BLD-Final | 9/13/2019 | 9/16/2019 | 9/16/2019 | A | PASS |
Tell Riley
|
|
|
Andy Phone #: ###-####//issues with corridors are taken care of//no changes needed//final complete//
|
Permanent Occupancy | | | 9/16/2019 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 9/13/2019 | 9/13/2019 | 9/13/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 9/4/2019 | 9/4/2019 | 9/4/2019 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 8/29/2019 | 8/30/2019 | 8/30/2019 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson. OK for temp occ. Needs to discuss corridor rating with plan review.
|
Temporary Occupancy | 8/30/2019 | 11/28/2019 | 8/30/2019 | | DONE |
Tisha Gallop
|
|
|
(Temp expires 9/30/19) Permanent Occupancy pending approvals by Planning & Zoning (per Josh W. 30 days from today ok), Public Works, and Structural.
|
PubWorks Temp Occupancy Appr | 8/30/2019 | 8/30/2019 | 8/30/2019 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Phone #: ###-#### Inspection requested via web by Andy Thompson
|
FIRE-Conference | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | DONE |
Troy Cobbley
|
|
|
Inspection was a conference/sprinkler rough-in for the "boxes/insulation" on the cpvc sprinkler pipng in the patio storage closets. Contractor has installed "boxed" the piping with insulation. Piping is ok for cover.
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
Zoning Approval Temp | 8/2/2019 | 8/2/2019 | 8/2/2019 | | PASS |
Josh Wilson
|
|
|
30-day temp occ
|
Print Occupancy Form | | | 8/1/2019 | | DONE |
|
|
|
|
BLD-Foundation | 11/6/2018 | 11/6/2018 | 11/6/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Footing | 11/4/2018 | 11/5/2018 | 11/5/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
Place hold on job | 10/29/2018 | | 10/31/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
Waiting for signed permits back
|
Print Occupancy Form | | | 10/25/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/25/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 10/18/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 4/12/2018 | 4/12/2018 | 10/18/2018 | | DONE |
Julie Romig
|
|
|
10/17 - 6th Rev - 1st Rev Comp - 506 Aventura West 4plex
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/18/2018 | | DONE |
|
|
|
met-don't iss w/o BLD18-00102-105 & 3811
(all ACHD fees to be paid on BLD18-00102 for BLD18-00101, 102-105 & 3811)
ESC18-00031 is for the whole project BLD18-00101, 102-105 & 3811
|
Routing Off Site - STRUCTURAL | 10/11/2018 | | 10/17/2018 | | PASS |
Julie Romig
|
|
|
AHJ 5th Review - passed per ePlanReview
|
Routing - PLAN CHECK | 10/15/2018 | | 10/17/2018 | | PASS |
Julie Romig
|
|
|
|
Routing PW Drainage | 10/15/2018 | | 10/17/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 10/15/2018 | | 10/15/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing Off Site - STRUCTURAL | 9/28/2018 | | 10/2/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 9/18/2018 | | 9/25/2018 | | FAIL |
Julie Romig
|
|
|
Need stamp/signature on grading plan.
|
Routing Off Site - STRUCTURAL | 9/18/2018 | | 9/25/2018 | | FAIL |
Julie Romig
|
|
|
AHJ
|
Routing - Erosion and Sediment | 9/18/2018 | | 9/20/2018 | | PASS |
Andy J. Long
|
|
|
Revised Grading Plan - changes made to the south end of the driveway and parking. ESC site plan to be modified to accomodate changes to Grading and drainage. Original site development permit ESC17-01426 shall be closed once this permit is issued. This will be main permit for the site and the 4 buildings.
|
Routing - FIRE | 9/18/2018 | 9/18/2018 | 9/18/2018 | | PASS |
Erika Akin
|
|
|
No changes to previous comments/FD access
|
Routing - PUBLIC WORKS | 9/18/2018 | | 9/18/2018 | | PASS |
Rachael Beierle
|
|
|
Revised Grading Plan - changes made to the south end of the driveway and parking.
|
Routing - Design Review | 7/18/2018 | | 9/18/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing Off Site - STRUCTURAL | 7/18/2018 | | 7/31/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 7/18/2018 | | 7/25/2018 | | PASS |
Troy James
|
|
|
|
Routing PW Drainage | 6/22/2018 | | 7/24/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 4/12/2018 | | 7/24/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Solid Waste | 4/12/2018 | | 7/24/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLAN CHECK | 7/18/2018 | | 7/23/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 7/18/2018 | | 7/23/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - Design Review | 7/19/2018 | | 7/19/2018 | | FAIL |
Andrea Tuning
|
|
|
The site plan and greading plan shall match one another.
