE
Third Notice 8/12/20189/10/2018 DONE
mailed 9-11-18
Third Notice 7/16/20188/7/2018 DONE
mailed 8-10-18
Second Notice 6/21/20187/11/2018 DONE
mailed 7-12-18
First Notice 6/11/20186/11/2018 DONE
mailed 6-12
BLD-Final6/1/20186/1/20186/1/2018PPASS
DetailsTony Young
Dan Phone #: ###-####
BLD-Final5/31/20186/1/20186/1/2018ANR
DetailsTony Young
Dan Phone #: ###-####
Permanent Occupancy  6/1/2018 DONE
BLD-Final5/31/20185/31/20185/31/2018PNR
DetailsTony Young
Dan Phone #: ###-####,, walk through,, needs hood passed
FIRE-Final Inspection5/30/20185/31/20185/31/2018APASS
DetailsJim Page
Fire sprinkle rinspection complete, fire alarm inspection complete, fire extinguishers are mounted with current inspection tags, building has an existing knox box in place. Signage will be placed above FDC noting that FDC is for this address only. Final life fire safety inspection complete.

Dan Phone #: ###-####
OVERRIDE  5/30/2018  
Plan assigned to (CJW)5/11/20185/11/20185/30/2018 PASS
DetailsCarl Westfall
x (2nd done) plan mod - Treasure Valley Skate
CHANGE STATUS TO (ISS)  5/30/2018 DONE
Print Occupancy Form  5/30/2018 DONE
Plan Reviewer's activity  5/30/2018 PASS
Plan mod approved
Permit Ready to Issue  5/30/2018 DONE
Plan Mod Approved
DO NOT REISSUE
Routing PW Environmental5/23/2018 5/29/2018 PASS
DetailsTerry Alber
Point-source grease trap connected to three compartment sink REQUIRED. It should be sized according to plumbing code.
Routing - PLAN CHECK5/22/2018 5/23/2018 PASS
DetailsCarl Westfall
Routing Off Site - C.D.H5/23/2018 5/23/2018 PASS
DetailsCarl Westfall
Scott Paradis
Routing PW Sewer Rating5/23/2018 5/23/2018 PASS
DetailsRachael Beierle
added hand sink. credits exist for food service.
Routing - PUBLIC WORKS5/23/2018 5/23/2018 PASS
DetailsRachael Beierle
Routing Off Site - C.D.H5/14/2018 5/22/2018 FAIL
DetailsCarl Westfall
Scott Paradis
Plan resubmittals requested  5/22/2018 DONE
Plan resubmittals received  5/22/2018 DONE
Routing - MECHANICAL5/14/2018 5/17/2018 PASS
DetailsTroy James
Routing - FIRE5/14/20185/14/20185/16/2018 PASS
DetailsErika Akin
Plan mod to install a Type II hood. No change to previous comments. Inspector to field verify.
Routing PW Environmental5/14/2018 5/16/2018 PASS
DetailsRick Christenson
Point-source grease trap connected to the three compartment sink REQUIRED. It should be sized according to plumbing code.
Routing PW Sewer Rating5/14/2018 5/15/2018 PASS
DetailsRachael Beierle
Perhaps a change in menu
Routing - PUBLIC WORKS5/14/2018 5/15/2018 PASS
DetailsRachael Beierle
No additional impact after mod review. menu and equipment schedule is uploaded in OnBase.
Routing - PLAN CHECK5/11/2018 5/14/2018 PASS
DetailsCarl Westfall
1st plan mod. Only about 220 pounds will be added to the roof.
Plan Modification Accepted  5/11/2018 DONE
plan modification to add hood in kitchen
BLD-Ceiling Grid Inspection5/3/20185/3/20185/3/2018PDONE
DetailsTony Young
Call half hour before // Dan Phone #: ###-####
BLD-Framing/Rough-in3/29/20183/29/20183/29/2018PPASS
DetailsTony Young
Call 15 mins. before // Dan Phone #: ###-####,, walls ok to cover,, recieved letter on changes
BLD-Conference3/21/20183/22/20183/22/2018APART
DetailsTony Young
Dan-pleae call 15 minutes prior to meet Phone #: ###-####,, ok to one side interior walls,, some may have electrical,, need a letter of ok on the 2x4 wall .vs 2x6,, went over ramp slopes,, ok if per plan
OVERRIDE  3/21/2018  
Plan assigned to (CJW)1/3/20181/3/20183/21/2018 PASS
DetailsCarl Westfall
(1st review) (Jan 23 - 15 days) (41 sheets) TV Skating Rink
Print Occupancy Form  3/21/2018 DONE
Issue PAID IN FULL permit  3/21/2018 DONE
Routing - PLAN CHECK3/20/2018 3/21/2018 PASS
DetailsCarl Westfall
Approved after 2nd review
PLANS/APPL TAKEN TO FRONT DESK  3/21/2018 DONE
Permit Ready to Issue  3/21/2018 DONE
Need
Revised Cert of Value
RP
GC Form
Plan resubmittals received  3/20/2018 DONE
Route to Impact Fee Review3/5/20183/8/20183/6/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  3/5/2018 DONE
Plan resubmittals requested  3/5/2018 DONE
Routing - PLAN CHECK2/13/2018 3/5/2018 FAIL
DetailsCarl Westfall
Routing Off Site - STRUCTURAL2/14/2018 2/20/2018 PASS
DetailsCarl Westfall
Dave Haugland (AHJ) - Drawings changed
Routing - PLUMBING2/14/2018 2/15/2018 PASS
DetailsBill VanDegrift
Drawings changed
Routing - MECHANICAL2/14/2018 2/15/2018 PASS
DetailsTroy James
Demand control ventilation installed to new air handlers.
Plan resubmittals received  2/13/2018 DONE
Plan resubmittals requested  1/23/2018 DONE
Routing - PLAN CHECK1/3/2018 1/23/2018 FAIL
DetailsCarl Westfall
The applicant wanted the workflow sent back to him so that he could upload additional drawings. The IBC plan review has NOT been done. The 1st review is NOT completed. When he resubmits, the IBC plan review will be done. Route it back to all applicable agencies.
Routing Off Site - STRUCTURAL1/3/2018 1/16/2018 PASS
DetailsCarl Westfall
Dave Haugland (AHJ)
Routing - MECHANICAL1/3/2018 1/11/2018 PASS
DetailsTroy James
Routing - FIRE1/3/20181/3/20181/10/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - PLUMBING1/3/2018 1/5/2018 PASS
DetailsBill VanDegrift
additional plumbing may be required. Plan is not showing existing. Install per plan and ISPC, verify premise protection, additional cross connection protection may be required.
Routing - Addressing1/3/2018 1/3/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS1/3/2018 1/3/2018 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment1/3/2018 1/3/2018 PASS
DetailsAndy J. Long
ESC plan waiver approved for demo work under BLD17-04501 and -04695. Need to designate RP.
Plan Reviewer's activity  1/3/2018 DONE
DetailsAdele J Schaffeld-Griffin
email sent to applicant Matt to verify fees with ACHD.
Intake Approval  1/3/2018 PASS
DetailsAdele J Schaffeld-Griffin
Julie accepted pre screen CDH approvals uploaded with submittal
Application received  12/29/2017 DONE
Application submitted via PDS Online on Dec 29 2017 12:39PM
Routing Off Site - C.D.H12/18/2017 12/18/2017 PASS
Scott Paradis approved before submission to Boise City