BLD-Aging Inspection | 11/30/2018 | 11/30/2018 | 12/3/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 11/29/2018 | 11/29/2018 | 12/3/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 7/17/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 7/16/2018 | 7/17/2018 | 7/17/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-####
|
BLD-Framing/Rough-in | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | PART |
Tony Young
|
|
|
Joe Phone #: ###-####,, need to verify the seal package at energy code
|
Routing - MECHANICAL | 6/20/2018 | | 6/20/2018 | | PASS |
Troy James
|
|
|
Manual j report submitted
|
BLD-Conference | 6/19/2018 | 6/19/2018 | 6/19/2018 | P | PART |
Tony Young
|
|
|
Joe Phone #: ###-####,, conf on carport seperation,, other frame ?s
|
Plan assigned to (JAB) Josh | 6/11/2018 | 6/11/2018 | 6/11/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 6/11/2018 | 6/11/2018 | 6/11/2018 | A | DONE |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 6/11/2018 | | 6/11/2018 | | PASS |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 6/11/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 6/11/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/11/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/11/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 6/11/2018 | | DONE |
|
|
|
plan mod-changing finish bonus room - orig permitted as unfinished
|
BLD-Footing | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Tony Young
|
|
|
footing inspection for stairs. and sonotube for carport. Thank you. Phone #: ###-#### Inspection requested via web by Joe Wilhelm
|
BLD-Conference | 5/1/2018 | 5/1/2018 | 5/1/2018 | A | PASS |
Tony Young
|
|
|
footing inspection for stairs. and sonotube for carport. Thank you. Phone #: ###-#### Inspection requested via web by Joe Wilhelm, ok
|
Routing Walk-In (Zoning) | 4/30/2018 | 4/30/2018 | 4/30/2018 | A | DONE |
Candy A. Nichols
|
|
|
modification
|
Routing Walk-In (Zoning) | 4/30/2018 | 4/30/2018 | 4/30/2018 | A | PASS |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 4/30/2018 | 4/30/2018 | 4/30/2018 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 4/30/2018 | | 4/30/2018 | | PASS |
Josh Bogle
|
|
|
modification to rebuild carport
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2018 | | DONE |
Josh Bogle
|
|
|
fee per added value
|
Permit Ready to Issue | | | 4/30/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/30/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/30/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/30/2018 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 4/30/2018 | | DONE |
|
|
|
plan mod to take down old and replace with new carport
|
Routing Walk-In (BLD) | 3/9/2018 | 3/9/2018 | 3/9/2018 | A | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 3/5/2018 | 3/5/2018 | 3/9/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/9/2018 | | 3/9/2018 | | PASS |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 3/9/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2018 | | DONE |
Josh Bogle
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/9/2018 | | DONE |
|
|
|
Plan Mod approved
|
Inspection Record Card- Bld | | | 3/9/2018 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 3/5/2018 | 3/5/2018 | 3/5/2018 | P | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/5/2018 | | 3/5/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 3/1/2018 | 3/1/2018 | 3/1/2018 | A | PASS |
Josh Bogle
|
|
|
Plan mod questions
|
Routing Walk-In (BLD) | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | PASS |
Josh Bogle
|
|
|
applicant was proposing a change to the plan but will be coming back after gathering some information JAB
|
Routing Walk-In (Zoning) | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | DONE |
Leon Letson
|
|
|
|
Routing Walk-In (BLD) | 1/12/2018 | 1/12/2018 | 1/12/2018 | P | DONE |
Josh Bogle
|
|
|
|
Routing - FRONT DESK | 1/12/2018 | | 1/12/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 1/12/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 1/12/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 1/12/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2018 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 1/12/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/12/2018 | | DONE |
|
|
|
|
Application received | | 1/12/2018 | | | |
|
|
|
|