BLD-Final | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | PASS |
Tony Young
|
|
|
Ben Phone #: ###-####
|
DOC - Permit Finaled | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | PASS |
Tony Young
|
|
|
c of o issued
|
PubWorks Occupancy Approval | 7/11/2018 | 7/11/2018 | 7/11/2018 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####
|
BLD-Final | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | NR |
Tony Young
|
|
|
Ben Phone #: ###-####,, need trades,, hillside
|
BLD-Energy code compliance | 4/5/2018 | 4/6/2018 | 4/6/2018 | A | PASS |
Tony Young
|
|
|
Ben Phone #: ###-####
|
BLD-Other | 4/4/2018 | 4/5/2018 | 4/5/2018 | A | PART |
Tony Young
|
|
|
soffit-Toby-leave tag if passed Phone #: ###-####,, sheet rock soffit areas ok,, other section will be fire rated tongue and groove,, still to verify,, needs rated vents in soffits by the final
|
BLD-Framing/Rough-in | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | PASS |
Tony Young
|
|
|
Van Phone #: ###-####,, ok to insulate
|
BLD-Framing/Rough-in | 3/28/2018 | 3/28/2018 | 3/28/2018 | A | FAIL |
Mike Jordan
|
|
|
Complete lateral bracing on A03 trusses. Complete all corrections as identified per Tony Young. Ok to insualte. Correction notice posted.
|
BLD-Framing/Rough-in | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | CANC |
Mike Jordan
|
|
|
Ben Phone #: ###-####. rescheduled. wrong entry.
|
BLD-Framing/Rough-in | 3/22/2018 | 3/22/2018 | 3/22/2018 | P | NR |
Tony Young
|
|
|
Ben Phone #: ###-####,, needs mech pass,, dont insulate,, partial walk through
|
BLD-Wall Bracing | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PART |
Tony Young
|
|
|
BEN Phone #: ###-####,, exterior ok to cover,, may need interior later
|
BLD-Wall Bracing | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | NR |
Tony Young
|
|
|
BEN Phone #: ###-####,, re do per plan
|
Plan Modification Accepted | | | 3/1/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 3/1/2018 | | 3/1/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Foundation | 2/11/2018 | 2/12/2018 | 2/13/2018 | P | PART |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo,, work in progress,, ok
|
BLD-Footing | 2/8/2018 | 2/9/2018 | 2/9/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
PubWorks Subgrade Approval | 2/9/2018 | 2/9/2018 | 2/9/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 2/2/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/2/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/2/2018 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 1/22/2018 | | 2/2/2018 | | DONE |
Michael Hanson
|
|
|
01/31 sfd L2 ePlan 1st review completed. Return to applicant - spray foam, foundation, hillside. MDH
|
Routing PW Grading-Hillside | 2/2/2018 | | 2/2/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - PLAN CHECK | 2/2/2018 | | 2/2/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/2/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 2/2/2018 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 1/26/2018 | | 1/26/2018 | | FAIL |
Jason C. Taylor
|
|
|
|
Plan Reviewer's activity | | | 1/23/2018 | | FAIL |
Michael Hanson
|
|
|
|
1st review completed | | | 1/23/2018 | | DONE |
Michael Hanson
|
|
|
RTA - spray foam, foundation, hillside. MDH
|
Routing - PLAN CHECK | 1/11/2018 | | 1/23/2018 | | FAIL |
Michael Hanson
|
|
|
RTA - spray foam, foundation, hillside. MDH
|
Plan assigned to (BJM) | 1/11/2018 | 1/11/2018 | 1/22/2018 | | DEFR |
Brian McGowan
|
|
|
1/31 sfd L2 Eplan
|
Routing - FIRE | 1/11/2018 | 1/11/2018 | 1/17/2018 | | PASS |
Scott Arellano
|
|
|
No comments. Approved as shown.
|
Route to Impact Fee Review | 1/11/2018 | 1/14/2018 | 1/12/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Erosion and Sediment | 1/11/2018 | | 1/12/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid certified RP and PD. Site preparation inspection is REQUIRED prior to excavation.
|
Routing PW Grading-Hillside | 1/11/2018 | | 1/11/2018 | | FAIL |
Jason C. Taylor
|
|
|
see changemarks in ePlan. JCT
|
Routing - MECHANICAL | 1/11/2018 | | 1/11/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/11/2018 | | 1/11/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 1/11/2018 | | 1/11/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/11/2018 | | 1/11/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/11/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/11/2018 | | DONE |
|
|
|
|
Intake Approval | | | 1/11/2018 | | PASS |
|
|
|
|
Intake Approval | | | 1/8/2018 | | FAIL |
|
|
|
WUI fire rated soffits, 2012 IRC review request letter
|
Application received | | | 1/4/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 4 2018 11:04AM
|