BLD-Final | 6/29/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
DOC - Permit Finaled | 6/29/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Energy code compliance | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Framing/Rough-in | 4/26/2018 | 4/27/2018 | 4/27/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Wall Bracing | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Footing | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PASS |
Jim Storey
|
|
|
Giber Phone #: ###-####
|
OVERRIDE | | | 2/14/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 1/29/2018 | 1/29/2018 | 2/14/2018 | | PASS |
Josh Bogle
|
|
|
1st done - PFG bracing not wide enough
|
Routing - PLAN CHECK | 2/14/2018 | | 2/14/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 2/14/2018 | | DONE |
|
|
|
Met
|
Issue PAID IN FULL permit | | | 2/14/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/14/2018 | | DONE |
|
|
|
|
Plan assigned to (RDP) | 1/18/2018 | 1/18/2018 | 1/29/2018 | | DEFR |
Rob Patrick
|
|
|
1/31 sfd L1 ePlan
|
Routing - PLAN CHECK | 1/18/2018 | | 1/29/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 1/29/2018 | | FAIL |
Josh Bogle
|
|
|
|
Plan Reviewer's activity | | | 1/29/2018 | | FAIL |
Josh Bogle
|
|
|
rejected resubmittal - no changes
|
Routing - MECHANICAL | 1/18/2018 | | 1/22/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 1/18/2018 | 1/21/2018 | 1/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 1/18/2018 | | 1/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/18/2018 | | 1/19/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 1/18/2018 | | 1/18/2018 | | PASS |
Sue Cummings
|
|
|
|
Intake Approval | | | 1/18/2018 | | FAIL |
|
|
|
corrections still not corrected-still need letter or need to change to the 2015 irc
|
Plans ACCEPTED BY PLAN TECH | | | 1/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 1/18/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 1/16/2018 | | FAIL |
|
|
|
Need letter for 2012 review
|
Application received | | | 1/15/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 15 2018 10:32AM
|