Letter of compliance/Occupancy | | | 7/31/2018 | | DONE |
|
|
|
|
BLD-Final | 6/26/2018 | 6/27/2018 | 6/27/2018 | A | PASS |
Brandon Shaw
|
|
|
As per approved set of plans
|
DOC - Permit Finaled | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 4/23/2018 | 4/24/2018 | 4/24/2018 | A | PASS |
Brandon Shaw
|
|
|
Corrections- SAT
|
BLD-Energy code compliance | 4/20/2018 | 4/23/2018 | 4/23/2018 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 4/19/2018 | 4/19/2018 | 4/19/2018 | P | PEND |
Brandon Shaw
|
|
|
Need foam seal 2 hold downs, (per plans) enrtyway from garage, right side
OK to insulate
|
BLD-Other | 4/19/2018 | 4/20/2018 | 4/19/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit
|
Plan Modification Accepted | | | 4/9/2018 | | DONE |
|
|
|
revised acca report
|
Routing - MECHANICAL | 4/9/2018 | | 4/9/2018 | | PASS |
Chad Schwendiman
|
|
|
revised acca report
|
BLD-Wall Bracing | 3/28/2018 | 3/29/2018 | 3/29/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 2/16/2018 | 2/16/2018 | 2/16/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
Frost protection required
|
BLD-Footing | 2/15/2018 | 2/15/2018 | 2/15/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 2/9/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/9/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 2/6/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 1/22/2018 | 1/22/2018 | 2/6/2018 | | PASS |
Josh Bogle
|
|
|
1st done - plans missing details
|
Routing - PLAN CHECK | 2/6/2018 | | 2/6/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2018 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 2/6/2018 | | DONE |
|
|
|
|
1st review completed | | | 1/23/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 1/11/2018 | | 1/23/2018 | | FAIL |
Josh Bogle
|
|
|
|
Plan assigned to (BJM) | 1/11/2018 | 1/11/2018 | 1/22/2018 | | DEFR |
Brian McGowan
|
|
|
1/25 sfd L1 paper - reassigned to JAB
|
Route to Impact Fee Review | 1/11/2018 | 1/14/2018 | 1/12/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 1/11/2018 | | 1/11/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/11/2018 | | 1/11/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 1/11/2018 | | 1/11/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/11/2018 | | 1/11/2018 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 1/11/2018 | | FAIL |
|
|
|
Missing 2012 IRC review request letter or change to 2015 IRC
|
Plans ACCEPTED BY PLAN TECH | | | 1/11/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/11/2018 | | DONE |
|
|
|
|
Intake Approval | | | 1/11/2018 | | PASS |
|
|
|
|
Application received | | | 1/10/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 10 2018 9:07AM
|
Intake Approval | | | 1/10/2018 | | FAIL |
|
|
|
2012 IRC review request letter, attic access, stair section, fire separation for garage
|