Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-00147
StatusIssued
Name WILHELM MELISSA J
Site Address 2104 N 30TH ST
Project NameWilhelm Remodel
Customer Number 
ePlanReviewNo
Description
***MODIFICATION (6/11/18) - UPSTAIRS BEING FINISHED AS PART OF THIS PERMIT, TWO BEDROOMS AND A FULL BATH - jab*** - **MODIFICATION (4/30/18) rebuilding 270sq' carport JAB** MODFICATION - ADDING BONUS ROOM TRUSSES AND STAIRS TO ADD 456SQ' OF ADDITIONAL UPSTAIRS SPACE. UPSTAIRS WILL BE INTERIOR STORAGE AT THIS TIME. TRUSSES CREATE A 4' PORCH OVERHANG TO THE REAR jab - Permit for a remodel, to include: new cabs/counters/fixtures in kitchen, new cabs/counters/fixtures/layout in bath, new windows (some sizes change), adding a new rear door (w/ header), adding an interior wall to separate a hall and bedroom, new siding, & new roofing. All work per plans, notes, & local code. Separate electrical, plumbing, & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection11/30/201811/30/201812/3/2018 PEND
DetailsTony Young
BLD-Aging Inspection11/29/201811/29/201812/3/2018 PEND
DetailsTony Young
BLD-Energy code compliance7/17/20187/18/20187/18/2018APASS
DetailsTony Young
Phone #: ###-####
BLD-Framing/Rough-in7/16/20187/17/20187/17/2018APASS
DetailsTony Young
Phone #: ###-####
BLD-Framing/Rough-in7/11/20187/12/20187/12/2018APART
DetailsTony Young
Joe Phone #: ###-####,, need to verify the seal package at energy code
Routing - MECHANICAL6/20/2018 6/20/2018 PASS
DetailsTroy James
Manual j report submitted
BLD-Conference6/19/20186/19/20186/19/2018PPART
DetailsTony Young
Joe Phone #: ###-####,, conf on carport seperation,, other frame ?s
Plan assigned to (JAB) Josh6/11/20186/11/20186/11/2018 PASS
DetailsJosh Bogle
Routing Walk-In (BLD)6/11/20186/11/20186/11/2018ADONE
DetailsJosh Bogle
Routing Walk-In (BLD)6/11/20186/11/20186/11/2018PDONE
DetailsJosh Bogle
Routing - PLAN CHECK6/11/2018 6/11/2018 PASS
DetailsJosh Bogle
Case Summary (BLD)  6/11/2018 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  6/11/2018 DONE
DetailsJosh Bogle
Permit Ready to Issue  6/11/2018 DONE
CHANGE STATUS TO (ISS)  6/11/2018 DONE
Inspection Record Card- Bld  6/11/2018 DONE
Plan Modification Accepted  6/11/2018 DONE
plan mod-changing finish bonus room - orig permitted as unfinished
BLD-Footing5/1/20185/1/20185/1/2018PPASS
DetailsTony Young
footing inspection for stairs. and sonotube for carport. Thank you. Phone #: ###-#### Inspection requested via web by Joe Wilhelm
BLD-Conference5/1/20185/1/20185/1/2018APASS
DetailsTony Young
footing inspection for stairs. and sonotube for carport. Thank you. Phone #: ###-#### Inspection requested via web by Joe Wilhelm, ok
Routing Walk-In (Zoning)4/30/20184/30/20184/30/2018ADONE
DetailsCandy A. Nichols
modification
Routing Walk-In (Zoning)4/30/20184/30/20184/30/2018APASS
DetailsSue Cummings
Routing Walk-In (BLD)4/30/20184/30/20184/30/2018ADONE
DetailsJosh Bogle
Routing - PLAN CHECK4/30/2018 4/30/2018 PASS
DetailsJosh Bogle
modification to rebuild carport
PLANS/APPL TAKEN TO FRONT DESK  4/30/2018 DONE
DetailsJosh Bogle
fee per added value
Permit Ready to Issue  4/30/2018 DONE
CHANGE STATUS TO (ISS)  4/30/2018 DONE
Inspection Record Card- Bld  4/30/2018 DONE
(F) Reprint permit  4/30/2018 DONE
Plan Modification Accepted  4/30/2018 DONE
plan mod to take down old and replace with new carport
Routing Walk-In (BLD)3/9/20183/9/20183/9/2018ADONE
DetailsJosh Bogle
Plan assigned to (JAB) Josh3/5/20183/5/20183/9/2018 PASS
DetailsJosh Bogle
Routing - PLAN CHECK3/9/2018 3/9/2018 PASS
DetailsJosh Bogle
Case Summary (BLD)  3/9/2018 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  3/9/2018 DONE
DetailsJosh Bogle
CHANGE STATUS TO (ISS)  3/9/2018 DONE
Plan Mod approved
Inspection Record Card- Bld  3/9/2018 DONE
Routing Walk-In (BLD)3/5/20183/5/20183/5/2018PFAIL
DetailsJosh Bogle
Routing - PLAN CHECK3/5/2018 3/5/2018 FAIL
DetailsJosh Bogle
Routing Walk-In (BLD)3/1/20183/1/20183/1/2018APASS
DetailsJosh Bogle
Plan mod questions
Routing Walk-In (BLD)1/12/20181/12/20181/12/2018PPASS
DetailsJosh Bogle
applicant was proposing a change to the plan but will be coming back after gathering some information JAB
Routing Walk-In (Zoning)1/12/20181/12/20181/12/2018PDONE
DetailsLeon Letson
Routing Walk-In (BLD)1/12/20181/12/20181/12/2018PDONE
DetailsJosh Bogle
Routing - FRONT DESK1/12/2018 1/12/2018 PASS
DetailsJosh Bogle
1st review completed  1/12/2018 DONE
DetailsJosh Bogle
Inspection Record Card- Bld  1/12/2018 DONE
DetailsJosh Bogle
Case Summary (BLD)  1/12/2018 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  1/12/2018 DONE
DetailsJosh Bogle
ESC no - Energy no
Permit Ready to Issue  1/12/2018 DONE
Issue PAID IN FULL permit  1/12/2018 DONE
Application received 1/12/2018