BLD-Final | 2/13/2018 | 2/14/2018 | 2/15/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Leonard
|
DOC - Permit Finaled | 2/14/2018 | 2/14/2018 | 2/14/2018 | P | PASS |
Tony Young
|
|
|
done
|
Issue PAID IN FULL permit | | | 1/25/2018 | | DONE |
|
|
|
|
Plan assigned to (RDP) | 1/22/2018 | 1/22/2018 | 1/24/2018 | | DONE |
Rob Patrick
|
|
|
1/26 Solar L2
|
Routing - PLAN CHECK | 1/24/2018 | | 1/24/2018 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 1/24/2018 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 1/24/2018 | | DONE |
|
|
|
|
Application received | | | 1/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 22 2018 3:41PM
|
Plan assigned to (JAB) Josh | 1/22/2018 | 1/22/2018 | 1/22/2018 | | DEFR |
Josh Bogle
|
|
|
|
Routing - PLANNING | 1/22/2018 | | 1/22/2018 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/22/2018 | | DONE |
|
|
|
|
Intake Approval | | | 1/22/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/22/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/22/2018 | | | | |
Josh Bogle
|
|
|
|