Meeting | | | 10/29/2018 | | DONE |
|
|
|
Emailed Elda Property Services about final values given. Values might be switched or demo value included in TI.
|
Third Notice | | 9/15/2018 | 10/12/2018 | | DONE |
|
|
|
mailed 10-15-18
|
First Follow up | | | 10/12/2018 | | DONE |
|
|
|
|
Third Notice | | 8/12/2018 | 9/10/2018 | | DONE |
|
|
|
mailed 9-11-18
|
Third Notice | | 7/16/2018 | 8/7/2018 | | DONE |
|
|
|
mailed 8-10-18
|
Second Notice | | 6/21/2018 | 7/11/2018 | | DONE |
|
|
|
mailed 7-12-18
|
First Notice | | 6/11/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
BLD-Final | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Tony Young
|
|
|
Dan Phone #: ###-####
|
BLD-Final | 5/31/2018 | 6/1/2018 | 6/1/2018 | A | NR |
Tony Young
|
|
|
Dan Phone #: ###-####
|
Permanent Occupancy | | | 6/1/2018 | | DONE |
|
|
|
|
BLD-Final | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | NR |
Tony Young
|
|
|
Dan Phone #: ###-####,, walk through,, needs hood passed
|
FIRE-Final Inspection | 5/30/2018 | 5/31/2018 | 5/31/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkle rinspection complete, fire alarm inspection complete, fire extinguishers are mounted with current inspection tags, building has an existing knox box in place. Signage will be placed above FDC noting that FDC is for this address only. Final life fire safety inspection complete.
Dan Phone #: ###-####
|
OVERRIDE | | | 5/30/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 5/11/2018 | 5/11/2018 | 5/30/2018 | | PASS |
Carl Westfall
|
|
|
x (2nd done) plan mod - Treasure Valley Skate
|
CHANGE STATUS TO (ISS) | | | 5/30/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/30/2018 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 5/30/2018 | | PASS |
|
|
|
Plan mod approved
|
Permit Ready to Issue | | | 5/30/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
Routing PW Environmental | 5/23/2018 | | 5/29/2018 | | PASS |
Terry Alber
|
|
|
Point-source grease trap connected to three compartment sink REQUIRED. It should be sized according to plumbing code.
|
Routing - PLAN CHECK | 5/22/2018 | | 5/23/2018 | | PASS |
Carl Westfall
|
|
|
|
Routing Off Site - C.D.H | 5/23/2018 | | 5/23/2018 | | PASS |
Carl Westfall
|
|
|
Scott Paradis
|
Routing PW Sewer Rating | 5/23/2018 | | 5/23/2018 | | PASS |
Rachael Beierle
|
|
|
added hand sink. credits exist for food service.
|
Routing - PUBLIC WORKS | 5/23/2018 | | 5/23/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing Off Site - C.D.H | 5/14/2018 | | 5/22/2018 | | FAIL |
Carl Westfall
|
|
|
Scott Paradis
|
Plan resubmittals requested | | | 5/22/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/22/2018 | | DONE |
|
|
|
|
Routing - MECHANICAL | 5/14/2018 | | 5/17/2018 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 5/14/2018 | 5/14/2018 | 5/16/2018 | | PASS |
Erika Akin
|
|
|
Plan mod to install a Type II hood. No change to previous comments. Inspector to field verify.
|
Routing PW Environmental | 5/14/2018 | | 5/16/2018 | | PASS |
Rick Christenson
|
|
|
Point-source grease trap connected to the three compartment sink REQUIRED. It should be sized according to plumbing code.
|
Routing PW Sewer Rating | 5/14/2018 | | 5/15/2018 | | PASS |
Rachael Beierle
|
|
|
Perhaps a change in menu
|
Routing - PUBLIC WORKS | 5/14/2018 | | 5/15/2018 | | PASS |
Rachael Beierle
|
|
|
No additional impact after mod review. menu and equipment schedule is uploaded in OnBase.
