Second Notice | | 7/20/2018 | 7/26/2018 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
First Notice | | 6/25/2018 | 7/10/2018 | | DONE |
|
|
|
mailed 7-11-18
|
Permanent Occupancy | | | 6/15/2018 | | |
|
|
|
|
BLD-Final | 6/13/2018 | 6/14/2018 | 6/14/2018 | P | PASS |
Mike Jordan
|
|
|
ceil Phone #: ###-####. Ok for perm occ. MAjority of scope of work for this project was deleted. Doors and concrete remained, no demo on walls for new lead. Pit was filled in and new equipment.
|
FIRE-Final Inspection | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Cecil Phone #: ###-####
|
BLD-Final | 6/13/2018 | 6/13/2018 | 6/13/2018 | P | CANC |
Mike Jordan
|
|
|
ceil Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/20/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/20/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/20/2018 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 2/5/2018 | 2/5/2018 | 3/14/2018 | | PASS |
Carl Westfall
|
|
|
(Feb 21 - 15 days) (24 sheets) SARMC LINAC Upgrade
|
Routing - PLAN CHECK | 2/5/2018 | | 3/14/2018 | | PASS |
Carl Westfall
|
|
|
1st IBC plan review completed and approved
|
1st review completed | | | 3/14/2018 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/14/2018 | | DONE |
|
|
|
email Brandon Byington at bbyington@kreizenbeck.com
Need
GC Form-met
Revised Cert of Value-met
|
Routing Off Site - STRUCTURAL | 2/5/2018 | | 2/13/2018 | | PASS |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - FIRE | 2/5/2018 | 2/5/2018 | 2/9/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - MECHANICAL | 2/5/2018 | | 2/8/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 2/5/2018 | | 2/7/2018 | | PASS |
Daryl Spivey
|
|
|
No plumbing plan to review
|
Routing - Addressing | 2/5/2018 | | 2/6/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/5/2018 | | 2/6/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 2/5/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Pre screen accepted by Carl W
|
Plan Reviewer's activity | | | 2/1/2018 | | PASS |
|
|
|
Plan intake review approved
|
Application received | | | 1/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 19 2018 3:43PM
|