BLD-Final | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | PASS |
Tony Young
|
|
|
Ron Phone #: ###-####
|
DOC - Permit Finaled | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | DONE |
Tony Young
|
|
|
Ron Phone #: ###-####// 4.3
|
PubWorks Occupancy Approval | 4/23/2019 | 4/23/2019 | 4/23/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 4/19/2019 | 4/22/2019 | 4/22/2019 | P | PART |
Tony Young
|
|
|
Ron Phone #: ###-####,, needs hillside approval
|
BLD-Aging Inspection | 4/18/2019 | 4/18/2019 | 4/22/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/17/2019 | 4/17/2019 | 4/22/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 12/3/2018 | 12/4/2018 | 12/4/2018 | A | PASS |
Tony Young
|
|
|
Ron Phone #: ###-####
|
BLD-Wall cover | 12/3/2018 | 12/3/2018 | 12/3/2018 | P | PASS |
Tony Young
|
|
|
Ron Phone #: ###-####
|
BLD-Framing/Rough-in | 11/29/2018 | 11/30/2018 | 11/30/2018 | A | PASS |
Tony Young
|
|
|
Ron Phone #: ###-####,, ok to insulate
|
BLD-Framing/Rough-in | 11/28/2018 | 11/29/2018 | 11/29/2018 | A | FAIL |
Brandon Shaw
|
|
|
No plans or Truss Engineering on site
|
BLD-Wall Bracing | 8/24/2018 | 8/24/2018 | 8/24/2018 | P | PASS |
Tony Young
|
|
|
Ron- Phone #: ###-####
|
BLD-Wall Bracing | 8/23/2018 | 8/23/2018 | 8/24/2018 | P | PART |
Tony Young
|
|
|
Ron-soffits and stairwells Phone #: ###-####,, soffits ok
|
BLD-Other | 7/23/2018 | 7/24/2018 | 7/24/2018 | A | PART |
Tony Young
|
|
|
Party wall - Aaron Phone #: ###-####,, 2nd floor over garage ok
|
BLD-Other | 7/3/2018 | 7/5/2018 | 7/5/2018 | A | PEND |
Tony Young
|
|
|
fire wall // Ron Phone #: ###-####,,
|
BLD-Other | 6/28/2018 | 6/28/2018 | 6/28/2018 | P | PART |
Tony Young
|
|
|
Aaron-party wall Phone #: ###-####,, upper main level firewall,, work in progress
|
BLD-Foundation | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PASS |
Tony Young
|
|
|
wall-Austin Phone #: ###-####
|
BLD-Footing | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | DONE |
Tony Young
|
|
|
Austin Phone #: ###-####,, upper house footings
|
BLD-Foundation | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PART |
Tony Young
|
|
|
Austin Phone #: ###-####,, back basement walls,, work in progress
|
BLD-Foundation | 4/24/2018 | 4/26/2018 | 4/26/2018 | A | NR |
Tony Young
|
|
|
Austin Phone #: ###-####
|
BLD-Foundation | 4/19/2018 | 4/20/2018 | 4/20/2018 | A | PART |
Tony Young
|
|
|
Austin Phone #: ###-####,, rear footings
|
BLD-Foundation | 4/17/2018 | 4/17/2018 | 4/17/2018 | P | PART |
Brandon Shaw
|
|
|
Front and side stem walls, and back wall footing
|
BLD-Footing | 4/9/2018 | 4/10/2018 | 4/10/2018 | A | PART |
Brandon Shaw
|
|
|
Work in progress
Front and side wall footings, back wall footing to be poured at later date
|
PubWorks Subgrade Approval | 4/10/2018 | 4/10/2018 | 4/10/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 4/4/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/4/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 2/21/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 2/5/2018 | 2/5/2018 | 2/21/2018 | | DONE |
Rob Patrick
|
|
|
2/22 sfd L2 eplan
|
Routing - PLAN CHECK | 2/5/2018 | | 2/21/2018 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 2/21/2018 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 2/21/2018 | | DONE |
|
|
|
met
|
Routing PW Grading-Hillside | 2/5/2018 | | 2/12/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Route to Impact Fee Review | 2/5/2018 | 2/8/2018 | 2/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 2/5/2018 | 2/5/2018 | 2/6/2018 | | PASS |
Scott Arellano
|
|
|
No comments attached. SFD with approved access and water supply. No field inspection required.
|
Routing - PLANNING | 2/5/2018 | | 2/6/2018 | | PASS |
Leon Letson
|
|
|
|
Routing - Addressing | 2/5/2018 | | 2/5/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/5/2018 | | 2/5/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 2/5/2018 | | 2/5/2018 | | PASS |
Michael Zawacki
|
|
|
Reference ESC15-00853 for overall site permit
|
Plans ACCEPTED BY PLAN TECH | | | 2/5/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/5/2018 | | DONE |
|
|
|
|
Intake Approval | | | 2/5/2018 | | PASS |
|
|
|
Per Nicolette, can accept prescreen but planning can't review until Feb 12 at 5:00pm.
|
Routing - MECHANICAL | 2/5/2018 | | 2/5/2018 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 1/22/2018 | | FAIL |
|
|
|
Project will require a CAT II Hillside application prior to acceptance of the building permit application. Application #114 will need to be filled out and turned in to the Planning & Zoning counter at city hall with the application fee. Once the application has been approved by P&Z please upload the approval letter and then this building permit case can be routed for approval
|
Intake Approval | | | 1/19/2018 | | FAIL |
|
|
|
need cat ll from p & z
need lot/blk specified by bold or circle or something on each drawing that has multiple lots
need sheets turned that are not facing correctly
need letter for 2012 IRC review
|
Application received | | | 1/18/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 18 2018 9:20AM
|