Change Expiration Date Only | | | 7/15/2020 | | DONE |
Jason Blais
|
|
|
First 180 day extension for an issued permit approved.
|
BLD-Aging Inspection | 1/3/2020 | 1/3/2020 | 1/3/2020 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Aging Inspection | 8/22/2019 | 8/22/2019 | 8/22/2019 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Aging Inspection | 8/21/2019 | 8/21/2019 | 8/22/2019 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Other | 6/28/2019 | 7/1/2019 | 7/1/2019 | A | PART |
Jim Storey
|
|
|
Marla- inspection for interior Phone #: ###-#### inside ok pending outside roofs
|
BLD-Aging Inspection | 4/9/2019 | 4/9/2019 | 4/9/2019 | | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 11/26/2018 | 11/26/2018 | 11/26/2018 | P | PASS |
Brandon Shaw
|
|
|
Marla (or alt. contact is Ella ###-####) Phone #: ###-####
|
BLD-Footing | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PART |
Mike Jordan
|
|
|
Marla Phone #: ###-####
|
BLD-Framing/Rough-in | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Storey
|
|
|
Call half hour before // Marla or ###-#### Ella Phone #: ###-####
|
BLD-Framing/Rough-in | 11/16/2018 | 11/16/2018 | 11/16/2018 | A | CANC |
Jim Sly
|
|
|
I added this on my list so I could see the history of inspections......and explain to the customer what defer......and NH means since she had to get on line to find out the result of her framing inspection. she said.....no notifications left on site.
|
BLD-Framing/Rough-in | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | NH |
Brandon Shaw
|
|
|
Marla Phone #: ###-####
|
BLD-Framing/Rough-in | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | DEFR |
Jim Storey
|
|
|
Marla Phone #: ###-#### out of time
|
Plan assigned to (BJM) | 10/22/2018 | 10/22/2018 | 10/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 10/22/2018 | | 10/26/2018 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLANNING | 10/23/2018 | | 10/26/2018 | | PASS |
Sue Cummings
|
|
|
Modifying/rebuilding existing front and rear porches
|
Case Summary (BLD) | | | 10/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 10/26/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 10/26/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE
|
Telephone call | | | 10/26/2018 | | DONE |
|
|
|
Spoke to Marla to inform her the plan mod is done and what fees are due.
|
CHANGE STATUS TO (ISS) | | | 10/26/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 10/22/2018 | | DONE |
|
|
|
plan mod accepted-1 set of engineering with drawings from the engineer-took to Brian McGowan
|
Plan assigned to (BJM) | 9/14/2018 | 9/14/2018 | 9/26/2018 | | DONE |
Brian McGowan
|
|
|
plan mod for res remodel
|
Routing - PLAN CHECK | 9/26/2018 | | 9/26/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 9/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 9/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 9/26/2018 | | DONE |
|
|
|
Plan Mod Approved
DO NOT REISSUE (fees due)
|
Telephone call | | | 9/26/2018 | | DONE |
|
|
|
Spoke with Marla to inform her the plan mod and what fees are due
|
CHANGE STATUS TO (ISS) | | | 9/26/2018 | | DONE |
|
|
|
|
BLD-Conference | 9/17/2018 | 9/17/2018 | 9/17/2018 | P | DONE |
Jim Sly
|
|
|
Ella Phone #: ###-#### Under floor....concrete and framing....OK
|
Routing Walk-In (BLD) | 9/17/2018 | 9/17/2018 | 9/17/2018 | A | PASS |
Josh Bogle
|
|
|
I had a conversation with Marla about how to handle inspections while waiting for the Modification Review
|
BLD-Foundation | 9/14/2018 | 9/14/2018 | 9/14/2018 | P | DONE |
Jim Storey
|
|
|
Marla ###-#### or Elenor Phone #: ###-####
|
Plan Modification Accepted | | | 9/14/2018 | | DONE |
|
|
|
received 1 packet (10 pgs) structural details and calcs; taken to Brian M.
|
BLD-Concrete | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | PASS |
Jim Storey
|
|
|
marla Phone #: ###-####
|
BLD-Concrete | 9/5/2018 | 9/5/2018 | 9/6/2018 | P | NR |
Jim Sly
|
|
|
Marla Phone #: ###-####
|
Routing Walk-In (BLD) | 6/13/2018 | 6/13/2018 | 6/13/2018 | P | DONE |
Brian McGowan
|
|
|
|
1st review completed | | | 6/13/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/13/2018 | | 6/13/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 6/13/2018 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 6/13/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/13/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/13/2018 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 1/9/2018 | 1/9/2018 | 1/9/2018 | P | FAIL |
Josh Bogle
|
|
|
needed some structural details on the plan
|
Routing - PLAN CHECK | 1/9/2018 | | 1/9/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 1/9/2018 | | FAIL |
Josh Bogle
|
|
|
|
BLD-Footing | 9/6/2018 | 9/6/2018 | | P | |
Jim Sly
|
|
|
Marla 208 870 1631
|
Application received | | 1/9/2018 | | | |
|
|
|
|