First Notice | | 5/11/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
Permanent Occupancy | | | 5/1/2018 | | DONE |
|
|
|
|
BLD-Final | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | PASS |
Dave Hannah
|
|
|
John-prefer late afternoon-call for access Phone #: ###-####
|
BLD-Final | 4/11/2018 | 4/11/2018 | 4/11/2018 | A | PEND |
Dave Hannah
|
|
|
ok for temp needs door and signage for rest room
|
BLD-Conference | 4/9/2018 | 4/10/2018 | 4/11/2018 | P | DONE |
Dave Hannah
|
|
|
John Phone #: ###-#### ok for temp occ
|
FIRE-Final Inspection | 4/6/2018 | 4/9/2018 | 4/9/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection for area of work complete.
|
BLD-Ceiling Grid Inspection | 4/3/2018 | 4/3/2018 | 4/3/2018 | P | PASS |
Dave Hannah
|
|
|
Late afternoon - John Phone #: ###-####
|
BLD-Wall cover | 3/15/2018 | 3/16/2018 | 3/17/2018 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/7/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/7/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/7/2018 | | DONE |
|
|
|
|
Plan assigned to (RMH) | 1/31/2018 | 1/31/2018 | 2/1/2018 | | PASS |
Ron Hill
|
|
|
2/06 L2 Backcountry ePlan*
|
1st review completed | | | 2/1/2018 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/1/2018 | | DONE |
Christina Prado
|
|
|
Need
GC form - met
Cert of Value - met
|
Routing - PLAN CHECK | 1/24/2018 | | 2/1/2018 | | PASS |
Javier Guzman
|
|
|
|
Plan assigned to (JG) | 1/24/2018 | 1/24/2018 | 1/31/2018 | | DEFR |
Javier Guzman
|
|
|
2/06 L2 Backcountry ePlan*
|
Routing - FIRE | 1/24/2018 | 1/24/2018 | 1/30/2018 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
Routing - Addressing | 1/24/2018 | | 1/26/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/24/2018 | | 1/24/2018 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 1/24/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 1/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 22 2018 8:05AM
|
Intake Approval | | | 1/22/2018 | | FAIL |
Rob Patrick
|
|
|
BLD18-00225
1-22-18 Please Provide the Following:
1. Page No.s on Checklist don't match dwgs submitted for requested information.
2. Keynote callouts at not represented accurately on details.
3. Plumbing Plan required for re-located bathroom.
Thank You
Rob Patrick
|