Provide a detailed landscape plan that identifies all species, size and location of all plantings on the site. The species are required to contain a diverse planting palette to create year round color and design interest. This plan shall also include:
. 6 Class I street trees along Cory Lane. (These are noted as NFP. NFP is not on the species list. They should be Class I trees that are approved by the Tree Selection Guide. Only 4 have been provided instead of teh required six. Also, these do not include the terminal planter trees that are required to be Class II trees.)
. One Class II or Class III tree located within all interior planter islands accompanied by low shrubs or other vegetative groundcover. (Sensation Box Elder trees are not an approved species wtihin the Tree Selection Guide. Replace this species with an approved Class II species within the Tree Selection Guide)
. An effective landscape barrier planted on the south and west property lines. (An effective buffer has not been provided. The mix of evergreen deciduous trees, shrubs, lawn, or other vegetative groundcover is required to result in an effective barrier within five years of installation and be maintained such that 60 percent or more of the vertical surface prevents the passage of vision through it.)
|
Routing - PLAN CHECK | 6/22/2018 | | 7/2/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 6/22/2018 | | 6/29/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Sewer Design | 6/22/2018 | | 6/25/2018 | | PASS |
DeAnn Brown
|
|
|
|
Route to Impact Fee Review | 5/23/2018 | 5/26/2018 | 5/24/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 4/12/2018 | | 5/23/2018 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 5/23/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 4/12/2018 | | 5/11/2018 | | PASS |
Tim Frost
|
|
|
5/11 new 4plex e plan
|
Routing - Erosion and Sediment | 4/12/2018 | | 4/25/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved under ESC site development permit ESC17-01426. Each apartment building requires individual ESC permit. Valid stormwater team designated
|
Routing Off Site - STRUCTURAL | 4/12/2018 | | 4/24/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Sewer Design | 4/12/2018 | | 4/18/2018 | | FAIL |
DeAnn Brown
|
|
|
Subdivision application was withdrawn. The only plans showing connection to sewer still show a lot split. Resubmit sewer plans showing property as only one parcel.
|
Routing - PLANNING | 4/12/2018 | | 4/17/2018 | | PASS |
Leon Letson
|
|
|
PUD14-00023
|
Routing - Design Review | 4/12/2018 | | 4/13/2018 | | FAIL |
Andrea Tuning
|
|
|
DRH15-00254
The stone located on the north and south elevations of the 4-plexes should extend to the natural material break and should not terminiate in the middle of the wall plane.
All pole lights are required to be relocated outside of the required planter islands.
Provide a maximum of 33-vehicle parking spaces.
Provide one van accessible space (8’ space with 8’ aisle) and one standard accessible space (8’ space with 5’ aisle) on the site.
Place the pavilion a minimum of 15-feet from the east property line.
Provide a minimum of 15-feet to the parking “bump outs” from the south and east property lines.
The site plan identifies covered parking. Covered parking was not reviewed or approved through Design Review. If the applicant wishes to install covered parking, a new Design Review application is required.
Provide a detailed landscape plan that identifies all species, size and location of all plantings on the site. The species are required to contain a diverse planting palette to create year round color and design interest. This plan shall also include:
. 6 Class I street trees along Cory Lane
. One Class II or Class III tree located within all interior planter islands accompanied by low shrubs or other vegetative groundcover.
. An effective landscape barrier planted on the south and west property lines.
. Include foundation plantings at the base of each building.
|
Intake Approval | | | 4/12/2018 | | PASS |
|
|
|
|
Routing - PLUMBING | 4/12/2018 | | 4/12/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans redlines and ISPC
|
Plans ACCEPTED BY PLAN TECH | | | 4/12/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/12/2018 | | DONE |
|
|
|
|
Routing - Addressing | 4/12/2018 | | 4/12/2018 | | PASS |
Doug Chausow
|
|
|
9351 W Cory Ln
|
Routing - PUBLIC WORKS | 4/12/2018 | | 4/12/2018 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 1/10/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 10 2018 11:39AM
|
First Notice | | 9/26/2019 | | | |
|
|
|
|
Routing PW Drainage | 4/12/2018 | | | | FAIL |
|
|
|
NO STAMP
|
Routing PW Drainage | 9/18/2018 | | | | FAIL |
Brian Murphy
|
|
|
Revised Grading Plan - changes made to the south end of the driveway and parking. NEED DRAINAGE STAMP
|