BLD-Energy code compliance | 3/29/2018 | 3/30/2018 | 3/30/2018 | A | PASS |
Jim Storey
|
|
|
Dusty Phone #: ###-####
|
BLD-Wall Bracing | 3/26/2018 | 3/27/2018 | 3/27/2018 | P | PASS |
Tony Young
|
|
|
Dusty Phone #: ###-####
|
BLD-Framing/Rough-in | 3/26/2018 | 3/27/2018 | 3/27/2018 | P | PASS |
Tony Young
|
|
|
Dusty Phone #: ###-####
|
BLD-Foundation | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PASS |
Tony Young
|
|
|
John Phone #: ###-####
|
BLD-Footing | 2/15/2018 | 2/15/2018 | 2/15/2018 | P | PASS |
Tony Young
|
|
|
John Phone #: ###-####
|
PubWorks Subgrade Approval | 2/14/2018 | 2/14/2018 | 2/14/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 2/6/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 1/29/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 1/4/2018 | 1/4/2018 | 1/29/2018 | | PASS |
Josh Bogle
|
|
|
1st done - PC done (2nd cycle)
|
Routing PW Grading-Hillside | 1/22/2018 | | 1/29/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 1/29/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/22/2018 | | 1/23/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLANNING | 1/22/2018 | | 1/22/2018 | | PASS |
Sue Cummings
|
|
|
Setback met 1/22/18
|
Routing PW Grading-Hillside | 1/4/2018 | | 1/9/2018 | | FAIL |
Jason C. Taylor
|
|
|
See changemarks for details. JCT
|
1st review completed | | | 1/9/2018 | | DONE |
Josh Bogle
|
|
|
|
Routing - Erosion and Sediment | 1/8/2018 | | 1/8/2018 | | PASS |
Michael Zawacki
|
|
|
Site prep required.
|
Routing - PUBLIC WORKS | 1/4/2018 | | 1/4/2018 | | PASS |
Morgan Webb
|
|
|
CONNECTED TO SEWER
|
Routing - PLAN CHECK | 1/4/2018 | | 1/4/2018 | | FAIL |
Josh Bogle
|
|
|
|
Intake Approval | | | 1/4/2018 | | FAIL |
|
|
|
The site plan needs to have the measurements from the house to the property lines. 1-4-18
|
Plans ACCEPTED BY PLAN TECH | | | 1/4/2018 | | DONE |
|
|
|
|
Intake Approval | | | 1/4/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/4/2018 | | DONE |
|
|
|
no fees taken at intake
|
Application received | | | 1/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 3 2018 8:17AM
|
Intake Approval | | | 1/3/2018 | | FAIL |
|
|
|
Missing
Site Plan
Floor Plan for after addition
|
Routing - PLANNING | 1/4/2018 | | | | FAIL |
|
|
|
Needs to meet 7 ft. side yard setback as noted on the plat.
|