Second Notice | | 4/20/2018 | 4/16/2018 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | 3/21/2018 | 3/21/2018 | 4/10/2018 | | DONE |
Tony Young
|
|
|
mailed 4-11-18
|
BLD-Final | 3/20/2018 | 3/21/2018 | 3/21/2018 | A | PASS |
Tony Young
|
|
|
Call 15 mins aheadm store opens at 9 - Brian Phone #: ###-####
|
DOC - Permit Finaled | 3/21/2018 | 3/21/2018 | 3/21/2018 | P | PASS |
Tony Young
|
|
|
damage has been repaired,, signed papers
|
FIRE-Final Inspection | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | CANC |
Troy Cobbley
|
|
|
No fire life safety sign off required per the project details.
call 15 mins ahead- Brian Phone #: ###-####
|
BLD-Framing/Rough-in | 1/24/2018 | 1/25/2018 | 1/25/2018 | A | PASS |
Jim Sly
|
|
|
call 20 min prior// Brian Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/19/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/19/2018 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 1/18/2018 | 1/18/2018 | 1/18/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 1/18/2018 | | 1/18/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
ok per Sarah no DR review as they are repairing damage to match previouse approval
|
1st review completed | | | 1/18/2018 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/18/2018 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED CERT
|
Intake Approval | | | 1/18/2018 | | FAIL |
Rob Patrick
|
|
|
BLD18-00195
1/18/18 Please Provide the Following:
1. Engineering for damaged structure.
2. Load dwgs individually not as a packet.
3. Load only effected dwgs.
4. Cloud areas of dwgs where work will be completed.
Thank you
Rob Patrick
|
Intake Approval | | | 1/18/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
pre screen accepted by Rob
|
Application received | | | 1/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 17 2018 1:39PM
|