BLD-Final | 8/3/2018 | 8/6/2018 | 8/6/2018 | A | PASS |
Jim Sly
|
|
|
CArl Phone #: ###-####
|
DOC - Permit Finaled | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Jim Sly
|
|
|
|
Plan assigned to (RDP) | 1/22/2018 | 1/22/2018 | 2/7/2018 | | DONE |
Rob Patrick
|
|
|
1st review completed 1/26 Solar L2 (Failed)
|
Routing - PLAN CHECK | 2/7/2018 | | 2/7/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 2/7/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/7/2018 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 2/6/2018 | | FAIL |
Rob Patrick
|
|
|
Need dimensioned roof plan and panel spec sheets.
|
Plan Reviewer's activity | | | 2/5/2018 | | FAIL |
Rob Patrick
|
|
|
Please Provide the Following per our Phone Discussion:
1. Spec sheets for tubing panels.
2. Dimensioned roof plan showing panels installation.
3. Current up-to-date Evaluation sheet.
Thank you
Rob Patrick
|
1st review completed | | | 1/24/2018 | | FAIL |
Rob Patrick
|
|
|
BLD18-00223 1-24-18
1. Evaluation Report Submitted is not valid.
2. All drawings and details necessary to show system is compliant per M2103 & M2301.
3. Stamped and Signed Engineering for loading at roof and for wind loading.
4. Connection details to Potable water supply.
|
Plan Reviewer's activity | | | 1/24/2018 | | FAIL |
Rob Patrick
|
|
|
|
Plan assigned to (JAB) Josh | 1/22/2018 | 1/22/2018 | 1/22/2018 | | DEFR |
Josh Bogle
|
|
|
|
Routing - PLANNING | 1/22/2018 | | 1/22/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/22/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/22/2018 | | DONE |
|
|
|
no fee taken at intake, 406
|
Intake Approval | | | 1/22/2018 | | PASS |
|
|
|
|
Application received | | | 1/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 20 2018 2:09PM
|