Print Occupancy Form | | | 11/16/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Inspection Record Card- Bld | | | 11/16/2018 | | DONE |
|
|
|
|
Print Statement | | | 5/25/2018 | | DONE |
|
|
|
|
First Notice | | 5/10/2018 | 5/11/2018 | | DONE |
|
|
|
mailed 5-14
|
BLD-Final | 4/27/2018 | 4/30/2018 | 4/30/2018 | P | PASS |
Tony Young
|
|
|
Greg Phone #: ###-####
|
Permanent Occupancy | | | 4/30/2018 | | DONE |
|
|
|
|
BLD-Final | 4/24/2018 | 4/24/2018 | 4/24/2018 | P | NR |
Tony Young
|
|
|
Greg Phone #: ###-####
|
BLD-Final | 4/23/2018 | 4/24/2018 | 4/24/2018 | A | NR |
Tony Young
|
|
|
Greg Phone #: ###-####
|
FIRE-Final Inspection | 4/20/2018 | 4/20/2018 | 4/20/2018 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection for area of work complete.
|
BLD-Other | 4/12/2018 | 4/13/2018 | 4/13/2018 | A | PASS |
Dave Hannah
|
|
|
t-bar grid- Greg Phone #: ###-####
|
BLD-Framing/Rough-in | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PASS |
Jim Sly
|
|
|
Greg Phone #: ###-####
|
BLD-Conference | 3/19/2018 | 3/20/2018 | 3/20/2018 | P | DONE |
Jim Sly
|
|
|
Greg Phone #: ###-####
|
Routing - PLAN CHECK | 2/27/2018 | | 2/28/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/28/2018 | | DONE |
|
|
|
ALL MET-Need
GC Form-met
Revised Cert of Value-met
|
Print Occupancy Form | | | 2/28/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/28/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 2/13/2018 | 2/13/2018 | 2/27/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 2/20 L3 The Joint Chiropractor TI ePlan
|
Routing - PLAN CHECK | 2/27/2018 | | 2/27/2018 | | PASS |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 2/17/2018 | 2/20/2018 | 2/20/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/17/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 1/11/2018 | | 2/17/2018 | | FAIL |
Javier Guzman
|
|
|
|
Plan assigned to (CJW) | 1/11/2018 | 1/11/2018 | 2/13/2018 | | DEFR |
Carl Westfall
|
|
|
(Jan 31 - 15 days) (34 sheets) The Joint Chiropractor TI
|
Routing - FIRE | 1/11/2018 | 1/11/2018 | 1/17/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - Erosion and Sediment | 1/11/2018 | | 1/12/2018 | | PASS |
Andy J. Long
|
|
|
No ESC permit required, no exterior excavation/disturbance in scope of project. If stormwater pollution violations are found at site, a permit shall be required.
|
Intake Approval | | | 1/11/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Javier accepted pre screen
|
Routing - MECHANICAL | 1/11/2018 | | 1/11/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/11/2018 | | 1/11/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 1/11/2018 | | 1/11/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/11/2018 | | 1/11/2018 | | PASS |
Morgan Webb
|
|
|
|
Plan Reviewer's activity | | | 1/11/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Emailed Jeff Likes to contact ACHD in regards to fee's.
|
Application received | | | 1/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 1 2018 8:19PM
|