First Notice | | 4/16/2018 | 4/16/2018 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
Permanent Occupancy | | | 4/6/2018 | | DONE |
|
|
|
|
BLD-Final | 4/5/2018 | 4/5/2018 | 4/5/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Gerome Fries OK for Perm Occ.
|
BLD-Final | 4/3/2018 | 4/3/2018 | 4/3/2018 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Gerome Fries OK for Temp. Occ. OK for Perm Occ. when large glass window wall is installed and inspected.
|
FIRE-Final Inspection | 4/2/2018 | 4/3/2018 | 4/3/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Call for access. Phone #: ###-#### Inspection requested via web by Gerome Fries
|
BLD-Ceiling Grid Inspection | 3/23/2018 | 3/26/2018 | 3/26/2018 | A | PART |
Dave Hannah
|
|
|
Please call 30 mins prior. Phone #: ###-#### Inspection requested via web by Gerome Fries ok to flood ceiling but need to add clips or spreader bar on edges
|
BLD-Framing/Rough-in | 2/13/2018 | 2/14/2018 | 2/15/2018 | P | PASS |
Jim Sly
|
|
|
Jermery Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/9/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/9/2018 | | DONE |
|
|
|
|
Telephone call | | | 2/8/2018 | | DONE |
|
|
|
Glenn called wanted to know where his permit was in review process-told him we needed the GC to fill out the 302 & 306 forms
|
Plan assigned to (RMH) | 1/19/2018 | 1/19/2018 | 1/19/2018 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (JG) | 1/9/2018 | 1/9/2018 | 1/19/2018 | | DEFR |
Javier Guzman
|
|
|
1/19 L1 Royal Jay Suite #250 ePlan*
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/19/2018 | | DONE |
|
|
|
MET
Need:
GC form
Rev cert value
|
Routing - PLAN CHECK | 1/13/2018 | | 1/19/2018 | | PASS |
Ron Hill
|
|
|
|
Routing - Addressing | 1/13/2018 | | 1/16/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/13/2018 | | 1/16/2018 | | PASS |
Rachael Beierle
|
|
|
DEMO BREAK SINK ADDING SHOWER. NO NEW FEES.
|
Route to Impact Fee Review | 1/9/2018 | 1/12/2018 | 1/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 1/9/2018 | | 1/9/2018 | | FAIL |
Javier Guzman
|
|
|
At request of architect the floor plan will be changing and wanted me to send project back before any reviews
|
1st review completed | | | 1/9/2018 | | FAIL |
Javier Guzman
|
|
|
|
Intake Approval | | | 1/9/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 1/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 5 2018 10:31AM
|