BLD-Final | 9/13/2019 | 9/16/2019 | 9/16/2019 | A | PASS |
Tell Riley
|
|
|
Andy Phone #: ###-####//corridor issue was taken care of//final is complete//
|
Permanent Occupancy | | | 9/16/2019 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 9/13/2019 | 9/13/2019 | 9/13/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 9/4/2019 | 9/4/2019 | 9/4/2019 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson. Ok for temp occ. Need to discuss corridor rating with plan reviewer on Tuesday.
|
FIRE-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Phone #: ###-#### Inspection requested via web by Andy Thompson
|
Temporary Occupancy | 8/30/2019 | 11/28/2019 | 8/30/2019 | | DONE |
Tisha Gallop
|
|
|
(Temp expires 9/30/19) Permanent Occupancy pending approvals by Planning & Zoning (per Josh W. 30 days from today ok), Public Works, and Structural.
|
PubWorks Temp Occupancy Appr | 8/30/2019 | 8/30/2019 | 8/30/2019 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide knox box, provide sheetrock in closets as discussed and provide second floor signage.
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
FIRE-Conference | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | DONE |
Troy Cobbley
|
|
|
Inspection was a conference/sprinkler rough-in for the "boxes/insulation" on the cpvc sprinkler pipng in the patio storage closets. Contractor has installed "boxed" the piping with insulation. Piping is ok for cover.
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
Zoning Approval Temp | 8/2/2019 | 8/2/2019 | 8/2/2019 | | PASS |
Josh Wilson
|
|
|
30-day temp occ
|
Print Occupancy Form | | | 8/1/2019 | | DONE |
|
|
|
|
BLD-Energy code compliance | 5/3/2019 | 5/3/2019 | 5/3/2019 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Framing/Rough-in | 5/1/2019 | 5/2/2019 | 5/2/2019 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Wall Bracing | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Wall Bracing | 12/31/2018 | 12/31/2018 | 1/2/2019 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Footing | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Andy Thompson
|
BLD-Footing | 11/4/2018 | 11/5/2018 | 11/4/2018 | A | CANC |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Andy Thompson Inspection cancelled from web by: Andy Thompson
|
Place hold on job | 10/29/2018 | | 10/31/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
Waiting for signed permits
|
Print Occupancy Form | | | 10/25/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/25/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 10/18/2018 | | |
|
|
|
|
Plan assigned to (JAR) | 4/12/2018 | 4/12/2018 | 10/18/2018 | | DONE |
Julie Romig
|
|
|
10/17 - 6th Rev - 1st Rev Comp - 506 Aventura West 4plex
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/18/2018 | | DONE |
|
|
|
Met-don't iss w/o BLD18-00102-105 & 3811
(all ACHD fees to be paid on BLD18-00102 for BLD18-00101, 102-105 & 3811)
ESC18-00031 is for the whole project BLD18-00101, 102-105 & 3811
|
Routing - PLAN CHECK | 10/11/2018 | | 10/17/2018 | | PASS |
Julie Romig
|
|
|
|
Routing PW Drainage | 10/11/2018 | | 10/17/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 10/11/2018 | | 10/17/2018 | | PASS |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 9/28/2018 | | 10/2/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 9/28/2018 | | 10/2/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 9/18/2018 | | 9/25/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 9/18/2018 | | 9/25/2018 | | FAIL |
Julie Romig
|
|
|
Need stamp/signed grading plan.
|
Routing - Erosion and Sediment | 9/18/2018 | | 9/20/2018 | | CANC |
Andy J. Long
|
|
|
VOID. Entire project covered under ESC18-00031
|
Routing - FIRE | 9/18/2018 | 9/18/2018 | 9/18/2018 | | PASS |
Erika Akin
|
|
|
No changes to previous comments/FD access
|
Routing - PUBLIC WORKS | 9/18/2018 | | 9/18/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 9/18/2018 | | 9/18/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing Off Site - STRUCTURAL | 7/18/2018 | | 7/31/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 7/18/2018 | | 7/25/2018 | | PASS |
Troy James
|
|
|
|
Routing PW Drainage | 4/12/2018 | | 7/24/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 4/12/2018 | | 7/24/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Solid Waste | 4/12/2018 | | 7/24/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLAN CHECK | 7/18/2018 | | 7/23/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 6/22/2018 | | 7/2/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 6/22/2018 | | 6/29/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Sewer Design | 6/22/2018 | | 6/25/2018 | | PASS |
DeAnn Brown
|
|
|
|
Route to Impact Fee Review | 5/23/2018 | 5/26/2018 | 5/24/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/23/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 4/12/2018 | | 5/23/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 4/12/2018 | | 5/11/2018 | | PASS |
Tim Frost
|
|
|
5/11 new 4plex e plan
|
Routing - Erosion and Sediment | 4/12/2018 | | 4/25/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved under ESC site development permit ESC17-01426. Each apartment building requires individual ESC permit. Valid stormwater team designated
|
Routing Off Site - STRUCTURAL | 4/12/2018 | | 4/24/2018 | | PASS |
Julie Romig
|
|
|
|
Routing PW Sewer Design | 4/12/2018 | | 4/18/2018 | | FAIL |
DeAnn Brown
|
|
|
Subdivision application was withdrawn. The only plans showing connection to sewer still show a lot split. Resubmit sewer plans showing property as only one parcel.
|
Routing - PLANNING | 4/12/2018 | | 4/17/2018 | | PASS |
Leon Letson
|
|
|
PUD14-00023
|
Routing - Design Review | 4/12/2018 | | 4/13/2018 | | FAIL |
Andrea Tuning
|
|
|
DRH15-00254
The stone located on the north and south elevations of the 4-plexes should extend to the natural material break and should not terminiate in the middle of the wall plane.
All pole lights are required to be relocated outside of the required planter islands.
Provide a maximum of 33-vehicle parking spaces.
Provide one van accessible space (8’ space with 8’ aisle) and one standard accessible space (8’ space with 5’ aisle) on the site.
Place the pavilion a minimum of 15-feet from the east property line.
Provide a minimum of 15-feet to the parking “bump outs” from the south and east property lines.
The site plan identifies covered parking. Covered parking was not reviewed or approved through Design Review. If the applicant wishes to install covered parking, a new Design Review application is required.
Provide a detailed landscape plan that identifies all species, size and location of all plantings on the site. The species are required to contain a diverse planting palette to create year round color and design interest. This plan shall also include:
. 6 Class I street trees along Cory Lane
. One Class II or Class III tree located within all interior planter islands accompanied by low shrubs or other vegetative groundcover.
. An effective landscape barrier planted on the south and west property lines.
. Include foundation plantings at the base of each building.
|
Intake Approval | | | 4/12/2018 | | PASS |
|
|
|
|
Routing - PLUMBING | 4/12/2018 | | 4/12/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans redlines and ISPC
|
Plans ACCEPTED BY PLAN TECH | | | 4/12/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/12/2018 | | DONE |
|
|
|
|
Routing - Addressing | 4/12/2018 | | 4/12/2018 | | PASS |
Doug Chausow
|
|
|
9333 W Cory Ln
|
Routing - PUBLIC WORKS | 4/12/2018 | | 4/12/2018 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 2/26/2018 | | FAIL |
|
|
|
|
Application received | | | 1/10/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 10 2018 11:39AM
|
First Notice | | 9/26/2019 | | | |
|
|
|
|
Routing PW Drainage | 9/18/2018 | | | | FAIL |
Brian Murphy
|
|
|
NEED DRAINAGE STAMP
|