|
Routing - PLAN CHECK | 5/11/2018 | | 5/14/2018 | | PASS |
Carl Westfall
|
|
|
1st plan mod. Only about 220 pounds will be added to the roof.
|
Plan Modification Accepted | | | 5/11/2018 | | DONE |
|
|
|
plan modification to add hood in kitchen
|
BLD-Ceiling Grid Inspection | 5/3/2018 | 5/3/2018 | 5/3/2018 | P | DONE |
Tony Young
|
|
|
Call half hour before // Dan Phone #: ###-####
|
BLD-Framing/Rough-in | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | PASS |
Tony Young
|
|
|
Call 15 mins. before // Dan Phone #: ###-####,, walls ok to cover,, recieved letter on changes
|
BLD-Conference | 3/21/2018 | 3/22/2018 | 3/22/2018 | A | PART |
Tony Young
|
|
|
Dan-pleae call 15 minutes prior to meet Phone #: ###-####,, ok to one side interior walls,, some may have electrical,, need a letter of ok on the 2x4 wall .vs 2x6,, went over ramp slopes,, ok if per plan
|
OVERRIDE | | | 3/21/2018 | | |
|
|
|
|
Plan assigned to (CJW) | 1/3/2018 | 1/3/2018 | 3/21/2018 | | PASS |
Carl Westfall
|
|
|
(1st review) (Jan 23 - 15 days) (41 sheets) TV Skating Rink
|
Print Occupancy Form | | | 3/21/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/21/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/20/2018 | | 3/21/2018 | | PASS |
Carl Westfall
|
|
|
Approved after 2nd review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/21/2018 | | DONE |
|
|
|
Need
Revised Cert of Value
RP
GC Form
|
Plan resubmittals received | | | 3/20/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/5/2018 | 3/8/2018 | 3/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 3/5/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/5/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/13/2018 | | 3/5/2018 | | FAIL |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 2/14/2018 | | 2/20/2018 | | PASS |
Carl Westfall
|
|
|
Dave Haugland (AHJ) - Drawings changed
|
Routing - PLUMBING | 2/14/2018 | | 2/15/2018 | | PASS |
Bill VanDegrift
|
|
|
Drawings changed
|
Routing - MECHANICAL | 2/14/2018 | | 2/15/2018 | | PASS |
Troy James
|
|
|
Demand control ventilation installed to new air handlers.
|
Plan resubmittals received | | | 2/13/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/23/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/3/2018 | | 1/23/2018 | | FAIL |
Carl Westfall
|
|
|
The applicant wanted the workflow sent back to him so that he could upload additional drawings. The IBC plan review has NOT been done. The 1st review is NOT completed. When he resubmits, the IBC plan review will be done. Route it back to all applicable agencies.
|
Routing Off Site - STRUCTURAL | 1/3/2018 | | 1/16/2018 | | PASS |
Carl Westfall
|
|
|
Dave Haugland (AHJ)
|
Routing - MECHANICAL | 1/3/2018 | | 1/11/2018 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 1/3/2018 | 1/3/2018 | 1/10/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLUMBING | 1/3/2018 | | 1/5/2018 | | PASS |
Bill VanDegrift
|
|
|
additional plumbing may be required. Plan is not showing existing. Install per plan and ISPC, verify premise protection, additional cross connection protection may be required.
|
Routing - Addressing | 1/3/2018 | | 1/3/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/3/2018 | | 1/3/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 1/3/2018 | | 1/3/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved for demo work under BLD17-04501 and -04695. Need to designate RP.
|
Plan Reviewer's activity | | | 1/3/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
email sent to applicant Matt to verify fees with ACHD.
|
Intake Approval | | | 1/3/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie accepted pre screen CDH approvals uploaded with submittal
|
Application received | | | 12/29/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 29 2017 12:39PM
|
Routing Off Site - C.D.H | 12/18/2017 | | 12/18/2017 | | PASS |
|
|
|
Scott Paradis approved before submission to Boise City
|