Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD18-00227
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 3447 S PHEASANT TAIL WAY
Project Namehc 61-1 Payette
Customer Number 
ePlanReviewYes
Description
*** WUI ZONE B REQUIREMENTS* Permit for the construction of a new 2387 sq. ft., two story (first story 1032 sq. ft., second story 1355 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately 8 sq. ft. of covered patio/porch and a 482 sq. ft. attached garage per the approved plans and any notations. SP-01 zoning and setbacks per planning.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/27/20188/28/20188/28/2018APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
DOC - Permit Finaled8/28/20188/28/20188/28/2018PPASS
DetailsBrandon Shaw
BLD-Energy code compliance6/19/20186/19/20186/19/2018PPASS
DetailsBrandon Shaw
BLD-Framing/Rough-in6/19/20186/19/20186/19/2018PCANC
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kyle Seick
BLD-Framing/Rough-in6/15/20186/15/20186/15/2018PPASS
DetailsBrandon Shaw
OK to insulate
BLD-Wall Bracing6/5/20186/6/20186/6/2018APASS
DetailsBrandon Shaw
Work in progress
BLD-Foundation4/16/20184/16/20184/16/2018PPASS
DetailsBrandon Shaw
Work in progress
BLD-Footing4/12/20184/12/20184/13/2018PPASS
DetailsBrandon Shaw
Work in progress
Issue PAID IN FULL permit  2/5/2018 DONE
Inspection Record Card- Bld  2/5/2018 DONE
OVERRIDE  2/2/2018  
Routing - MECHANICAL2/2/2018 2/2/2018 PASS
DetailsTroy James
1st review completed  2/2/2018 DONE
DetailsMichael Hanson
PLANS/APPL TAKEN TO FRONT DESK  2/2/2018 DONE
DetailsMichael Hanson
Permit Ready to Issue  2/2/2018 DONE
Plan assigned to (M_H)1/22/2018 2/2/2018 DONE
DetailsMichael Hanson
02/02 sfd L1 ePlan - Plan Check completed pending mechanical 1-26-2018 MDH Failed mechanical waiting response. 1-29-2018 MDH
Routing - PLAN CHECK1/22/2018 2/2/2018 PASS
DetailsMichael Hanson
Routing - PLANNING1/22/2018 2/2/2018 PASS
DetailsSue Cummings
per ePlan approval
Routing - MECHANICAL1/22/2018 1/29/2018 FAIL
DetailsTroy James
emailed correction to manual j designer
Plan Reviewer's activity  1/26/2018 DONE
DetailsMichael Hanson
Route to Impact Fee Review1/22/20181/25/20181/23/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Application received  1/22/2018 DONE
Application submitted via PDS Online on Jan 22 2018 8:31AM
Intake Approval  1/22/2018 FAIL
DetailsChristina Prado
Font color on electrical sheet must be corrected prior to acceptance
Plans ACCEPTED BY PLAN TECH  1/22/2018 DONE
Recd Pcfee & Taken To Pln CK  1/22/2018 DONE
Intake Approval  1/22/2018 PASS
Routing - Addressing1/22/2018 1/22/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS1/22/2018 1/22/2018 PASS
DetailsMorgan Webb