Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD18-00202
StatusFinaled
Name KB FINANCIAL LLC
Site Address 2272 W HILL TERRACE LN
Project NameNORTH HILL SUBDIVISION
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 1485 sq. ft., two story (first story 780 (garage) sq. ft., second story 1485 sq. ft.) single family dwelling with 2 bedrooms, 2 bathrooms, approximately -0- sq. ft. of covered patio/porch and a 780 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. W.U.I. Hillside, Class A Roof Required. See also BLD18-00203; BLD18-00204; BLD18-00206. R-1C zoning and setbacks per planning.

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/15/20193/18/20193/18/2019APASS
DetailsTony Young
Ron Phone #: ###-####
DOC - Permit Finaled3/18/20193/18/20193/18/2019PPASS
DetailsTony Young
c of o issued
BLD-Final3/14/20193/15/20193/15/2019ANR
DetailsTony Young
Ron Phone #: ###-####,, needs firecaulking for seperation
BLD-Final3/13/20193/14/20193/14/2019PNR
DetailsTony Young
Ron Phone #: ###-####,, needs fire caulking
PubWorks Occupancy Approval3/14/20193/14/20193/14/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.

BLD-Aging Inspection2/28/20192/28/20193/1/2019 PEND
DetailsTony Young
BLD-Aging Inspection2/27/20192/27/20193/1/2019 PEND
DetailsTony Young
BLD-Energy code compliance10/16/201810/16/201810/16/2018PPASS
DetailsTony Young
Ron Phone #: ###-####
BLD-Wall Bracing10/12/201810/15/201810/15/2018ACANC
DetailsTony Young
Ron Phone #: ###-####
BLD-Framing/Rough-in10/8/201810/9/201810/9/2018APASS
DetailsTony Young
Ron; Phone #: ###-####
BLD-Energy code compliance10/8/201810/8/201810/8/2018PPART
DetailsTony Young
Rod Phone #: ###-####,, seal package ok,, ok to insulate
BLD-Conference9/18/20189/19/20189/19/2018APASS
DetailsTony Young
Ron Phone #: ###-####,, stair ?s
BLD-Wall Bracing8/24/20188/24/20188/24/2018PPASS
DetailsTony Young
Ron- Phone #: ###-####
BLD-Wall Bracing8/23/20188/23/20188/24/2018PPART
DetailsTony Young
Ron-soffits and stairwells Phone #: ###-####,, soffits ok
BLD-Other7/23/20187/24/20187/24/2018APART
DetailsTony Young
Party wall - Aaron Phone #: ###-####,, 2nd floor over garage ok
BLD-Other7/3/20187/5/20187/5/2018APART
DetailsTony Young
fire wall // Ron Phone #: ###-####,,lower garage firewall ok
BLD-Other6/28/20186/28/20186/28/2018PPART
DetailsTony Young
Aaron-party wall Phone #: ###-####,, upper main level firewall,, work in progress
BLD-Foundation6/18/20186/19/20186/19/2018APASS
DetailsTony Young
wall-Austin Phone #: ###-####
BLD-Footing6/15/20186/15/20186/15/2018PDONE
DetailsTony Young
Austin Phone #: ###-#### upper house footings
BLD-Foundation5/30/20185/30/20185/30/2018PPART
DetailsTony Young
Austin Phone #: ###-####,, back basement walls,, work in progress
BLD-Foundation4/24/20184/26/20184/26/2018ANR
DetailsTony Young
Austin Phone #: ###-####
BLD-Foundation4/19/20184/20/20184/20/2018APART
DetailsTony Young
Austin Phone #: ###-####,, rear footings
BLD-Foundation4/17/20184/17/20184/17/2018PPART
DetailsBrandon Shaw
Front and side stem walls, and back wall footing
BLD-Footing4/9/20184/10/20184/10/2018APASS
DetailsBrandon Shaw
Work in progress
PubWorks Subgrade Approval4/10/20184/10/20184/10/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

Issue PAID IN FULL permit  3/27/2018 DONE
Inspection Record Card- Bld  3/27/2018 DONE
OVERRIDE  2/21/2018  
Plan assigned to (RDP)2/5/20182/5/20182/21/2018 DONE
DetailsRob Patrick
2/22 sfd L2 ePlan
Routing - PLAN CHECK2/5/2018 2/21/2018 PASS
DetailsRob Patrick
1st review completed  2/21/2018 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  2/21/2018 DONE
DetailsRob Patrick
Permit Ready to Issue  2/21/2018 DONE
RP Exipred
Routing PW Grading-Hillside2/5/2018 2/12/2018 PASS
DetailsMelissa Jannusch


A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
Route to Impact Fee Review2/5/20182/8/20182/6/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - FIRE2/5/20182/5/20182/6/2018 PASS
DetailsScott Arellano
No comments attached. SFD with approved access and water supply. No field inspection required.
Routing - PLANNING2/5/2018 2/6/2018 PASS
DetailsColleen T Carroll
Routing - Addressing2/5/2018 2/5/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS2/5/2018 2/5/2018 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment2/5/2018 2/5/2018 PASS
DetailsMichael Zawacki
Reference ESC15-00853 for overall site permit
Plans ACCEPTED BY PLAN TECH  2/5/2018 DONE
Recd Pcfee & Taken To Pln CK  2/5/2018 DONE
Intake Approval  2/5/2018 PASS
Per Nicolette, can accept prescreen but planning can't review until Feb 12 at 5:00pm.
Routing - MECHANICAL2/5/2018 2/5/2018 PASS
DetailsTroy James
Intake Approval  1/22/2018 FAIL
Project will require a CAT II Hillside application prior to acceptance of the building permit application. Application #114 will need to be filled out and turned in to the Planning & Zoning counter at city hall with the application fee. Once the application has been approved by P&Z please upload the approval letter and then this building permit case can be routed for approval
Intake Approval  1/19/2018 FAIL
need cat ll from P & Z, need lots marked so we know which one pertains to the address
need letter for 2012 IRC
Application received  1/18/2018 DONE
Application submitted via PDS Online on Jan 18 2018 9:03AM