BLD-Final | 5/30/2018 | 5/30/2018 | 5/30/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
DOC - Permit Finaled | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 5/30/2018 | 5/30/2018 | 5/30/2018 | A | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
4.5 ACH @50pca.
|
BLD-Final | 5/29/2018 | 5/29/2018 | 5/29/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover. Insulate crawl sapce, provide CO detector and blower door test result.
|
BLD-Final | 5/25/2018 | 5/25/2018 | 5/25/2018 | A | NR |
Brandon Shaw
|
|
|
Need Mech finals
|
BLD-Energy code compliance | 3/28/2018 | 3/28/2018 | 3/28/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Framing/Rough-in | 3/28/2018 | 3/28/2018 | 3/28/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Framing/Rough-in | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover.. Ok to insulate. Nees to install fireplace and have rough in inspection prior to energy code inspection.
|
BLD-Wall Bracing | 3/5/2018 | 3/6/2018 | 3/6/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover
|
BLD-Foundation | 2/12/2018 | 2/13/2018 | 2/13/2018 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 2/9/2018 | 2/12/2018 | 2/12/2018 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
OVERRIDE | | | 2/7/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/7/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/7/2018 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 2/7/2018 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 2/7/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 2/7/2018 | | DONE |
|
|
|
Met
|
Plan assigned to (M_H) | 1/30/2018 | | 2/7/2018 | | DONE |
Michael Hanson
|
|
|
02/12 sfd L1 ePlan
|
Routing - PLAN CHECK | 1/30/2018 | | 2/7/2018 | | PASS |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 1/30/2018 | | 2/1/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 1/30/2018 | 2/2/2018 | 1/31/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 1/30/2018 | | 1/30/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 1/30/2018 | | 1/30/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/30/2018 | | 1/30/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/30/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/30/2018 | | DONE |
|
|
|
|
Intake Approval | | | 1/30/2018 | | PASS |
|
|
|
|
Intake Approval | | | 1/22/2018 | | FAIL |
|
|
|
Need
Manual J and either a letter for plans to be reviewed as 2012 IRC and copy of letter uploaded or change plans to 2015 IRC
Permit for the construction of a new 1,784 sq. ft., one story single family dwelling with 3 bedrooms, 2 bathrooms, approximately 108 sq. ft. of covered patio/porch and a 502 sq. ft. attached garage per the approved plans and any notations. R-1C zoning and setbacks per planning.
|
Application received | | | 1/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 19 2018 3:02PM
|