BLD-Conference | 12/19/2018 | 12/19/2018 | 12/19/2018 | P | CANC |
Jim Sly
|
|
|
|
Routing Walk-In (BLD) | 1/29/2018 | 1/29/2018 | 1/29/2018 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 1/29/2018 | | 1/29/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 1/29/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 1/29/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 1/29/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/29/2018 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 1/23/2018 | 1/23/2018 | 1/23/2018 | P | DONE |
Jeff Lowe
|
|
|
tandem parking ok in anticpation of new garage. no adu proposed or allowed with this permit
|
Routing Walk-In (BLD) | 1/23/2018 | 1/23/2018 | 1/23/2018 | P | FAIL |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 1/23/2018 | | 1/23/2018 | | FAIL |
Rob Patrick
|
|
|
Requires ES Report for insulation.
|
1st review completed | | | 1/23/2018 | | FAIL |
Rob Patrick
|
|
|
|
Intake Approval | | | 1/23/2018 | | |
|
|
|
|
Application received | | 1/11/2018 | | | |
|
|
|
|